Commercial unit with two flats at Central Garage, 93 Bristol Road, Whitchurch, Bristol

Summary of planning committee decision

Decided by Bath Planning Committee on 19 Nov 2025.

23/04552/FULApproved

What was proposed

The application proposed demolishing the existing garage and building a commercial unit with two flats above.

“REPORT The application refers to an existing vehicle repair garage (Use Class B2) located within the housing development boundary and local centre of Whitchurch.”

“Planning permission is sought for the demolition of the existing garage building and erection of a commercial unit (Use Class E) with two flats above (Use Class C3).”

Officer report

The site and its history

The site was an existing vehicle repair garage within Whitchurch’s housing development boundary and local centre, following an earlier withdrawn application.

“22/00757/FUL - Withdrawn - 27 June 2022 - Demolition and replacement of existing garage repair building and Change of Use for new mixed-use development comprising two commercial units (Use Class E(c) and E(g) and two maisonettes (Use Class C3).”

Officer report

What officers recommended

Officers recommended approval, finding the proposal acceptable overall despite less-than-substantial harm to the setting of the listed cottage.

“As expressed above, the proposal by virtue of its siting and scale would cause less than substantial harm to the setting of the Grade II Listed Yew Tree Cottage. Whilst the harm is quantified as being less than substantial, it must still be afforded great weight as set out in Paragraph 212 of the NPPF.”

“On balance it is considered that in this instance the public benefits of the proposal do outweigh the less than substantial harm to the setting of the designated heritage asset. The proposal therefore accords with the provisions of the Planning (Listed Buildings and Conservation Areas) Act 1990, policy HE1 of the Placemaking Plan for Bath and North East Somerset (2017) and Part 16 of the NPPF.”

Officer report

What consultees said

The highway authority raised no objection, while consultees requested controls or further information on heritage, drainage, ecology, noise and contamination.

“Drainage and Flooding - 09/01/24. Further information relating to the surface water drainage of the property is required. The applicant has stated they wish to discharge surface water to Wessex water's public surface water sewer at 5L/s, we will require evidence that permission has been granted by Wessex water. We will need to see the calculations for the sizing of the surface water storage tank as well as details of how the SUDS attenuation tank will be maintained.”

“Highway Authority - 04/01/24. The highway authority has no objection to the application proposal. However, there would be a need for a condition to ensure that the site parking is secured.”

Officer report

Objections received

The parish council and four objectors raised concerns about parking, highway safety, heritage, amenity, employment, contamination and the suitability of the development.

“Whitchurch Village Council - OBJECT. 16/07/25. There is a lack of parking spaces for the two retail units, this would have a detrimental impact on road safety in this location and be detrimental to Policy ST7 & Policy No's WV4.2 - Traffic Impacts of Developments & WV4.3 Traffic & Safety. It would also be an overdevelopment of the site and have a negative impact on the listed building, Yew Tree cottage, which is situated at the rear of the site.”

“Four letters of objection have been received. The concerns raised can be summarised as follows:”

Officer report

The decision

“PERMIT 1 Standard Time Limit (Compliance) The development hereby permitted shall be begun before the expiration of three years from the date of this permission. Reason: As required by Section 91 of the Town and Country Planning Act 1990 (as amended) and to avoid the accumulation of unimplemented planning permission. 2 Plans List (Compliance) The development/works hereby permitted shall only be implemented in accordance with the plans as set out in the plans list. Reason: To define the terms and extent of the permission. 3 Construction Management Plan (Pre-commencement) No development shall commence until a Construction Management Plan has been submitted to and approved in writing by the Local Planning Authority. This shall include details of the following: 1. Deliveries (including storage arrangements and timings); 2. Contractor parking; 3. Traff”

Minutes, 19 Nov 2025

Councillors at the meeting

Apologies Hal MacFie Lib Dem, Toby Simon Lib Dem

Source: Plota analysis of the council's minutes; parties from the council's list of councillors.

Sources

  • Bath Planning Committee minutes, 19 November 2025
  • Agenda and papers (council website)

Source: Plota analysis of Bath's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Council
Bath
Date
Wednesday 19 November 2025
Recommendation
Officers recommended approval
Committee decided
Approved
Councillors
9Lib Dem 6Conservative 1Independent 1Labour 1Show councillors
Minutes
The council's minutes
Meeting
Agenda and papers (council website)
Application
The application (council website)

This committee's year

20 decisions in the 12 months to this meeting, 6 against officer advice.

Source: Plota analysis of the committee's minutes.

Every decision by this council's committees →