Wood Hall Norwich Road Hethersett Norfolk NR9 3DE Data via plota.co.uk

2026/3157 - Works to TPO trees Pending Consideration

Proposal

Oak T0009 - Reduce to monolith at 4m, Holly - Fell, Beech - Crown lift to achieve a clearance height of 2m over the cottage roof, Ash - Fell, Sycamore - Fell, Ash - Pollard at 3.5m, Poplar T2796 - Monolith to 4m, Ash - Monitor/consider pollard to 4m, Oak T0039 - Monolith to 4m Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
20 Oct 2026
Decision
Expected by 15 Dec 2026

Under consideration

No decision has been issued yet. Plota predicts a decision around 13 Nov 2026, from South Norfolk Broadland's recent tree and landscaping works.

Site constraints 8

Grade II listed: Wood Hall and Attached Garden Wall
List entry 1050536 · 26 m away · 2 more listed buildings within 150 m (2 Grade II)
Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show the other 2 with distances
Historic England ↗
Nutrient neutrality catchment: Yare Broads and Marshes
New homes and overnight accommodation must show nutrient neutrality before approval.
Natural England advice: extra wastewater in these catchments harms protected habitats, so schemes must offset their nutrient load, usually through credits.
Habitat network: Network Enhancement Zone 1
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
National infrastructure project 878 m away: Sheringham and Dudgeon Extension Projects
The site is 878 m from the project boundary. Generating station, decided. The project page says whether consent was granted. Also within 2 km: A47 - A11 Thickthorn Junction (decided, 1544 m); Hornsea Project Three Offshore Wind Farm (decided, 1565 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Tree preservation order 18 m away: The Norfolk (South Norfolk District Council) Hethersett. Tree Preservation Order 1992 No.1.; Inside the Hethersett built-up area; Priority habitat 40 m away: Deciduous woodland; Natural England's Provisional ALC map (1:250,000, 1970s) had this area as grade 3, but it predates the buildings here and the current map does not class it as farmland.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 22 October 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in South Norfolk Broadland - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Works to TPO trees
Postcode
NR9 3DE
Received
20 Oct 2026
Validated
20 Oct 2026
Ward
Hethersett
Parish
Hethersett
Target decision
15 Dec 2026
Decision level
Delegated
Applicant
Show
Agent
Norfolk Trees

Decision outlook

Day 8 of the 56-day target. South Norfolk Broadland usually decides tree and landscaping works by day 24.

Day 848 days to the 56-day target
99%decided within 8 weeks
98%approved
811decided in the last year

Plota live figures for tree and landscaping works decided by South Norfolk Broadland in the last twelve months, from validation. South Norfolk Broadland decision record →

Public comments

No public comments yet.

Last counted 22 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-15311754
Planning Portal ref
PP-15311754
Statutory expiry
15 Dec 2026
Env. assessment
No
South Norfolk Broadland
Planning Authority Score
5.9/10
Average
#106 of 296 councils
Relevant to this application:
Householder decisions

South Norfolk Broadland ranks #136 out of 296 councils for householder decision speed. Householder applications are slightly more likely to be approved here (95%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
South Norfolk Broadland decision statistics
Based on MHCLG data, the year to March 2026
93%
Overall approval rate
Above avg (87%) #50 of 296
95%
Householder approved
Above avg (90%) #71 of 296
67%
Decided in 8 weeks
Above avg (63%) #136 of 296
42%
Extended time limit
Above avg (41%) #161 of 296
82%
Minor dwellings approved
137 decided (1-9 homes)
92%
Major dwellings approved
12 decided (10+ homes)
100%
Change of use approved
33 decided
1,013
Total decisions
67 refused in the year to March 2026