154,612 square metres employment space at Winwick Road, Newton-le-Willows, St Helens
Summary of planning committee decision
Decided by St Helens Planning Committee on 3 Feb 2026.
What was proposed
The hybrid application sought up to 154,612 square metres of employment floorspace, together with earthworks, roads, landscaping, drainage and access from the Parkside Link Road.
“The proposals comprise Phase 2 of the comprehensive redevelopment at Parkside West, delivering a significant quantum of employment floorspace. The application seeks planning permission for up to 154,612 m² (Gross Internal Area) of employment development, submitted as a hybrid planning application comprising both full and outline elements.”
“Site-wide earthworks and creation of two development platforms • Vehicular access and internal road network • Strategic landscaping, including ecological and noise mitigation • Sustainable drainage systems and associated infrastructure • Primary access from the Parkside Link Road (PLR)”
Officer report
The site and surroundings
The 48.42-hectare former colliery site lies east of Newton-le-Willows near railways, the M6, the A49 and protected trees, heritage assets and rural land.
“The site forms part of the former Parkside Colliery and extends to approximately 48.42 hectares. It is located to the east of Newton-le-Willows, circa 3 miles to the east of St Helens. The West Coast Mainline railway runs along the north western boundary of the site, while the Liverpool–Manchester railway (Chat Moss Line) lies to the north. Newton-le-Willows Rail Station is situated to the west/northwest, approximately 400 metres from the west site boundary.”
“P/2024/0419/HYEIA development area, with land beyond designated as a Registered Battlefield associated with the Battle of Winwick. Newton Park Farm, which includes two Grade II Listed Buildings (Newton Park Farmhouse and the adjacent barn), lies within the wider former Parkside Colliery site.”
Officer report
Earlier permissions
Earlier permissions covered Phase 1 employment development, the Parkside Link Road, infrastructure and reserved matters, with some highway conditions later removed.
“P/2018/0048/OUP - Outline application (all matters reserved except for access) for the construction of up to 92,900 m2 of employment floorspace (Use Class B8 with ancillary B1(a)) and associated servicing and infrastructure including car parking; vehicle and pedestrian circulation space; alteration of existing access road including works to existing A49 junction; noise mitigation; earthworks to create development platforms and bunds; landscaping including buffers; works to…”
“P/2023/0342/RES - Reserved Matters Application seeking Access and Landscaping for enabling and infrastructure works to facilitate employment development comprising site wide earthworks to create development platforms, details of strategic landscaping (off plot), including bunds, planting, ecological mitigation, drainage and ground works, upgrades to existing substation and details of spine road access and Parkside Link Road (PLR) pursuant to outline planning permission…”
Officer report
What officers recommended
Officers recommended permission because the site is allocated for strategic employment and the proposal’s economic, social and environmental benefits outweigh identified harm, subject to safeguards.
“The application site forms part of the allocated Strategic Employment Site of Parkside West and aligns with the St Helens Local Plan’s vision for transformational economic growth. The proposal would deliver a significant quantum of B2 and B8 floorspace in a highly accessible location adjacent to the strategic highway network, contributing meaningfully to the Borough’s employment land supply.”
“The proposal is considered to be fully compliant with the St Helens Borough Local Plan and the National Planning Policy Framework, subject to resolution of the updated planting plans and BNG information, with authority delegated to the Head of Planning Services on these matters.”
Officer report
Concerns from residents
Five representations raised concerns about pollution, noise, dust, traffic, amenity, ecology, consultation, energy, connectivity, employment and cumulative impacts.
“P/2024/0419/HYEIA 4.2 5 representations (including Tritax Big Box) were received as part of the consultation process, which raised the following concerns (in summary): • Concerns over air pollution and deteriorating local air quality, with some residents attributing health conditions to emissions from Phase 1. • Objections to noise, dust, and general disturbance, both from construction activity and HGV operations associated with the development.”
“Concerns that historic buildings (barns) on the site are unacknowledged and unprotected in the application. • Scepticism over the claimed economic and employment benefits. • Overreliance on B8 logistics uses, leading to low density employment, limited high skilled jobs, and vulnerability to automation. • Absence of a robust energy strategy, with concerns that solar provision may again be minimal.”
Officer report
Who spoke
The committee heard from a local resident, a councillor and the applicant’s agent after the principal planning officer presented the application.
The committee’s decision
The committee granted permission subject to conditions, a legal agreement and updated landscaping and biodiversity information removing planting from the safeguarded rail area.
“Grant permission subject to the listed conditions, with authority delegated to the Head of Planning Services to add, amend or remove conditions as they deem appropriate and to issue the decision once a legal agreement as detailed below is completed to secure the contributions detailed in the report and once updated landscaping plans and Biodiversity Net Gain (BNG) information has been satisfactorily received to remove the planting and onsite habitat improvements from the…”
“The legal agreement was to secure a financial contribution of at least £6,054,190 (plus monitoring fee) as detailed below:”
Minutes
Councillors at the meeting
- Derek LongChairLabour
- David BanksLabour
- Andy BowdenLabour
- John CaseConservative
- Karl CollierIndependent
- Tracy DickinsonLabour
- John HodkinsonLabour
- Keith LairdLabour
- Richard McCauleyLabour
- Geoff PearlLib Dem
- Lisa PrestonLabour
- James TaskerIndependent
Apologies Susan Murphy Labour
Absent David Hawley Reform UK
Source: Plota analysis of the council's minutes; parties from the council's list of councillors.
Sources
- St Helens Planning Committee minutes, 3 February 2026
- Agenda and papers (council website)
Source: Plota analysis of St Helens's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Committee
- St Helens Planning Committee
- Council
- St Helens
- Date
- Tuesday 3 February 2026
- Recommendation
- Officers recommended approval
- Committee decided
- Approved
- Councillors
- 12Labour 8Conservative 1Independent 1Lib Dem 1Independent 1Show councillors
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- The application (council website)
- All decisions
- St Helens committee decisions →
This committee's year
24 decisions in the 12 months to this meeting.
Source: Plota analysis of the committee's minutes.