4 apartments at 65 & 65a Beach Road, Portballintrae
Summary of planning committee decision
Decided by Causeway And Glens Planning Committee on 25 Mar 2026.
No officer report was published for this decision; this summary is from the committee minutes.
4 new apartments
The application proposed demolishing an existing dwelling and building 4 apartments, with new access, parking, storage sheds and a bin store.
“Objection Application to be determined by Planning Committee App No: LA01/2024/0699/F App Type: Full Proposal: Demolition and erection of 4 no apartments, improvements to existing access and new site access, parking provision, and all ancillary works including 4 no. storage sheds and bin store.”
“LA01/2024/0699/F is a full application for the demolition and erection of 4 no apartments, improvements to existing access and new site access, parking provision and all ancillary works including bin store.”
Minutes
A seafront site in an AONB
The site is within the settlement limit and an Area of Outstanding Natural Beauty, currently a semi-detached dwelling with a yard and amenity space.
“(Slide 2 - SLP) The site, as outlined in red, is located within the settlement development limit for Portballintrae, and within the Causeway Coast Area of Outstanding Natural Beauty. The site is adjacent to the Bay Local Landscape Policy Area as identified in the Northern Area Plan 2016. The site is located at 65 & 65a Beach Road and currently comprises an existing semi-detached dwelling with informal yard and amenity space to the rear.”
Minutes
Officers recommended approval
Officers said the design, scale and massing were acceptable, overlooking and overshadowing would not be unacceptable, and parking was an improvement on the existing site.
“To the rear of the proposal development comprises a 3 storey rear return which drops down to 2 storeys. It is assessed that this can be provided without undue impact to surrounding visual or residential amenity. The scale and massing are considered acceptable given the existing arrangement of the rear returns on neighbouring sites and the orientation of the sites, with the rears facing south.”
“Proposed materials and finishes are considered acceptable. Adequate communal and private amenity space is provided for all 4 apartments. The ground floor apartment to the front, Apartment 2, has an enclosed area to the front which provides amenity and in curtilage parking. Further incurtilage parking for 3 cars is provided to the rear of the site. Objections raised the issue of parking, and the proposed access arrangements at the front of the site.”
Minutes
A water company objection
The water authority recommended refusal over sewage capacity, but conditions were recommended to require the applicant to address this.
“With the exception of NI Water, there have been no objections raised by Consultees. Objectors had raised the issue of foul sewage and the impact of the load on the sewer system. NI Water have recommended refusal subject to the applicant engaging with NI Water. Negative conditions are recommended to address this to ensure that an adequate means of sewage disposal is provided and to ensure protection of the aquatic environment.”
Minutes
An objector raised design and parking concerns
An objector speaking for himself and neighbours said the development's scale did not match surrounding buildings and would cause overshadowing and parking and traffic problems.
“S McCullough stated that his speaking notes provide extensive details in objection to the application so he would provide a summary. S McCullough stated that he was speaking on behalf of himself and 3 of the neighbours. S McCullogh stated that the objection focuses on 3 main aspects of the proposal – visual impact on the street scape, rear return and carparking and traffic flow.”
“In response to questions about problems with parking S McCullough stated that there is currently space for parking at the rear and that this proposal sets out 3 parking spaces at the rear and 1 at the front. S McCullough stated that the Planning Department had previously stated that 3 apartments on this site would be better but have been convinced that 4 apartments can be accommodated.”
Minutes
Supporters backed the scheme
Two supporters said the development was modest and well-designed, met space standards, and asked members to approve it as officers recommended.
Committee voted to approve
The committee voted unanimously, 9 in favour and 0 against, to approve planning permission.
“Proposed by Councillor McGurk Seconded by Councillor C Archibald - That the Committee has taken into consideration and agrees with the reasons for the recommendation set out in section 9 and the policies and guidance in sections 7 and 8 and resolves to APPROVE planning permission as set out in section 10.”
“The Vice Chair put the motion to the Committee to vote. Members voted For; Members voted Against, 0 Members Abstained. The Vice Chair declared the motion carried and application approved…”
Minutes
Permission approved
The committee resolved to approve planning permission.
“RESOLVED - That the Committee has taken into consideration and agrees with the reasons for the recommendation set out in section 9 and the policies and guidance in sections 7 and 8 and resolves to APPROVE planning permission as set out in section 10.”
Minutes
Councillors at the meeting
- Michael CoyleSDLP
- Lee KaneAlliance
- Sandra HunterUUP
- Edgar ScottDUP
- Philip AndersonDUP
- Ciarán ArchibaldSinn Féin
- Bill KennedyDUP
- Kathleen McGurkSinn Féin
- Oliver McMullanSinn Féin
- McQuillan
- Mervyn StoreyDUP
- Russell WattonProgressive Unionist…
Proposed by Councillor Kathleen McGurk, seconded by Councillor Ciarán Archibald.
Source: Plota analysis of the council's minutes; parties from Democracy Club.
Sources
- Causeway And Glens Planning Committee minutes, 25 March 2026
- Agenda and papers (council website)
Source: Plota analysis of Causeway And Glens's committee minutes. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Council
- Causeway And Glens
- Date
- Wednesday 25 March 2026
- Recommendation
- Officers recommended approval
- Committee decided
- Approved
- Vote
- 9 for, 0 against
- Councillors
- 12DUP 4Sinn Féin 3Alliance 1Progressive Unionist… 1SDLP 1UUP 11 otherShow councillors
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- The application (council website)
- All decisions
- Causeway And Glens committee decisions →
Source: Plota analysis of the minutes.
This committee's year
48 decisions in the 12 months to this meeting, 3 against officer advice.
Source: Plota analysis of the committee's minutes.