14 apartments at 49 - 51 Collingdon Street, Luton

Summary of planning committee decision

Decided by Luton Development Management Committee on 15 Dec 2025.

25/00378/FULApproved

What was proposed

The application proposed a six-storey residential building with set-back upper floors, amenity spaces and 14 apartments: four one-bedroom and ten two-bedroom homes.

“Item No: Committee: Development Management Date of Meeting: December 2025 Application Ref: 25/00378/FUL Subject: Erection of a six storey residential development with set-back upper storeys and associated amenity spaces, comprising of 14 apartments; four No. 1 bed and ten No. 2 bed Address: 49 - 51 Collingdon Street, Luton.”

Officer report

The site and surroundings

The vacant 420-square-metre town-centre site was in a Category A employment area, between residential, office, health-centre and commercial uses.

“Background: The Site and Surroundings 3. The site is located at number 49 – 51 Collingdon Street, at the western end of the street and located in the North-Western corner of the Town Centre (as defined by the Luton Local Plan policy map) not far from the Telford Way Roundabout and pedestrian crossing bridges, accessed via a footway at the western end of the street.”

“The site comprises an area of approximately 420 sq m and is located within the Town Centre in an allocated Category A Key Employment Area (as shown in the town centre policy map extract below). Category A Key Employment Areas are described in the LLP N”

Officer report

Earlier site history

The former two-storey workshop was approved for demolition in 2024 and had been demolished before this application.

“To the immediate North of the site is the four-storey office and red brick built building ‘Clody House’ housing various commercial businesses, along with a Pentecostal Church. Further to the East and adjacent to Clody House is another existing office building known as Hamilton House, another four-storey red brick office building.”

“Site History 9. 24/01115/DOC - Request for Prior Approval - Demolition of the existing building. Discharge of condition 3 (Demolition Method Statement) of Planning permission 24/00835/PRIORD dated 20th August 2024. 10. 24/00835/PRIORD – Request for Prior Approval: Demolition of the Existing Building. 11. 85/00287/TEMP - Continued use of First Floor of Hat Factory as office accommodation. 12.”

Officer report

Consultees and residents

Technical consultees generally raised conditions or contributions; the flood authority initially objected over drainage information, and no public representations were received.

“Consultation Responses Technical Consultation 24. The application was notified to several technical consultees and no significant issues have been raised towards the development, in some cases following the receipt of additional information. Conditions have been recommended and, where appropriate and reasonable, these have been incorporated into the conditions as set out at ‘Appendix A’ and summarised above.”

Officer report

Committee discussion

Members discussed the application before the Chair moved the officer recommendation to approve it with updated conditions.

“Following discussions, comments and statements by Members of the Committee, the Chair moved the Officer’s recommendation to approve the application, as set out in the report and the updated conditions previously circulated. The recommendation as moved by the Chair was seconded and Members voted in support of the application.”

Minutes

The decision

Planning permission was granted subject to resolving the flood authority’s objection, conditions and a legal agreement including a highways contribution, local labour and a viability review.

“(iv) That planning permission be granted subject to the satisfactory completion of a legal agreement (or appropriate mechanism) which will include inter-alia the following heads of terms.”

“⋅ Highways Contribution (£4.5k); ⋅ The provision of local goods, services and labour; ⋅ A viability review clause so the council would benefit from any improvement in the viability of the scheme with any uplift to be provided towards affordable housing; and ⋅ A legal agreement monitoring fee of £10,000”

Minutes

Sources

  • Luton Development Management Committee minutes, 15 December 2025
  • Agenda and papers (council website)

Source: Plota analysis of Luton's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Council
Luton
Date
Monday 15 December 2025
Recommendation
Officers recommended approval
Committee decided
Approved
Minutes
The council's minutes
Meeting
Agenda and papers (council website)
Application
The application (council website)

This committee's year

6 decisions in the 12 months to this meeting.

Source: Plota analysis of the committee's minutes.

Every decision by this council's committees →