Battery storage system at Land Off Illey Lane, Hunnington, Halesowen
Summary of planning committee decision
Decided by Bromsgrove Redditch Planning Committee on 9 Oct 2025.
What was proposed
The application sought a battery energy storage system with 60 battery units, power stations, a substation, fencing, landscaping and associated infrastructure.
“Full planning permission is sought for the erection of Battery Energy Storage System (BESS) to provide energy balancing services to the National Grid. The application proposes the erection of storage containers, support infrastructure and security fencing along with landscaping and associated works.”
“The battery units are laid out in 5 rows of 12 battery units, with 2 sets of power stations within each row. At the frontage of the battery storage facility has a substation, switchgear buildings and monitoring room/office. Of the 3.8ha application site the developable area of the site is around 1ha.”
Officer report
The site and surroundings
The site covered about 3.8 hectares of agricultural land, with development on about one hectare, access from Illey Lane and nearby heritage assets.
“The application site extends to approx. 3.8ha, lies to the south of Illey Lane and comprises agricultural land and encompasses several fields, with the proposed development situated towards the middle of the site area.”
“The site’s immediate surrounding area is considered to be rural and agricultural, it is screened and surrounded by dense vegetation, tall trees and situated away from the primary residential areas located along Bromsgrove Road (approx. 120m from the western site boundary to the nearest dwelling). Site access will be taken via an existing private gate along Illey Lane.”
Officer report
What residents said
Seventy-seven objections and one neutral comment raised concerns about Green Belt harm, cumulative effects, access, appearance, fire, flooding, noise, wildlife and agricultural land.
“Green Belt • Harm to openness and visual amenity • No very special circumstances • No need for the proposed development • Cumulative impact with other proposals…”
“Other matters • Battery fires, unsafe technology, decommissioning • Infrastructure upgrade to facilitate development • Impact on wildlife/biodiversity • Loss of agricultural land • Noise from BESS • Construction noise • Flooding/Drainage • No strategy to future BESS facilities • Proposed connection to Kitwell…”
Officer report
Who spoke
The committee heard from a local resident, the applicant’s planning agent, a parish council representative and the ward member.
The committee decision
Planning permission was granted subject to the conditions set out in the agenda, including conditions covering fire safety, access, drainage and emergency response.
“RESOLVED that Planning Permission be granted, subject to the Conditions as detailed on pages 77 - 85 of the main agenda pack.”
Minutes
The members' reasons
“However, if Members were of the opinion that the site was in the Green Belt there would still be grounds for granting planning permission under Very Special Circumstances as it satisfied the Government’s Renewable Energy Strategy, therefore making it a material planning consideration. • Location of access points within the site – Officers explained that there were two access points within the site to the battery storage areas.”
Minutes
Source: the council's minutes, quoted word for word.
Sources
- Bromsgrove Redditch Planning Committee minutes, 9 October 2025
- Agenda and papers (council website)
Source: Plota analysis of Bromsgrove Redditch's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Council
- Bromsgrove Redditch
- Date
- Thursday 9 October 2025
- Recommendation
- Officers recommended approval
- Committee decided
- Approved
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- The application (council website)
- All decisions
- Bromsgrove Redditch committee decisions →
This committee's year
6 decisions in the 12 months to this meeting.
Source: Plota analysis of the committee's minutes.