Erith Quarry - Parcel 9 Fraser Road Erith Kent Data via plota.co.uk

20/00775/OUTM58 - Details pursuant to Planning Condition With Case Officer

Proposal

Application to approve partial details of condition Part B of Condition 12 for Parcel 9 (Circular Economy Statement) pursuant to application for hybrid planning application for the phased development of up to a total of 249 residential dwellings (use class C3) with associated works including informal and formal open space, pedestrian and cycle infrastructure, car and cycle parking (only access to be considered) and with detailed submission for parcel 3a with associated works including parking and landscaping. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
27 Oct 2026
✓
Consultation
6 Nov 2026
Decision
Expected by 22 Dec 2026

Under consideration

No decision has been issued yet. A decision is expected by 22 Dec 2026.

Comments are open until 27 Nov 2026

Comment on this application ↗

Site constraints 7

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Locally significant industrial site
A borough-level industrial site.
Boroughs protect these sites for industrial and related uses.
Air quality management area: Bexley AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project about 215 m away: Riverside Energy Park
The site is about 215 m from the project boundary. Generating station, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, about 1.8 km).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Radon affected area, class 2; Inside the Bexley built-up area; Public transport access: PTAL 2 (poor), TfL 2023, for the 100 m square.
Not affected
Not green belt · No scheduled monument at the site

Checked on 1 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI), Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Bexley - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Bexley
Application type
Details pursuant to Planning Condition
Received
27 Oct 2026
Validated
27 Oct 2026
Ward
ERITH
Target decision
22 Dec 2026
Decision level
Delegated
Applicant
Show

Public comments

No public comments yet.

Last counted 19 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-15327138
Planning Portal ref
PP-15327138
Consultation
6 Nov 2026
Comments by
27 Nov 2026
Statutory expiry
22 Dec 2026
Env. assessment
No
Bexley
Planning Authority Score
8.9/10
Excellent
#5 of 296 overall
Relevant to this application:
Householder decisions

Bexley is one of the fastest councils in England for householder decisions: #17 of 296 on speed. Only 20% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Householder applications are slightly more likely to be approved here (95%) than the national average (90%).

Among the fastest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Bexley decision statistics
Based on MHCLG data, the year to March 2026
90%
Overall approval rate
Above avg (87%) #106 of 296
95%
Householder approved
Above avg (90%) #69 of 296
89%
Decided in 8 weeks
Above avg (63%) #17 of 296
20%
Extended time limit
Below avg (41%) #17 of 296
69%
Minor dwellings approved
124 decided (1-9 homes)
88%
Major dwellings approved
8 decided (10+ homes)
58%
Change of use approved
90 decided
1,324
Total decisions
133 refused in the year to March 2026