Flat 1-15 Kintyre House, Cold Harbour, Flat 1-5 Lewis House, Cold Harbour and Flat 1-22 Arran House, Raleana… Data via plota.co.uk

PA/25/01827/NC - Full Planning Permission Approved

Proposal

Fire safety remediation works, including the replacement of combustible timber decking, cladding and balustrades with non combustible alternatives, installation of fire-rated coverings where required and the provision of horizontal cavity barriers within wall systems. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
around 12 Nov 2025
✓
Consultation
17 Nov 2025
✓
Approved
6 Jan 2026

Approved on 6 Jan 2026 · Delegated · Last checked 16 Oct 2026

Documents 60

Plans & drawings 54

PDF 1313-DMA-05-AZZ-D-A-039006 P06 ARH - PROPOSED ELEVATIONS (RENDERED) - (SHEET 2 OF 4) Current Plan · 5 Jan 2026 View ↗ PDF 1313-DMA-05-AZZ-D-A-030006 P01 ARH - EXISTING ELEVATIONS (RENDERED) - (SHEET 2 OF 4) Current Plan · 5 Jan 2026 View ↗ PDF 1313-DMA-5-LZZ-D-A-039003 P01 LWH - PROPOSED ELEVATIONS (RENDERED) - (SHEET 1 OF 2) Current Plan · 13 Nov 2025 View ↗ PDF 1313-DMA-5-LZZ-D-A-039004 P01 LWH - PROPOSED ELEVATIONS (RENDERED) - (SHEET 2 OF 2) Current Plan · 13 Nov 2025 View ↗ PDF 1313-DMA-05-AZZ-D-A-039007 P01 ARH - PROPOSED ELEVATIONS (RENDERED) - (SHEET 3 OF 4) Current Plan · 13 Nov 2025 View ↗ PDF 1313-DMA-05-AZZ-D-A-030005 P01 ARH - EXISTING ELEVATIONS - RENDERED - SHEET 1 OF 4 Current Plan · 13 Nov 2025 View ↗ PDF 1313-DMA-05-AZZ-D-A-030007 P01 ARH - EXISTING ELEVATIONS - RENDERED - SHEET 3 OF 4 Current Plan · 13 Nov 2025 View ↗ PDF 1313-DMA-05-AZZ-D-A-030008 P01 ARH - EXISTING ELEVATIONS - RENDERED - SHEET 4 OF 4 Current Plan · 13 Nov 2025 View ↗ PDF 1313-DMA-05-AZZ-D-A-039005 P01 ARH - PROPOSED ELEVATIONS - RENDERED - SHEET 1 OF 4 Current Plan · 13 Nov 2025 View ↗ PDF 1313-DMA-05-AZZ-D-A-039008 P01 ARH - PROPOSED ELEVATIONS - RENDERED - SHEET 4 OF 4 Current Plan · 13 Nov 2025 View ↗ PDF 1313-DMA-05-KZZ-D-A-030004 P01 KNH - EXISTING ELEVATIONS RENDERED - SHEET 1 OF 3 Current Plan · 13 Nov 2025 View ↗ PDF 1313-DMA-05-KZZ-D-A-030005 P01 KNH - EXISTING ELEVATIONS RENDERED - SHEET 2 OF 3 Current Plan · 13 Nov 2025 View ↗ PDF 1313-DMA-05-KZZ-D-A-030006 P01 KNH - EXISTING ELEVATIONS RENDERED - SHEET 3 OF 3 Current Plan · 13 Nov 2025 View ↗ PDF 1313-DMA-05-KZZ-D-A-039004 P01 KNH - PROPOSED ELEVATIONS RENDERED - SHEET 1 OF 3 Current Plan · 13 Nov 2025 View ↗ PDF 1313-DMA-05-KZZ-D-A-039005 P01 KNH - PROPOSED ELEVATIONS RENDERED - SHEET 2 OF 3 Current Plan · 13 Nov 2025 View ↗ PDF 1313-DMA-05-KZZ-D-A-039006 P01 KNH - PROPOSED ELEVATIONS RENDERED - SHEET 3 OF 3 Current Plan · 13 Nov 2025 View ↗ PDF 1313-DMA-05-LZZ-D-A-030004 P01 LWH - EXISTING ELEVATIONS RENDERED - SHEET 2 OF 2 Current Plan · 13 Nov 2025 View ↗ PDF 1313-DMA-05-LZZ-D-A-030003 P01 LWH - EXISTING ELEVATIONS RENDERED - SHEET 1 OF 2 Current Plan · 13 Nov 2025 View ↗ PDF Drawing/Document Issue Register Drawing/Document Issue Register · 15 Oct 2025 View ↗ PDF 1313-DMA-03-ZZZ-D-A-010001 P05 LOCATION PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-ZZZ-D-A-011001 P04 EXISTING SITE PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-05-LZZ-D-A-017101 P03 LWH - DEMOLITION / STRIP OUT ELEVATIONS - SHEET 1 OF 2 Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-05-KZZ-D-A-017012 P04 KWH - DEMOLITION / STRIP OUT ELEVATIONS - SHEET 2 OF 3 Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-05-LZZ-D-A-017102 P03 LWH - DEMOLITION / STRIP OUT ELEVATIONS - SHEET 2 OF 2 Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-05-KZZ-D-A-017011 P04 KHN - DEMOLITION / STRIP OUT ELEVATIONS - SHEET 1 OF 3 Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-05-KZZ-D-A-017013 P04 KHN - DEMOLITION / STRIP OUT ELEVATIONS - SHEET 3 OF 3 Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-A01-D-A-017001 P05 ARH-GROUND FLOOR - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-A02-D-A-017002 P05 ARH-FIRST FLOOR - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-A03-D-A-017003 P05 ARH-SECOND FLOOR - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-A04-D-A-017004 P05 ARH-THIRD FLOOR - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-A05-D-A-017006 P05 ARH-FOURTH FLOOR - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-A06-D-A-017008 P05 ARH-FIFTH FLOOR - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-A07-D-A-017009 P05 ARH-SIXTH FLOOR - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-A08-D-A-017010 P05 AR-SEVENTH FLOOR - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-A09-D-A-017011 P05 ARH-EIGHTH FLOOR - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-AR1-D-A-017012 P02 ARH-ROOF PLAN - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-K01-D-A-017001 P05 KNH-GROUND FLOOR - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-K02-D-A-017002 P05 KNH-FIRST FLOOR - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-K03-D-A-017003 P05 KNH-SECOND FLOOR - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-K04-D-A-017004 P05 KNH-THIRD FLOOR - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-K05-D-A-017006 P05 KNH-FOURTH FLOOR - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-K06-D-A-017008 P05 KNH-FIFTH FLOOR - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-K07-D-A-017009 P05 KNH-SIXTH FLOOR - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-KR1-D-A-017010 P02 KNH-ROOF PLAN - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-L01-D-A-017001 P05 LWH-GROUND FLOOR - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-L02-D-A-017002 P05 LWH-FIRST FLOOR - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-L03-D-A-017003 P05 LWH-SECOND FLOOR - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-L04-D-A-017004 P05 LWH-THIRD FLOOR - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-L05-D-A-017005 P05 LWH-FOURTH FLOOR - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-03-LR1-D-A-017006 P05 LWH-ROOF PLAN - DEMOLITION STRIP OUT PLAN Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-05-AZZ-D-A-017014 P04 ARH-DEMOLITION STRIP OUT ELEVATION - SHEET 1 OF 4 Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-05-AZZ-D-A-017015 P04 ARH-DEMOLITION STRIP OUT ELEVATION - SHEET 2 OF 4 Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-05-AZZ-D-A-017016 P04 ARH-DEMOLITION STRIP OUT ELEVATION - SHEET 3 OF 4 Current Plan · 15 Oct 2025 View ↗ PDF 1313-DMA-05-AZZ-D-A-017017 P04 ARH-DEMOLITION STRIP OUT ELEVATION - SHEET 4 OF 4 Current Plan · 15 Oct 2025 View ↗

