Breighton Road Community Centre Breighton Road Bubwith East Riding Of Yorkshire YO8 6LL Data via plota.co.uk

26/02720/REG3 - Regulation 3 - Development by Council Pending Consideration

Proposal

Change of use and alterations to existing community centre to a dwelling including installation of new windows and doors to all elevations following blocking up and creation of window and door openings, re-location of boundary line with installation of new 1.8m high timber fencing and installation of solar panels to front and rear elevations Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
8 Oct 2026
✓
Validated
5 Nov 2026
Decision
Expected by 31 Dec 2026

Under consideration

No decision has been issued yet. Plota predicts a decision around 30 Dec 2026, from East Riding's recent changes of use.

Comments are open until 9 Dec 2026

Comment on this application ↗

Site constraints 7

Special area of conservation 189 m away: River Derwent
Work nearby can need a habitats assessment.
Harm to a protected site is only accepted where there is no alternative and an overriding public interest.
Habitat network: Network Enhancement Zone 1
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
SSSI 189 m away: River Derwent SSSI
Natural England may need consulting, depending on what is proposed.
Sites of special scientific interest are the best wildlife and geological sites in the country. Development likely to harm one is rarely permitted.
National infrastructure project 1.1 km away: East Yorkshire Solar Farm
The site is 1.1 km from the project boundary. Generating station, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Coalfield, development low risk area; Inside the Bubwith built-up area; Natural England's Provisional ALC map (1:250,000, 1970s) had this area as grade 3, but it predates the buildings here and the current map does not class it as farmland.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 12 November 2026. Historic England, the Environment Agency, Natural England, the Mining Remediation Authority, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in East Riding - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Regulation 3 - Development by Council
Postcode
YO8 6LL
Received
8 Oct 2026
Validated
5 Nov 2026
Ward
Howdenshire
Parish
Bubwith Parish Council
Case officer
Show
Target decision
31 Dec 2026
Applicant
Show
Agent
East Riding Of Yorkshire

Decision outlook

Day 18 of the 56-day target. East Riding usually decides changes of use by day 55.

Day 1838 days to the 56-day target
85%decided within 8 weeks
76%approved
191decided in the last year

Plota live figures for changes of use decided by East Riding in the last twelve months, from validation. East Riding decision record →

Public comments

No public comments yet.

Last counted 19 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-15282624
Planning Portal ref
PP-15282624
Comments by
9 Dec 2026
Env. assessment
No
East Riding
Planning Authority Score
8.1/10
Excellent
#24 of 296 overall
Relevant to this application:
Change of use

East Riding is one of the fastest councils in England for householder decisions: #7 of 296 on speed. Only 14% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

Among the fastest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
East Riding decision statistics
Based on MHCLG data, the year to March 2026
90%
Overall approval rate
Above avg (87%) #110 of 296
92%
Householder approved
Above avg (90%) #152 of 296
95%
Decided in 8 weeks
Above avg (63%) #7 of 296
14%
Extended time limit
Below avg (41%) #9 of 296
76%
Minor dwellings approved
190 decided (1-9 homes)
95%
Major dwellings approved
42 decided (10+ homes)
86%
Change of use approved
79 decided
1,887
Total decisions
198 refused in the year to March 2026