POINT OF AYR CARAVAN CAMP, West Road, Talacre, Holywell, CH8 9SA Data via plota.co.uk

FUL/000717/26 - Full - Building Works Consultation period opened

Proposal

Partial Demolition of existing sales, reception, offices, bar and swimming pool and alterations and extensions to comprise of reception, sales centre, shop, bars/lounges, swimming pool, including decked terrace areas, landscaping and associated works Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
26 Aug 2026
✓
Validated
30 Oct 2026
✓
Consultation
3 Nov 2026
Decision
Expected by 25 Dec 2026

Under consideration

No decision has been issued yet. Plota predicts a decision around 21 Dec 2026, from Flintshire's recent demolitions.

Comments are open until 23 Nov 2026

Comment on this application ↗

Documents 18

All documents on the council site ↗

Site constraints 15

Coal mining legacy areaIPC and RAS Sites BHP Petroleum LtdIPC and RAS Sites Evergreen ResourcesDevelopment Control North TeamCounty Boundary Flintshire Unitary Authority County BoundaryWindfarm Consultation Area Consult National Air Traffic Services.Existing Waste Management Site Consult Environmental HealthArticle 4 directionTAN 15 Defended Zones SeaFlood Map Seas Flood Zone 3
Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Special protection area 198 m away: The Dee Estuary (Wales)
Work nearby can need a habitats assessment.
Harm to a protected site is only accepted where there is no alternative and an overriding public interest.
National infrastructure project 787 m away: HyNet Carbon Dioxide Pipeline
The site is 787 m from the project boundary. Pipeline, decided. The project page says whether consent was granted. Also within 2 km: Hynet North West Hydrogen Pipeline (at pre-application, 787 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
SSSI 198 m away: Gronant Dunes and Talacre Warren
Natural England may need consulting, depending on what is proposed.
Sites of special scientific interest are the best wildlife and geological sites in the country. Development likely to harm one is rarely permitted.
Coal mining legacy areaCouncil record
Recorded by the council for this site.
Council site ↗
IPC and RAS Sites BHP Petroleum LtdCouncil record
Recorded by the council for this site.
Council site ↗
IPC and RAS Sites Evergreen ResourcesCouncil record
Recorded by the council for this site.
Council site ↗
Development Control North TeamCouncil record
Recorded by the council for this site.
Council site ↗
County Boundary Flintshire Unitary Authority County BoundaryCouncil record
Recorded by the council for this site.
Council site ↗
Windfarm Consultation Area Consult National Air Traffic Services.Council record
Recorded by the council for this site.
Council site ↗
Existing Waste Management Site Consult Environmental HealthCouncil record
Recorded by the council for this site.
Council site ↗
Article 4 directionCouncil record
Some permitted development rights are withdrawn. The direction is on the council's register but not published as open data.
Council site ↗
TAN 15 Defended Zones SeaCouncil record
Recorded by the council for this site.
Council site ↗
Flood Map Seas Flood Zone 3Council record
Recorded by the council for this site.
Council site ↗
Also on the record
Coalfield, development low risk area.
Not affected
No listed building at the site · No scheduled monument at the site

Checked on 4 November 2026. Historic England, the Environment Agency, Natural England, the Mining Remediation Authority, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area504 m² (5,425 sq ft)
Energy ratingD (asset rating 79)
UseA3/A4/A5 Restaurant and Cafes/Drinking Establishments and Hot Food takeaways
HeatingHeating and Natural Ventilation

From the energy performance certificate lodged in July 2021, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in Flintshire - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Flintshire
Application type
Full - Building Works
Postcode
CH8 9SA
Received
26 Aug 2026
Validated
30 Oct 2026
Ward
Flintshire Ward Llanasa and Trelawynd
Parish
Flintshire Community Llanasa Community Council
Case officer
Show
Target decision
25 Dec 2026
Applicant
Show
Agent
PLPlanning
Freehold owner
Show

Decision outlook

Day 24 of the 56-day target. Flintshire usually decides demolitions by day 52.

Day 2432 days to the 56-day target
74%decided within 8 weeks
88%approved
49decided in the last year

Plota live figures for demolitions decided by Flintshire in the last twelve months, from validation. Flintshire decision record →

Consultation & key dates

Comments by
23 Nov 2026
Site or press notice
2 Nov 2026

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.