All documents on the council site ↗

Site constraints 11

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Archaeological priority area: Tower Hamlets APA 2.17
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Tower Hamlets AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project about 744 m away: Silvertown Tunnel
The site is about 744 m from the project boundary. Highway, decided. The project page says whether consent was granted. Also within 2 km: Thames Tideway Tunnel (decided, about 889 m); London Strategic Heat Main Project (at pre-application, about 1526 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Conservation area about 10 m away: Coldharbour
The edge of the area; work outside it can still affect its setting.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
7 listed buildings within 150 m of the postcode pin; Inside the Tower Hamlets built-up area; Public transport access: PTAL 3 (moderate), TfL 2023, for the 100 m square; Flood defence about 38 m from the postcode pin (wall, designed for a 1 in 1000 year flood); Priority habitat about 38 m away: Mudflats.
Not affected
Not green belt · No scheduled monument at the site

Checked on 2 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Tower Hamlets - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Planning Permission
Received
around 12 Nov 2025
Validated
12 Nov 2025
Ward
Blackwall and Cubitt Town
Case officer
Show
Target decision
7 Jan 2026
Decision
Permit
Decision date
6 Jan 2026
Decision level
Delegated
Applicant
Show
Agent
Planning & Development Associates Ltd

How this decision compares

Decided in 55 days from validation, about the council's usual 56 days. Approved, as 85% of full applications here are.

60%decided within 8 weeks
85%approved
557decided in the last year

Plota live figures for full applications decided by Tower Hamlets in the last twelve months, from validation. Tower Hamlets decision record →

Consultation & key dates

Neighbours
17 Nov 2025
Consultation
17 Nov 2025
Comments by
8 Dec 2025
Site or press notice
5 Dec 2025
Statutory expiry
7 Jan 2026
Env. assessment
No
Tower Hamlets
Planning Authority Score
3.9/10
Below average
#201 of 296 councils
Relevant to this application:
Householder decisions

Tower Hamlets is slower than most councils at deciding householder applications, ranking #207 out of 296. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

Slower than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Tower Hamlets decision statistics
Based on MHCLG data, the year to March 2026
84%
Overall approval rate
Below avg (87%) #229 of 296
92%
Householder approved
Above avg (90%) #167 of 296
56%
Decided in 8 weeks
Below avg (63%) #207 of 296
42%
Extended time limit
Above avg (41%) #167 of 296
63%
Minor dwellings approved
52 decided (1-9 homes)
80%
Major dwellings approved
15 decided (10+ homes)
55%
Change of use approved
67 decided
998
Total decisions
164 refused in the year to March 2026