Seven-turbine wind farm at Existing Beinn Ghlas Wind Farm, Taynuilt
Summary of planning committee decision
Decided by Argyll Planning, Protective Services and Licensing Committee on 15 Sept 2026.
What was proposed
The application proposed seven turbines up to 149.9 metres, associated infrastructure and decommissioning of the existing wind farm.
“Reference No: 25/01240/PP Planning Hierarchy: Major Applicant: Beaufort Wind Limited Proposal: Erection of 7 turbines (up to 149.9m to tip) and ancillary development and decommissioning of existing Beinn Ghlas wind farm. Site Address: Existing Beinn Ghlas Wind Farm, Taynuilt…”
“Erection of 7 turbines (up to 149.9m to tip) • Hardstanding areas at the base of each turbine, with a permanent area of approximately 1,400 m2; • Upgrading of four existing road junctions to support construction and abnormal road traffic; • Upgrading of forestry tracks from the A85 through Fearnoch Forest, Glen Lonan Road (C32) and existing wind farm access track to accommodate the delivery of abnormal loads to the site and use of existing track for access to the first…”
Officer report
The site and surroundings
The site is a 436-hectare existing wind farm in remote countryside, with upland heath, mires, woodland and access tracks.
“The Site currently contains the existing Beinn Ghlas Wind Farm comprising 14 wind turbines (approximately 54.1 m to blade tip), each with a capacity of 600 kilowatts (kW) providing an overall installed capacity of 8.4 MW. The Wind Farm has been operational since May 1999. In June 2022, an application to extend the life of the Wind Farm (ref: 21/00870/PP) was approved to allow the Wind Farm to operate to August 2033.”
“3,4 The site landscape context comprises low, rugged hills, scattered with small outcrops of rocks and scoured with steep sided streams. There is open moorland, predominantly upland heath and mires including bog pools on the higher ground and a mixture of rough grassland and woodland on the lower slopes. Within the surrounding area there is a combination of native deciduous woodland and commercial coniferous forestry to the north and southeast of the Site.”
Officer report
Why officers supported it
Officers considered the proposal consistent with renewable energy policies and found that conditions could address its environmental effects.
“The proposal is consistent with the primary renewable energy policies of NPF4 and LDP2 and other relevant policies providing the recommended conditions are attached.”
“Classification: OFFICIAL Assessment) (Scotland) Regulations 2017. There is a requirement to examine the environmental information submitted and reach a reasoned conclusion on the significant environmental effects of the proposal including those matters set out in FEI relating to the proposed grid connection.”
Officer report
What people said
Three objections raised visual, environmental and eagle impacts and questioned new turbine bases, while 26 submissions supported the proposal.
“Representations are published in full on the planning application file and are available to view via the Public Access section of the Council’s website. A list of those who have made representations is contained at Appendix B attached to this report. At time of writing there has been 3 objections, and 26 submissions in support of the proposals.”
“The proposal will have an unacceptable visual and environmental impact • The proposals will adversely impact on Eagles • Existing turbine bases should be used not new ones to reduce impacts on the site.”
Officer report
Who spoke at the meeting
The Senior Planning Officer explained the existing wind farm, the proposal and the view that permission could be granted subject to conditions.
The decision
“Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: 1. PP - Approved Details & Standard Notes – EIA Development The development shall be implemented in accordance with the details specified on the application form dated 21.07.25 and the Environmental Impact Assessment Report dated 25.07.25, supporting information and the approved drawings listed in the table below unless the prior written approval of the planning authority is obtained for an amendment to the approved details under Section 64 of the Town and Country Planning (Scotland) Act 1997. The developer and subsequent operators shall at all times construct and operate the development hereby permitted in accordance with the provisions of the Environmental Impact Assessment Report (and FEI submissions), accompanying the application with mitigation measures ad”
Minutes, 15 Sept 2026
Conditions
Approved subject to 2 conditions, set out in the minutes.
Councillors at the meeting
- Gordon BlairChairSNPFor(no vote against recorded)
- Kieron GreenIndependentFor(no vote against recorded)
- Fiona HowardLabourFor(no vote against recorded)
- Willie HumeSNPFor(no vote against recorded)
- Andrew KainIndependentFor(no vote against recorded)
- Reeni Kennedy-BoyleSNPFor(no vote against recorded)
- Liz McCabeIndependentFor(no vote against recorded)
- Luna MartinGreenFor(no vote against recorded)
- Peter WallaceConservativeFor(no vote against recorded)
The minutes record this decision with no vote against, so each member present for this item is shown as voting for it.
Apologies Jan Brown SNP, Daniel Hampsey Conservative, Graham Hardie Lib Dem, Paul Donald Kennedy Lib Dem
Source: Plota analysis of the council's minutes; parties from the council's list of councillors.
Sources
- Argyll Planning, Protective Services and Licensing Committee minutes, 15 September 2026
- Agenda and papers (council website)
Source: Plota analysis of Argyll's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Council
- Argyll
- Date
- Tuesday 15 September 2026
- Recommendation
- Officers recommended approval
- Committee decided
- Approved
- Councillors
- 9Independent 3SNP 3Conservative 1Green 1Labour 1Show votes
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- View application →
- All decisions
- Argyll committee decisions →
This committee's year
20 decisions in the 12 months to this meeting.
Source: Plota analysis of the committee's minutes.