Land remediation works at Robberhall Road, Motherwell

Summary of planning committee decision

Decided by North Lanarkshire Planning Committee on 4 Dec 2025.

24/01267/FULApproved

What was proposed

The application sought 14-year permission to extract, process and remove waste materials, then remediate and restore the Meadowhead and TC1-3 sites.

“1) Stage 1 - extraction, crushing, screening and removal of waste material (i.e. inert soil and stones). This process involves the excavation of waste material to a depth of 4m in each cell, where at the point of extraction the material will then be loaded onto a mobile crusher or mobile screener by an excavator and processed. All waste materials will be imported to raise site levels within the site and will be placed within the cells as engineered fill.”

“2) Stage 2 - remediation and reinstatement of each cell. Following extraction, reinstatement and restoration with clean soils will be undertaken across the site. TC1-3 will be treated in Phase 1 and Meadowhead will be treated in two separate phases (Phase 1 and 2). Each cell within Meadowhead and TC1-3 will be restored before work commences on the next cell. Imported soils will be spread and rolled in 1m layers in strips following the pattern of extraction.”

Officer report

What officers recommended

Officers recommended approval because the works would address contaminated brownfield land and support future redevelopment without significant effects, subject to conditions.

“The proposed development seeks to manage the legacy of contaminated land on two large parcels of land within the former Ravenscraig steelworks site. Remediation will take place over a period of 14 years and will involve extraction, crushing, screening and removal of inert material to use as engineered fill followed by the spreading of clean soils across each site.”

“Subject to appropriate conditions, the proposed remediation works are considered to comply with the Development Plan and can be carried out without significant effects on ecology, air quality, the water environment, the road network and residential amenity. Accordingly, it is recommended that the application is approved subject to the conditions detailed in this repor…”

Officer report

Consultation responses

Council services and external bodies raised no objections, subject to conditions covering ecology, trees, pollution, noise, contamination, roads, drainage, waste and coal mining risks.

“NLC Protective Services (ENV H Noise) has no objection to the proposed development subject to conditions relating to noise limits and the protection of amenity of noise sensitive receptors, hours of operation and noise monitoring.”

“Coal Mining Remediation Authority has no objection to the proposed development subject to conditions to ensure submission of a scheme of intrusive site investigations and where necessary remediation works and/or mitigation measures to address land instability arising from coal mining legacy followed by a declaration prepared by a suitably competent person confirming that the site is, or has been made, safe and stable for future development.”

Officer report

Public representations

No letters of representation were received about the application.

“No letters of representation have been received.”

Officer report

The committee’s decision

The committee granted planning permission for the proposed extraction and remediation works.

“24/01267/FUL Applicant: Ravenscraig Ltd Development/Locus: Extraction of Contaminated Materials and Remediation of Ground at Sites known as Meadowhead and TC1-3 Ravenscraig Masterplan Area Land to the South of Ravenscraig Park, Robberhall Road, Motherwell Decision: Grant…”

Minutes

Sources

  • North Lanarkshire Planning Committee minutes, 4 December 2025
  • Agenda and papers (council website)

Source: Plota analysis of North Lanarkshire's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Date
Thursday 4 December 2025
Recommendation
Officers recommended approval
Committee decided
Approved
Minutes
The council's minutes
Meeting
Agenda and papers (council website)
Application
The application (council website)

This committee's year

12 decisions in the 12 months to this meeting.

Source: Plota analysis of the committee's minutes.

Every decision by this council's committees →