Electricity substation at Land 1.6km Southeast Of Redshaw B7078 From Millbank A70 To Abington Int A702 Douglas Lanark

Summary of planning committee decision

Decided by South Lanarkshire Planning Committee on 16 Sept 2025.

P/25/0662Approved

What was proposed

The application proposed a 400kV/132kV electricity substation, buildings, transformers, access, roads, fencing, drainage, landscaping and construction areas.

“A new 400kV Gas Insulated Switchgear substation building (approximately 91m x 30m x 12m) • A new 132kV Gas Insulated Switchgear building (approximately 56m x 17.5m x 10.8m) • A small distribution Grid Supply Point substation building • External grid transformers • A new permanent access track from the B7078 to the substation compound • Internal access roads and parking • Security fence around the live compound • Drainage works • Landscape works • Temporary construction…”

“Access to the proposed development would be via a new vehicular access off the B7078, and it is envisaged that the construction of the proposed development would take up to six years, starting in November 2025 until October 2031.”

Officer report

The site

The 20.65-hectare site is open moorland and rough grassland between the B7078 and M74, near an existing overhead power line.

“Site Description 2.1 The site is located in close proximity to the existing 400kV overhead power line route at Redshaw and sits between the B7078 and the M74, approximately 3.5km southeast of Douglas, and occupies an area of approximately 20.65ha.”

“The landcover within the site consists mainly of open moorland and rough grassland and the nearest residential property to the site is a property at Redshaw, which lies some 1.4km to the northwest.”

Officer report

Planning history

There was no relevant planning history, and supporting documents included an environmental impact assessment and transport information.

“Supporting Information 5.1. The applicants have submitted several supporting documents with the application as set out below:-”

“Environmental Impact Assessment Report • Construction Traffic Management Plan • Design and Access Statement • Ecological Appraisal Report…”

Officer report

What officers recommended

Officers recommended permission because the development accorded with national and local policies and would reinforce the transmission network for renewable energy and net zero.

“Policy 1 of NPF4 affords significant weight to the global climate and nature crisis when assessing the acceptability of all development decisions. The proposed development will assist in reinforcing the existing transmission network which in turn will support greenhouse gas reductions by enabling new renewable energy developments to connect to the transmission network.”

“In addition to this, the proposed development is afforded National Development status under the terms of NPF4 and, as such, benefits from high level support in terms of the role that it will play in the reinforcement of the national transmission network, thus facilitating the delivery of renewable energy and assisting in the delivery of Scotland energy transition to Net Zero.”

Officer report

Environmental effects

Officers considered the landscape and visual effects localised, with appropriate mitigation, and identified no concerns under the renewable energy assessment checklist.

“Significant residual environmental effects have been identified for a small number of landscape and visual receptors, these being assessed as being very localised in nature. At part (e)(ii), Policy 11 advises that “Where impacts are localised and/or appropriate design mitigation has been applied, they will generally be considered acceptable.”

“The proposed development has demonstrated an appropriate alignment with regards to landscape and visual impacts, including the provision of appropriate landscape mitigation, SUDs and biodiversity enhancement and on balance is considered to be compliant with the relevant LDP policies.”

Officer report

Consultation responses

Archaeology, roads and transport consultees offered no objection subject to conditions.

“Consultations 6.1 West of Scotland Archaeology Service (WoSAS) – offered no objection to the proposed development subject to conditions. Response: Noted.”

“Roads Development Management Team – offered no objection to the proposed development subject to conditions. Response: Noted.”

Officer report

Public representations

No representations were submitted about the proposed development.

“Representations 7.1 No representations have been submitted in respect of the proposed development.”

Officer report

The committee decision

The committee granted planning permission subject to the conditions specified in the officer report.

“P/25/0662 for Construction of 400kV/132kV Electricity Sub-Station and Associated Supporting Infrastructure at Land 1.6km Southeast of Redshaw, B7078 from Millburn to Abington A report dated 8 September 2025 by the Executive Director (Community and Enterprise Resources) was submitted on planning application P/25/0662 by [the applicant] (SPEN) for the construction of a 400kV/132kV electricity sub-station and associated supporting infrastructure at land 1.6km…”

“The Committee decided: that planning application P/25/0662 by [the applicant] (SPEN) for the construction of a 400kV/132kV electricity sub-station and associated supporting infrastructure at land 1.6km southeast of Redshaw, B7078 from Millburn to Abington be granted subject to the conditions specified in the Executive Director’s report.”

Minutes

Sources

  • South Lanarkshire Planning Committee minutes, 16 September 2025
  • Agenda and papers (council website)

Source: Plota analysis of South Lanarkshire's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Date
Tuesday 16 September 2025
Recommendation
Officers recommended approval
Committee decided
Approved
Minutes
The council's minutes
Meeting
Agenda and papers (council website)
Application
The application (council website)

This committee's year

6 decisions in the 12 months to this meeting.

Source: Plota analysis of the committee's minutes.

Every decision by this council's committees →