90m anemometer mast at Land at Pwll Yr Lwrch (1.7km to east of Maesteg and 3km west of Blaengarw) Maesteg

Summary of planning committee decision

Decided by Bridgend Development Control Committee on 2 Oct 2025.

P/25/41/FULApproved

What was proposed

A temporary 90-metre mast would collect wind data for up to three years before removal and restoration of the site.

“PROPOSAL: The installation of a 90m high anemometer mast for a temporary period of up to three years…”

“DESCRIPTION OF PROPOSED DEVELOPMENT Full Planning Permission is sought for the installation of a 90m high anemometer mast for a temporary period of up to three years after which time the mast would be removed and the site restored to its current condition.”

Officer report

The site and history

The mast would stand on grazed marshy upland grassland near forestry, with access using existing tracks; an earlier solar farm screening request was recorded.

“SITE DESCRIPTION The proposal is located on agricultural land located below Mynydd Pwll yr Lwrch (previously Mynydd Bach) a 425m high hill which is situated to the east of Nantyffyllon. Access to the site would be via public highway through Caerau and then Croeserw onto the gated Natural Resources Wales forestry and farm access track which runs from Bryn Coed.”

“The site comprises grazed marshy grassland located on an upland plateau and is enclosed by post and wire fencing. Land to the north and east contains significant areas of mature pine plantation forestry, known as Dunraven Forest.”

Officer report

Consultation responses

Highways, drainage, ecology, archaeology and Natural Resources Wales raised no objection or accepted mitigation, while the town council did not support the proposal.

“CONSULTATION RESPONSES Maesteg Town Council: It was advised that Members wished to not support the application ‘on the basis of it being a precursor to another wind farm which will encase the valley and continue to erode the surrounding environment both visually and mentally for the local residents.”

“Natural Resources Wales: Initially raised concerns with the lack of information regarding Ornithology. Following receipt of the Ornithology Technical Note, NRW advised they had no objection to the proposed development.”

Officer report

Objections received

Five residents objected over visual effects, ecology, birds, lighting, peat, aviation, construction, wellbeing and the possible cumulative impact of wind energy development.

“REPRESENTATIONS RECEIVED Five objections were received from residents of Cavan Row, Bank Street, Mill View Estate and Heol ty Gwyn, Maesteg and Wesley Street, Caerau. Concerns raised in the objections include:”

“Incorrect spelling of application location • Insufficient consultation and survey work has been undertaken prior to lodgement of the application. • Loss of nature in area since industrialisation • Impact on birds and rare butterflies • Visual impact of the mast • Cumulative impact of mast and other infrastructure features on the landscape • The use of existing tracks will result in disturbance to the ecology of the area • No information provided on connections to power,…”

Officer report

What officers recommended

Officers recommended approval because the temporary mast was considered acceptable in principle and would not cause unacceptable impacts on visual amenity, biodiversity, heritage or highways.

“Having regard to the above, the main issues to consider in this Application relate to the principle of development, impact on the visual amenity of the location, biodiversity, archaeological and transport impacts.”

Officer report

Main effects assessed

The assessment found limited landscape, transport and archaeological effects, with biodiversity mitigation and habitat aftercare required.

“Highway Safety Policy SP5: Sustainable Transport and Accessibility of the RLDP states that new development must be located and designed in a way that minimises the need to travel, reduces dependency on the private car and enables sustainable access to local services. Development must be designed to provide safe and efficient access to the transport network, which includes the active travel, public transport and street networks.”

“The ADBC concludes that the impacts from the proposed development are expected to be ‘fairly limited’ given the placement of the mast and method of its construction. The predicted impact can be reduced by a mitigation strategy involving either archaeological fieldwork or mitigation by design.”

Officer report

The committee’s decision

The committee granted the application subject to the conditions in the officer report.

“RESOLVED: That the above application be granted, subject to the conditions contained in the report of the Corporate Director – Communities.”

Minutes

Conditions attached

The mast must follow the approved documents, be removed within three years of commissioning, and meet the specified biodiversity mitigation and aftercare requirements.

“The development shall be undertaken in strict accordance with the Landscape & Habitat Mitigation proposals as outlined in the Landscape & Habitat Mitigation Note prepared by WSP and dated 24 July 2025. The biodiversity proposals shall be maintained in accordance with the aftercare Maintenance & Management measures listed in the Note for a minimum period of 5 years.”

Officer report

Sources

  • Bridgend Development Control Committee minutes, 2 October 2025
  • Agenda and papers (council website)

Source: Plota analysis of Bridgend's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Council
Bridgend
Date
Thursday 2 October 2025
Recommendation
Officers recommended approval
Committee decided
Approved
Minutes
The council's minutes
Meeting
Agenda and papers (council website)
Application
The application (council website)

This committee's year

12 decisions in the 12 months to this meeting.

Source: Plota analysis of the committee's minutes.

Every decision by this council's committees →