105 Pages Walk London Southwark SE1 4HD Data via plota.co.uk

26/AP/2861 - Outline Application Under consideration/assessment

Proposal

Outline planning permission (all matters to be determined: scale, access, landscaping, layout and appearance) for the construction of a part-two, part-single storey commercial building (Class E(g)); a detached single-storey annexe building, erection of new site boundary enclosure, provision of vehicular access on Mandela Way and parking of a T-34 tank vehicle. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
24 Sept 2026
✓
Validated
29 Sept 2026
Decision
Expected by 23 Nov 2026

Under consideration

No decision has been issued yet. Plota predicts a decision by 20 Dec 2026, from Southwark's recent commercial and major works.

Site constraints 14

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Pages Walk conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
2 Article 4 directions
Old Kent Road North District Town Centre · Site allocation NSP58: Mandela Way. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
Locally significant industrial site
A borough-level industrial site.
Boroughs protect these sites for industrial and related uses.
Archaeological priority area
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Southwark AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project 552 m away: Thames Tideway Tunnel
The site is 552 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, 177 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
Wider setting of protected view 23A.1 Centre of Bridge over the Serpentine to the Palace of Westminster; Radon affected area, class 2; Tree preservation order 15 m away: Land at Pages Walk/Leroy Street; 1 listed building within 150 m; Inside the Southwark built-up area; Public transport access: PTAL 4 (good), TfL 2023, for the 100 m square.
Not affected
Not green belt · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI), Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Southwark - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Southwark
Application type
Outline Application
Postcode
SE1 4HD
Received
24 Sept 2026
Validated
29 Sept 2026
Ward
London Bridge & West Bermondsey
Parish
Bermondsey And Rotherhithe
Case officer
Show
Target decision
23 Nov 2026
Applicant
Show

Decision outlook

Day 55 of the 56-day target. Southwark usually decides commercial and major works by day 64.

Day 559 days to the predicted decision (day 64)
43%decided within 8 weeks
95%approved
11%go to committee

Plota live figures for commercial and major works decided by Southwark in the last twelve months, from validation. Southwark decision record →

Public comments

8comments received
5 objecting1 neutral2 supporting

63% object · below the UK average of 74%

Last counted 22 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Statutory expiry
23 Nov 2026
Env. assessment
No
Southwark
Planning Authority Score
7/10
Good
#64 of 296 overall
Relevant to this application:
Major dwellings

Southwark is faster than most councils at deciding householder applications: #54 of 296 on speed. Householder applications are slightly more likely to be approved here (95%) than the national average (90%).

Faster than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Southwark decision statistics
Based on MHCLG data, the year to March 2026
92%
Overall approval rate
Above avg (87%) #93 of 296
95%
Householder approved
Above avg (90%) #92 of 296
78%
Decided in 8 weeks
Above avg (63%) #54 of 296
37%
Extended time limit
Below avg (41%) #122 of 296
92%
Minor dwellings approved
259 decided (1-9 homes)
86%
Major dwellings approved
14 decided (10+ homes)
82%
Change of use approved
38 decided
1,622
Total decisions
132 refused in the year to March 2026