Greenway lighting and resurfacing at Foyle Valley Greenway, Londonderry

Summary of planning committee decision

Decided by Derry And Strabane Planning Committee on 3 Sept 2025.

LA11/2024/0909/FApproved

The site and surroundings

The site is an existing greenway, grassland and open-space corridor beside the River Foyle, near residential areas, parks and sports pitches.

“Site and Surrounding Area The application site comprises an existing greenway path and parcels of grassland located along the Foyle Valley Greenway, which extends in a linear fashion from the Craigavon Bridge towards the Settlement limit of Derry City, an area of formal open space as identified in Map 3 of the Derry Area Plan (DAP) . A portion of the site also lies within the Primary Retail Core and Central Area.”

“Site Constraints Area of Existing Recreation and Open Space Proximity to a Listed Building (HB01/19/095) Craigavon Bridge Potential Impact upon Natural Heritage features Within the Primary Retail Core & Central Area…”

Officer report

What officers recommended

Officers recommended approval, considering the project acceptable in principle and beneficial for greenway safety, access and public use.

“Given that the application lies within an urban area and the proposed works are taking place along an existing greenway and area of zoned recreational/ open space, it is considered that the proposed works will improve and enhance safety along this greenway, and as such the proposal is considered to be acceptable in principle, subject to all other planning and material considerations being met.”

Officer report

Responses from consultees

The consultees raised no objections, subject in some cases to conditions, informatives, mitigation or an updated environmental assessment.

“Environmental Health – No objections subject to informatives…”

“NIEA – NED – No objections subject to informatives/conditions…”

Officer report

What people said

One neighbour’s letter supported improved safety and accessibility and the renewal of a neglected area.

“Neighbour Notifications/ Representations One hundred and forty-one ( 141) neighbouring properties were notified and one (1) letter of representation has been received from one (1) neighbour.”

“The following is a summary of the items raised in the letters of support: -Support that proposal will improve safety and accessibility - Support that proposal will rejuvenate neglected area…”

Officer report

Who spoke

The Senior Planning Officer presented the application, and Councillor Jackson proposed supporting the recommendation with the Chair seconding it.

Conditions attached

The conditions covered the implementation period, a final construction environmental management plan, retained vegetation and compliance with approved drawings.

“Proposed Conditions 1. The development hereby permitted shall be begun before the expiration of 5 years from the date of this permission. Reason: As required by Section 61 of the Planning Act (Northern Ireland) 2011. Prior to works commencing, a final Construction Environmental Management Plan (CEMP) must be submitted by the appointed contractor and agreed by the Council and NIEA WMU.”

“The existing vegetation along the site boundaries as indicated as retained on approved plan Drawing No.02 (received 5 th December 2024) shall be retained at a minimum height of 1.5 metres for hedging/shrubs and 4 metres for trees and shall be allowed to grow. Reason: To ensure the maintenance of screening to the site.”

Officer report

The decision

“Resolved to support the Officer recommendation to approve application LA11/2024/0909/F, subject to conditions as outlined within the report. P120/25 Supplementary Planning Guidance (SPG) documents to accompany LDP Plan Strategy - Tranche 3 The Principal Planning Officer presented the above report, a copy of which was previously circulated to Members. The purpose of the report was to introduce the third Tranche of draft Supplementary Planning Guidance (SPG) documents to support the recently adopted LDP Plan Strategy. Members are asked for any initial input and then for agreement for these three SPG documents to be issued for public consultation. This process is similar to that for Tranche 1 and Tranche 2 draft SPG documents that were agreed at the June and July meetings of the Planning Committee, which are currently out for consultation. The Head of Planning assured Co”

Minutes, 3 Sept 2025

Councillors at the meeting

Source: Plota analysis of the council's minutes; parties from the council's list of councillors.

Sources

  • Derry And Strabane Planning Committee minutes, 3 September 2025
  • Agenda and papers (council website)

Source: Plota analysis of Derry And Strabane's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Date
Wednesday 3 September 2025
Recommendation
Officers recommended approval
Committee decided
Approved
Vote
Unanimous
Councillors
11Sinn Féin 6SDLP 2DUP 1Independent 1UUP 1Show councillors
Minutes
The council's minutes
Meeting
Agenda and papers (council website)
Application
The application (council website)

This committee's year

11 decisions in the 12 months to this meeting, 4 against officer advice.

Source: Plota analysis of the committee's minutes.

Every decision by this council's committees →