Dowdyke Road Sutterton, Boston, Lincolnshire, PE20 2LZ Data via plota.co.uk

B/26/0234 - Form B - Overhead/Electricity Decided

Proposal

Notification to Boston Borough Council under the Electricity Act 1989: The Overhead Lines (Exemption) (England and Wales) Regulations 2009 for the proposed improvement of a section of overhead network, to accommodate an increased demand on the network. In order to carry out these works a new pole will be installed next to the pole in situ to support the existing overhead line works reference 21VJSCAP36 Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
14 May 2026
Decision
Target date was 24 Jun 2026

Under consideration

No decision has been issued yet. Plota predicted a decision around 23 Nov 2026; it is now day 193.

Site constraints 3

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Agricultural land, grade 3b
Not best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s), which most planning maps still show, had this area as grade 1. The predicted grade is Defra's current estimate; only a site survey settles it.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
Also on the record
National infrastructure project 1.1 km away: Outer Dowsing Offshore Wind (Generating Station).
Not affected
Not green belt · No listed building at the site · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Boston - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Boston
Application type
Form B - Overhead/Electricity
Postcode
PE20 2LZ
Received
14 May 2026
Validated
14 May 2026
Ward
Five Village Ward
Parish
Sutterton
Target decision
24 Jun 2026
Decision level
Delegated Decision
Applicant
Show

Decision outlook

Day 193, past the statutory target. 85% of utility and infrastructure works in Boston are decided within thirteen weeks; extensions of time are common, and the council need not decide on the day. Last seen undecided on 21 Nov 2026.

Day 193137 days past the 56-day target
81%decided within 8 weeks
96%approved
26decided in the last year

Plota live figures for utility and infrastructure works decided by Boston in the last twelve months, from validation. Boston decision record →

Public comments

No public comments yet.

Last counted 21 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Statutory expiry
24 Jun 2026
Env. assessment
No