Estate operations complex at Land 600 Metres North East Of Sealtainn Bolfracks, Aberfeldy

Summary of planning committee decision

Decided by Perth Planning and Placemaking Committee on 9 Sept 2026.

24/01616/FLMApproved

What was proposed

The application proposed an operations complex with welfare, office, laundry and workshop buildings, access changes, roads, parking and associated works.

“Proposal: Formation of operations complex comprising erection of welfare buildings, office building, laundry facilities, workshop, alterations to existing access, formation of roads, parking areas and associated works…”

Officer report

Why officers supported it

Officers considered the development essential estate infrastructure, supported rural business and employment, and acceptable because its localised impacts could be mitigated.

“137 The proposed Back of House Operations Village is considered to constitute essential operational infrastructure required to support the long-term management and operation of the evolving Taymouth Castle Estate. The development has a clear functional relationship with an established rural enterprise and is supported in principle by LDP Policy 8 and NPF4 Policy 29.”

“141 On balance, it is considered that the operational and economic benefits of the development outweigh the identified localised impacts, which can be appropriately mitigated. Subject to the recommended conditions, the proposal is considered to accord with the relevant policies of the Perth and Kinross Local Development Plan 2019 and National Planning Framework 4. Accordingly, the application is recommended for approval.”

Officer report

What consultees said

consultees generally raised no objection, while recommending conditions covering archaeology, drainage, ecology, noise, transport, trees and construction impacts.

“32 Environmental Health (Noise Odour) - No objection. Advise the submitted Noise Impact Assessment and Air Quality Impact Assessment are accepted and conclude that operational noise, traffic and air quality impacts would not be significant. Recommend conditions relating to operating hours for the workshop and vehicle wash bay, noise limits for plant and equipment, external lighting, construction hours, dust management and controls on vehicle idling.”

“33 Transportation and Development - No objection, subject to conditions. Advise satisfaction with the proposed access arrangements, parking provision, internal road layout and transport assessment, but recommend conditions relating to access construction, visibility splays, a Construction Traffic Management Plan, bus stop infrastructure, covered cycle parking, a Green Travel Plan, and servicing arrangements for the wastewater treatment plant.”

Officer report

What residents raised

Five objections concerned traffic, road safety, landscape, noise, ecology, flooding, trees, lighting, waste, tourism and the River Tay SAC.

“38 5 objections have been received, a summary of the issues are:”

“Traffic generation and impact • Road Safety • Contrary to Development Plan • Alternative sites preferable • Timing ang and hours of operation • Noise and residential amenity impact • “Salami” slicing of site • Impact on tourism • Waste management • Impact on River Tay Special Area of Conservation • Lighting impact • Out of character with area • Over intensive development • Lack of Environmental Impact Assessment • Flood Risk • Loss of trees • Loss of open space • Impact on…”

Officer report

Who spoke

The agent answered members’ questions.

The decision

“Resolved: Grant, subject to the following terms, conditions and informatives: Conditions 1. This planning permission will last only for three years from the date of this decision notice, unless the development has been lawfully started within that period. Reason - This is a Planning Permission in terms of Section 58 of the Town and Country Planning (Scotland) Act 1997, as amended by Section 32 of the Planning (Scotland) Act 2019. 2. The detailed landscaping and planting scheme hereby approved shall be implemented on a phased basis. Prior to the commencement of any development details of the phasing and timetable for the implementation of the landscaping and planting scheme shall be submitted to and approved in writing by the Planning Authority. The phasing and timetable shall accord with the Phasing and Implementation Plan required by Condition 27 of this permission.”

Minutes, 9 Sept 2026

Councillors at the meeting

The minutes record this decision with no vote against, so each member present for this item is shown as voting for it.

Apologies Dave Cuthbert Independent, Ken Harvey SNP, Richard Watters SNP

Source: Plota analysis of the council's minutes; parties from Democracy Club.

Sources

  • Perth Planning and Placemaking Committee minutes, 9 September 2026
  • Agenda and papers (council website)

Source: Plota analysis of Perth's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Council
Perth
Date
Wednesday 9 September 2026
Recommendation
Officers recommended approval
Committee decided
Approved
Councillors
9SNP 5Conservative 4Show votes
Minutes
The council's minutes
Meeting
Agenda and papers (council website)
Application
The application (council website)

This committee's year

61 decisions in the 12 months to this meeting, 6 against officer advice.

Source: Plota analysis of the committee's minutes.

Every decision by this council's committees →