49.9 MW solar farm at Kinnon Park Farm, Methven, Perth
Summary of planning committee decision
Decided by Perth Planning and Placemaking Committee on 13 May 2026.
What was proposed
The application proposed a 49.9 MW solar farm and battery storage system with panels, substations, fencing, CCTV, tracks and related works.
“Proposal: Formation of a 49.9 MW solar farm and battery energy storage system comprising of ground mounted solar arrays, inverters, transformers, a substation, a DNO substation, security fencing, CCTV cameras, cabling, access tracks and associated works…”
“Arrays of ground mounted solar panels. Panels will have mountings up to 3m high, fixed south facing. The panels will be located in rows or strings to provide a coherent and simple layout. 232 inverters and 20 transformers will be positioned around the solar farm to allow conversion of energy into electrical current suitable for feeding into the grid.”
Officer report
The site and its surroundings
The site is agricultural land at Kinnon Park Farm, south-west of Methven, with the East Pow along its southern boundary and access from the U47.
“The proposed development is located at Kinnon Park Farm lying 700m to the south-west of the settlement of Methven, on the A85 and lying 3.5km west of the city of Perth. Kinnon Park Farm steading comprises several vacant buildings and fields which have been in agricultural use.”
“The existing use of Kinnon Park Farm is agricultural arable land, mostly planted in crop for grain. The group of buildings that form the farmstead complex are located within the Site. However, none of the ancillary structures will be used as a site compound, but the Site compound will be located next to them. The fields are delineated by a combination of mixed shelter belts, hedgerows with individual trees with evident gaps.”
Officer report
Earlier applications and consultation
Earlier proposals included housing and a golf course, while this solar project followed a proposal notice and screening application submitted in 2023.
“An EIA screening has been undertaken. The proposal being a Schedule 2 development in terms of the Town and Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2017. In the case of these regulations, prohibition is given to the granting of planning permission to “EIA development” unless an environmental impact assessment has been undertaken.”
“A Pre-Application Consultation (PAC) Report has been submitted with the planning application. A Proposal of Application Notice (PAN) was submitted to Perth and Kinross Council on the 9th August 2023. The PAN sets out the consultation strategy which includes the arrangement of two in-person consultation events, which were held two weeks apart from each other.”
Officer report
What officers recommended
Officers recommended refusal because the proposal conflicted with the Development Plan and no material consideration outweighed that conflict.
“To conclude, the application must be determined in accordance with the Development Plan unless material considerations indicate otherwise. In this respect, the proposal is considered to be contrary to the Development Plan. Account has been taken account of the relevant material considerations, and none has been found that would justify overriding the Development Plan. Accordingly, the proposal is recommended for refusal on the grounds identified below. . Recommendation…”
“The development, owing to its size, scale, appearance and location, raises significant landscape character and visual impact concerns, failing to contribute positively to the quality of the surrounding built and natural environment.”
Officer report
What consultees said
Most consultees raised no objection, although National Gas Transmissions submitted a holding objection and several bodies sought conditions.
“National Gas Transmissions (NGT) - Given that NGT operates a high-pressure gas pipeline that runs through the proposed development site, a holding objection…”
Officer report
What people said
There were 320 representations, with objections focused on visual effects, policy conflict, flooding, traffic, noise, light, land use and biodiversity.
“The proposed development will result in an adverse effect on visual amenity • The proposed development is contrary to Local Development Plan Policy • The proposed development will result in an adverse impact on employment provision • The proposals are excessive in terms of height • The proposed development will result in a flood risk • The proposed development will result in an inappropriate land use • The proposed development will result in a loss of open space • There is…”
Officer report
Who spoke at the meeting
An objector, the local member, the agent and a supporter addressed the committee; the objector, agent and supporter answered questions.
The committee’s decision
The committee resolved to refuse the application for the stated landscape, energy mitigation and prime agricultural land reasons.
“Resolved: Refuse, for the following reasons:”
“Reasons 1. The development, owing to its size, scale, appearance and location, raises significant landscape character and visual impact concerns, failing to contribute positively to the quality of the surrounding built and natural environment.”
Minutes
Why it was refused
The proposal was not in accordance with the Development Plan, and no material reasons justified departing from it.
“Justification The proposal is not in accordance with the Development Plan and there are no material reasons which justify departing from the Development Plan.”
Minutes
The members' reasons
The resolution gives these reasons:
Minutes
- The development, owing to inadequate mitigation in seeking to offset landscape concerns raised, fails to comply with Policy 11(e)(ii) ‘Energy’, of the National Planning Framework 4 (2023).
- The development negatively impacts upon soils and the loss of prime agricultural
Source: the council's minutes, quoted word for word.
Sources
- Perth Planning and Placemaking Committee minutes, 13 May 2026
- Agenda and papers (council website)
Source: Plota analysis of Perth's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Council
- Perth
- Date
- Wednesday 13 May 2026
- Recommendation
- Officers recommended refusal
- Committee decided
- Refused
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- The application (council website)
- All decisions
- Perth committee decisions →
This committee's year
39 decisions in the 12 months to this meeting, 1 against officer advice.