21 flats above shop at Queens Parade, North Road, Lancing

Summary of planning committee decision

Decided by Adur Planning Committee on 1 Sept 2025.

AWDM/0153/25Approved

No officer report was published for this decision; this summary is from the committee minutes.

What was proposed

The application proposed a two storey upward extension including an additional floor above the Co-op building to provide 21 flats, plus aesthetic improvements, landscaping, refuse and cycle storage.

“Proposal: Proposed 2 storey upwards extension (including additional floor over the Co-Op building) to provide 21no. flats (Class C3) plus aesthetic improvements to the existing building. Provision of hard and soft landscaping, refuse and cycle storage.”

Minutes

What officers explained

Officers were still awaiting drainage comments and explained that a viability assessment showed a planning obligation contribution of £80,723 was feasible, due largely to the costs of building on and improving the existing structure.

“The Principal Planning Officer presented the report explaining that Officers were still waiting for updated comments from LLFA and Southern Water regarding the discharge of surface water into the foul network. Regarding the 106 contributions, the viability test showed a contribution of £80,723 was feasible and members were requested to decide how this should be spent.”

Minutes

Who spoke

A supporting speaker said PV panels were feasible but the scheme already met sustainability requirements through air source heat pumps, and that existing tenants would get new double glazed windows and improved exteriors.

What members discussed

Members discussed requiring PV panels by condition despite the effect on viability, and wanted officers to explore whether existing residents could also benefit from them.

“During debate Members discussed the possibility of adding a condition that prescribed that PV panels must be installed and acknowledged that this would alter the viability. The committee was keen to have the applicant explore the possibility that existing residents could benefit from the PV panels.”

Minutes

Deciding how to spend the contribution

Members rejected spending the contribution on additional infrastructure by 2 votes to 6, then voted 6 to 2 to direct all of it to off-site affordable housing.

“Members discussed the options for the use of the s106 money. A proposal was put forward to use the money for additional infrastructure. This was seconded and voted on with an outcome of 2 in favour and 6 against. 4”

“A second proposal was put forward to use all of the contributions for off site affordable housing. This was seconded and voted on with an outcome of 6 in favour and 2 against.”

Minutes

The vote to approve

Members unanimously asked officers to discuss PV panels for existing residents with the applicant, then voted 7 to 1 to approve the application with that request added.

“A proposal was put forward to add a request that Officers discuss with the applicant the possibility of the installation of PV panels and arranging that existing residents benefit from them if possible. This was seconded and voted in favour of unanimously.”

“A proposal was put forward to accept the Officers recommendation and approve the application with the additional requested PV panel discussions. This was seconded and voted on with an outcome of 7 in favour and 1 against.”

Minutes

What was decided

The committee delegated authority to the Head of Planning to approve the application, subject to satisfactory drainage details, a planning obligation for affordable housing, and conditions.

“Decision - Delegated authority granted to Head of Planning to approve subject to receipt of satisfactory drainage details and removal of objection from the LLFA; completion of s106 Agreement to secure £80,273 to be spent solely on provision of affordable housing within Adur District.”

Minutes

Sources

  • Adur Planning Committee minutes, 1 September 2025
  • Agenda and papers (council website)

Source: Plota analysis of Adur's committee minutes. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Council
Adur
Date
Monday 1 September 2025
Recommendation
Officers recommended approval
Committee decided
Approved
Vote
Unanimous
Minutes
The council's minutes
Meeting
Agenda and papers (council website)
Application
The application (council website)