61 Barton Lane, Barton-on-Sea, New Milton BH25 7PJ Data via plota.co.uk

25/11128 - Full Planning Permission Approved

Proposal

Roof alterations in association with new first floor; partial demolition of existing structure; front & rear single-storey extensions; side dormer and rooflights. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
17 Dec 2025
✓
Consultation
17 Dec 2025
✓
Approved
17 Jun 2026

Approved on 17 Jun 2026 · Development Control Committee · Last checked 5 Oct 2026

Planning committee

Decided by New Forest (District) Planning Committee on 11 Mar 2026.

Approved

Against officer advice: officers had recommended refusal.

  • Officers advised refusal because the design would harm the street scene and protected-species information was missing.
  • One representation supported the proposal and one objected over overlooking and loss of privacy.
Read how the committee decided The proposed changes, site context, officers’ assessment, public comments, speakers and committee decision. Includes the meeting recording, from 1:41:44 where this application was taken

Source: Plota analysis of New Forest (District)'s committee minutes of 11 Mar 2026.

Site constraints 3

Article 4 direction
Hovercraft in the Solent. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
National infrastructure project: Navitus Bay Wind Park
The site is inside the project boundary. Generating station, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Inside the Barton on Sea built-up area.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Sales history 1

Last sold for £440,000 in July 2025. Detached house, freehold.

1 July 2025£440,000

Sale prices from HM Land Registry's price paid record, matched to this application by its address.

Building

Floor area88 m² (947 sq ft)
Energy ratingF (36 out of 100), could reach C
PropertyDetached bungalow, 6 habitable rooms
Built1930 to 1949
HeatingBoiler and radiators, mains gas
WallsCavity wall, as built, no insulation (assumed)

From the energy performance certificate lodged in February 2018, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in New Forest (District) - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Planning Permission
Postcode
BH25 7PJ
Received
17 Dec 2025
Validated
17 Dec 2025
Ward
Barton & Becton
Parish
New Milton
Case officer
Show
Target decision
11 Feb 2026
Decision
Granted Subject to Conditions
Decision date
17 Jun 2026
Decision level
Development Control Committee
Applicant
Show
Agent
plans4home

How this decision compares

Decided in 182 days from validation, 129 days slower than New Forest (District)'s median of 53 for full applications. Approved, as 92% of full applications here are.

67%decided within 8 weeks
92%approved
746decided in the last year

Plota live figures for full applications decided by New Forest (District) in the last twelve months, from validation. New Forest (District) decision record →

Public comments

2comments received
1 objecting1 supporting

5 neighbours consulted · Last counted 5 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14562267
Planning Portal ref
PP-14562267
Consultation
17 Dec 2025
Comments by
16 Jan 2026
Committee
11 Mar 2026
Env. assessment
No
New Forest (District)
Planning Authority Score
7.8/10
Good
#29 of 296 councils
Relevant to this application:
Householder decisions

New Forest (District) is faster than most councils at deciding householder applications, ranking #37 out of 296. Householder applications are slightly more likely to be approved here (96%) than the national average (90%).

Faster than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
New Forest (District) decision statistics
Based on MHCLG data, the year to March 2026
90%
Overall approval rate
Above avg (87%) #112 of 296
96%
Householder approved
Above avg (90%) #54 of 296
80%
Decided in 8 weeks
Above avg (63%) #37 of 296
35%
Extended time limit
Below avg (41%) #103 of 296
69%
Minor dwellings approved
87 decided (1-9 homes)
91%
Major dwellings approved
11 decided (10+ homes)
78%
Change of use approved
40 decided
885
Total decisions
85 refused in the year to March 2026

Sale prices: Contains HM Land Registry data © Crown copyright and database right 2026. This data is licensed under the Open Government Licence v3.0.

Freehold boundary: © Crown copyright and database rights 2026, HM Land Registry. Polygons © Crown copyright and database rights 2026 Ordnance Survey 100026316. Conditions of use

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.