Warehouse unit at Land At Mere Lane Magna Park Bittesby, Lutterworth

Summary of planning committee decision

Decided by Harborough Planning Committee on 13 Oct 2026, in a recorded vote.

26/01074/REMApproved

The site

Plot L is at the northwestern end of a predominantly agricultural site north and northwest of Magna Park, west of a former railway embankment.

“Site & Surroundings 1.1 The overall application site comprises an approximately 232Ha triangular parcel of predominantly agricultural land to the north and north west of Magna Park, Lutterworth. (see Figures 1 & 2). Plot L sits at the northwestern end of the site, to the north of the northern access junction, and to the west of the former railway embankment (see Figure 3).”

“The site is linked to and extends Magna Park. A full assessment of the characteristics of the site and its surroundings was carried out as part the outline planning permission. This included consideration of such matters as the site’s geology, hydrology, ecology, historic features (above and below ground) and landscape value.”

Officer report

Earlier permissions

The site has outline permission for a wider strategic distribution development, with later approvals covering infrastructure, parcel changes and an earlier layout.

“Site History 2.1 The site has an extensive Planning history, however, the relevant history is that the site benefits from Outline Planning Permission (15/01531/OUT) for the erection of up to 419,800sqm of Storage, Distribution buildings (B8) with ancillary offices (B1a), up to 3,700 sq m for a Logistics Institute of Technology (D1) with associated playing field, up to 9,000 sq m small business space (B1a, B1b), up to 300 sq m estate office with conference facility and…”

“Application 24/01650/NMA (approved January 2025) allowed for a slight adjustment between Parcels K and L enabling a building to meet the specific needs of an identified end user to be accommodated on Parcel L.”

Officer report

Why officers supported it

Officers considered the building, layout, landscaping and appearance broadly consistent with the approved parameters and unlikely to create greater impacts than assessed at outline stage.

“As set out above, the Reserved Matters proposals are broadly in accordance with the Parameters approved at Outline stage. As such, it is considered that the proposed scale will not result in a development which results in any greater impact than that which was considered at Outline stage. It is therefore considered that the Reserved Matters detail of proposed scale for MPN7 is considered to be acceptable.”

Officer report

Main planning issues

The proposal stayed within the approved height and floorspace limits, provided landscaped pedestrian and cycle routes, and did not breach the access condition.

“The overall layout accommodates a range of unit sizes, integrated into what will become an extensively landscaped setting. The proposed building is orientated to present the short gable end to the west (see Figures 10 & 12). Access to and egress from the development plot is via the new estate road which was approved as part of 22/00443/REM.”

“Objections have been raised through representations regarding the potential conflict between this application and Condition 24 of the outline planning permission. Condition 24 states: 24. Prior to the occupation of the final 35,000sqm of the development hereby permitted, improvement works to the A5 as detailed in URS Drawing No.47066811/A008/SK13 (or as amended by Road Safety Audit or Detailed Design) shall be complete and open to traffic.”

Officer report

Consultation and objections

Highways recommended conditions, several consultees raised no objection or made no comment, and no letters of objection were received.

“Consultee Date Summary National Bodies National Gas 24/08/26 No National Gas assets affected in this area Regional Bodies Leicestershire Police 06/08/26 General comments provided LCC Highways 19/08/26 Conditions recommended Archaeology 10/08/26 No further archaeological action LLFA 21/08/26 No objection Other Local Authorities Warwickshire Highways 13/08/26 No Comment Rugby BC 07/08/26 No Comment…”

Officer report

Who spoke

The Head of Development Management introduced the application, and the applicant’s agent addressed the committee.

The decision

Planning permission was approved for the reasons in the report and subject to the recommended conditions.

“Therefore, Planning Permission was approved for the reasons set out in the report and subject to the recommended conditions set out in Section 8 of the report. 8. Any Urgent Business There was no urgent business considered.”

Minutes

Councillors at the meeting

Proposed by Councillor Amanda Jane Burrell, seconded by Councillor Sindy Modha.

Source: Plota analysis of the council's minutes; parties from Democracy Club.

Sources

  • Harborough Planning Committee minutes, 13 October 2026
  • Agenda and papers (council website)

Source: Plota analysis of Harborough's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Council
Harborough
Date
Tuesday 13 October 2026
Recommendation
Officers recommended approval
Committee decided
Approved
Vote
10 for, 0 against (recorded vote)
Councillors
10Conservative 4Lib Dem 42 otherShow councillors
Minutes
The council's minutes
Meeting
Agenda and papers (council website)

Source: Plota analysis of the minutes.

This committee's year

21 decisions in the 12 months to this meeting.

Source: Plota analysis of the committee's minutes.