Estuary View Farm Wardleys Lane Hambleton Poulton-Le-Fylde Lancashire FY6 9DX Data via plota.co.uk

25/00705/AGR - Agricultural Notification Allowed on appeal

Proposal

Prior Notification for the erection of 1.no storage building for the storage of hay under Class A of Part 6, Schedule 2 of the GPDO Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
1 Sept 2025
✗
Refused
26 Sept 2025
✓
Appeal allowed
23 Jan 2026

Refused on 26 Sept 2025 · Delegated Decision · Last checked 13 Oct 2026

Documents 22

All documents on the council site ↗

Site constraints 5

Agricultural land, grade 3b
Not best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s) agrees.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
Special protection area 101 m away: Morecambe Bay
Work nearby can need a habitats assessment.
Harm to a protected site is only accepted where there is no alternative and an overriding public interest.
Habitat network: Network Enhancement Zone 1
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
SSSI 101 m away: Wyre Estuary SSSI
Natural England may need consulting, depending on what is proposed.
Sites of special scientific interest are the best wildlife and geological sites in the country. Development likely to harm one is rarely permitted.
National infrastructure project 968 m away: Preesall Saltfield Underground Gas Storage
The site is 968 m from the project boundary. Underground gas storage, decided. The project page says whether consent was granted. Also within 2 km: East Irish Sea Transmission Project (at pre-application, 150 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Wyre - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Wyre
Application type
Agricultural Notification
Postcode
FY6 9DX
Received
1 Sept 2025
Validated
1 Sept 2025
Ward
Hambleton And Stalmine-with-Staynall
Parish
Stalmine-with-Staynall
Case officer
Show
Target decision
29 Sept 2025
Decision
Prior Approval Refused
Decision date
26 Sept 2025
Decision level
Delegated Decision
Appeal
Allowed · 23 Jan 2026 · Written Representations · Inspectorate case 3373811 ↗
Applicant
Show

How this decision compares

Decided in 25 days from validation, about the council's usual 28 days. Approved, as 78% of prior approvals here are.

94%decided within 8 weeks
78%approved
73decided in the last year

Plota live figures for prior approvals decided by Wyre in the last twelve months, from validation. Wyre decision record →

Public comments

No public comments yet.

Last counted 13 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14293837
Planning Portal ref
PP-14293837
Statutory expiry
29 Sept 2025
Env. assessment
No
Wyre
Planning Authority Score
1.2/10
Poor
#288 of 296 overall
Relevant to this application:
Householder decisions

Wyre is one of the slowest councils in England for householder decisions: #272 of 296 on speed. The council extends the time limit on 66% of applications - one of the highest rates in England. Expect your application to take longer than the standard deadline. Householder applications are slightly less likely to be approved here (88%) than the national average (90%).

Among the slowest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Wyre decision statistics
Based on MHCLG data, the year to March 2026
83%
Overall approval rate
Below avg (87%) #243 of 296
88%
Householder approved
Below avg (90%) #228 of 296
38%
Decided in 8 weeks
Below avg (63%) #272 of 296
66%
Extended time limit
Above avg (41%) #281 of 296
56%
Minor dwellings approved
41 decided (1-9 homes)
67%
Major dwellings approved
6 decided (10+ homes)
75%
Change of use approved
52 decided
539
Total decisions