Care home extension at Stanton Court, Stanton Drew, Bristol

Summary of planning committee decision

Decided by Bath Planning Committee on 13 May 2026.

24/02755/FULApproved

What was proposed

The application proposed demolishing the existing rear extension and building a two-storey rear extension for the existing care home.

“Planning permission is sought for the erection of a two-storey rear extension and associated works, to follow demolition of existing rear extension.”

“There is a concurrent application for Listed Building Consent, reference: 24/02756/LBA, for internal and external alterations for the erection of a two storey rear extension and associated works, to follow demolition of the existing rear extension.”

Officer report

The site and its history

The site is a Grade II* listed care home in the Green Belt and conservation area, near the River Chew and Stanton Drew Stone Circles.

“REPORT The application refers to an existing care home in the village of Stanton Drew. The original building is believed to be constructed in 1753 and is Grade II* listed. The site fronts the main road through Stanton Drew and is located close to the River Chew and the Stanton Drew Stone Circles. The proposal is within the Green Belt and the village conservation area.”

Officer report

Earlier applications

Earlier permissions covered converting outbuildings into staff accommodation and associated listed building consent.

“99/02949/FUL - PERMIT - 27 October 1999 - Conversion of outbuildings to form staff accommodation (renewal of planning permission WC 12245/K)”

“99/02950/LBA - PERMIT - 22 November 1999 - Conversion of outbuildings to form staff accommodation (renewal of listed building consent WCLB 12245/L)”

Officer report

What consultees said

Adult Social Care supported the need, while conservation officers maintained an objection because the extension would cause less than substantial heritage harm.

“28th August 2024: Objection. The scheme is considered to cause less than substantial harm to the significance of the listed building and is considered to be at the higher end of this spectrum. The degree of harm will need to be outweighed by public benefit.”

“12th August 2025: Objection. Additional information submitted has not addressed whether underpinning to the listed building will be required. The concerns raised in the previous consultation (dated 28.08.24) regarding the design and extent of the extension remain. It is considered to cause less than substantial harm to the significance of the listed building and its setting.”

Officer report

What people said

Five objections raised concerns including scale, character, construction, highways, pollution, heritage and legal restrictions; one comment supported the improvement.

“BANES Core Strategy Policy GB1, GB2 The B&NES planning portal highlights relevant related planning information and constraints for this application, including both the green belt and infill boundaries. Policy GB1 states that development will permitted but limited to infilling, with infilling defined as an otherwise extensively built up frontage.”

“Five objections have been received from third parties, the following is a summary of the points raised: - Out of proportion - Out of character - Structural concerns - Highways impacts of construction - Public transport concerns - Construction phase impacts on parking - Construction management Plan concerns…”

Officer report

The decision

“PERMIT 1 Standard Time Limit (Compliance) The development hereby permitted shall be begun before the expiration of three years from the date of this permission. Reason: As required by Section 91 of the Town and Country Planning Act 1990 (as amended) and to avoid the accumulation of unimplemented planning permission. 2 Archaeology Watching Brief (Pre-commencement) No development shall commence, except archaeological investigation work, until the applicant, or their agents or successors in title, has secured the implementation of a programme of archaeological work in accordance with a written scheme of investigation which has been submitted to and approved in writing by the Local Planning Authority. The programme of archaeological work should provide a controlled watching brief during ground works on the site, with provision for excavation of any significant”

Minutes, 13 May 2026

Councillors at the meeting

Apologies John Leach Lib Dem, Hal MacFie Lib Dem, Fiona Gourley Lib Dem

Source: Plota analysis of the council's minutes; parties from the council's list of councillors.

Sources

  • Bath Planning Committee minutes, 13 May 2026
  • Agenda and papers (council website)

Source: Plota analysis of Bath's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Council
Bath
Date
Wednesday 13 May 2026
Recommendation
Officers recommended approval
Committee decided
Approved
Councillors
9Lib Dem 6Conservative 1Independent 1Labour 1Show councillors
Minutes
The council's minutes
Meeting
Agenda and papers (council website)
Application
The application (council website)

This committee's year

51 decisions in the 12 months to this meeting, 10 against officer advice.

Source: Plota analysis of the committee's minutes.

Every decision by this council's committees →