Temporary flexible building uses at Unit A, Creek Road, Barking

Summary of planning committee decision

Decided by Barking And Dagenham Planning Committee on 11 Nov 2026.

26/00666/VARApproved

What was proposed

The application sought to vary the use condition for five years, allowing specified commercial, service, healthcare, office, education, arts and museum uses.

“Variation of Condition 27 (Use Class Orders) attached to planning consent 20/02298/FULL dated 31/03/2021 to allow additional use classes for a temporary period of five years. Recommendation Planning Committee is asked to resolve to: 1. Agree the reasons for approval as set out in this report; 2.”

“Condition 28 – Restriction on educational uses to higher education, further education, adult education, vocational training, tuition and healthcare-related educational activities only.”

Officer report

The site and building

The completed four-storey development provides about 11,362 square metres of flexible industrial floorspace in a Strategic Industrial Location.

“Site, Situation and Relevant Background Information i. The application site comprises the completed Industria development located at the corner of Creek Road and Long Reach Road within the River Road industrial area. The site extends to approximately 0.8 hectares and occupies the former Remploy Factory site, which was redeveloped following the grant of planning permission ref. 20/02298/FULL in March 2021.”

“Figure 1 – The completed Industria development vi. The original planning permission was granted in recognition of the site's Strategic Industrial Land designation and the proposal's ability to intensify industrial floorspace provision within the Borough. The approved development was intended to provide modern industrial accommodation capable of accommodating a range of industrial occupiers whilst contributing towards employment growth objectives. vii.”

Officer report

Consultation responses

Environmental Health, Waste and Recycling, Historic England, the Fire Brigade and other consultees raised no objection, while transport consultees requested further information.

“Be First Environmental Health 24/06/2026 No comments to make and no objection raised to the proposal. Be First Transport 24/06/2026 Raised concerns regarding trip generation, parking demand, cycle parking provision and the transport implications of the proposed flexible uses. Requested additional transport assessment. The applicant subsequently submitted an updated Transport Statement and agreed a 50% cap on flexible uses.”

“Confirmed that the archaeological condition attached to the original permission has been satisfied and no further archaeological requirements are necessary. London Fire Brigade (water team) 24/06/2026 No objection. Confirmed that no additional fire hydrants are required and no further action is required in respect of hydrant provision. Building Safety Regulator 24/06/2026 Confirmed no comments to make.”

Officer report

Who spoke

The Senior Development Management Officer presented the application and referred to its history, constraints and key planning issues.

The committee’s consideration

Members were advised that the identified benefits would outweigh the limited policy conflict and that the proposal represented sustainable development.

“Officers had acknowledged that the proposal would give rise to some policy conflict insofar as it would permit a range of non-industrial uses within a Strategic Industrial Land designation. However seeing that occupation of this particular development has proved materially slower than originally anticipated and that there was a demonstrable demand from alternative employment-generating occupiers, significant weight had been attached to a number of material considerations set…”

“Officers were satisfied that the proposal would support economic activity, improve utilisation of an existing employment building and contribute towards the social and economic objectives of sustainable development as set out in the National Planning Policy Framework (NPPF), and having regard to the Development Plan as a whole and all other material considerations, officers concluded that the proposal represented sustainable development, and…”

Minutes

Councillors at the meeting

The minutes record this decision with no vote against, so each member present for this item is shown as voting for it.

Apologies Faruk Choudhury Green, Billy Edmunds Reform UK, Ingrid Robinson Lab Co-op

Source: Plota analysis of the council's minutes; parties from the council's list of councillors.

Sources

  • Barking And Dagenham Planning Committee minutes, 11 November 2026
  • Agenda and papers (council website)

Source: Plota analysis of Barking And Dagenham's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Date
Wednesday 11 November 2026
Recommendation
Officers recommended approval
Committee decided
Approved
Councillors
6Labour 5Reform UK 1Show votes
Minutes
The council's minutes
Meeting
Agenda and papers (council website)

This committee's year

6 decisions in the 12 months to this meeting.

Source: Plota analysis of the committee's minutes.

Every decision by this council's committees →