Former B&M Site Kennedy Way Immingham North East Lincolnshire DN40 1PT Data via plota.co.uk

DM/0946/25/CEA - Cert of Lawful Use/Operation - Proposed Approved

Proposal

Certificate of Lawfulness for proposed change of use of former B&M Site to a gym with associated works Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
around 3 Dec 2025
✓
Consultation
10 Dec 2025
✓
Approved
29 Jan 2026

Approved on 29 Jan 2026 · Delegated Decision · Last checked 3 Oct 2026

Site constraints 3

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
National infrastructure project 1064 m away: Immingham Green Energy Terminal
The site is 1064 m from the project boundary. Harbour, decided. The project page says whether consent was granted. Also within 2 km: Viking CCS Pipeline (decided, 1269 m); Immingham Eastern Ro-Ro Terminal (decided, 1291 m); VPI Immingham OCGT (decided, 1707 m); Hornsea Offshore Wind Farm (Zone 4) - Project Two (decided, 1779 m); Hornsea Offshore Wind Farm (Zone 4) - Project One (decided, 1779 m); H2East Pipeline: Humber to Nottinghamshire (at pre-application, 211 m); Stallingborough Combined Cycle Gas Turbine (CCGT) generating plant and Carbon Capture Plant (CCP) (at pre-application, 710 m); Humber Carbon Capture Pipeline (at pre-application, 1983 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Inside the Immingham built-up area.
Not affected
Not green belt · No listed building at the site · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in North East Lincs - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Cert of Lawful Use/Operation - Proposed
Postcode
DN40 1PT
Received
around 3 Dec 2025
Validated
3 Dec 2025
Ward
Immingham
Parish
Immingham Town Council
Case officer
Show
Target decision
28 Jan 2026
Decision
Approved
Decision date
29 Jan 2026
Decision level
Delegated Decision
Applicant
Show
Agent
D2 Planning Limited

How this decision compares

Decided in 57 days from validation, 5 days slower than North East Lincs's median of 52 for lawful development certificates. Approved, as 83% of lawful development certificates here are.

79%decided within 8 weeks
83%approved
45,796decided in the last year

Plota live figures for lawful development certificates decided across the UK in the last twelve months, from validation; too few recent lawful development certificates in North East Lincs to go on. North East Lincs decision record →

Public comments

No public comments yet.

Last counted 3 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14180499
Planning Portal ref
PP-14180499
Consultation
10 Dec 2025
Comments by
3 Jan 2026
Statutory expiry
28 Jan 2026
Env. assessment
No
North East Lincs
Planning Authority Score
5.3/10
Average
#132 of 296 councils
Relevant to this application:
Change of use

North East Lincs ranks #151 out of 296 councils for householder decision speed. 52% of applications have the time limit extended, above the 41% national average. Householder applications are more likely to be approved here than most councils, with a 97% approval rate vs 90% nationally.

More permissive than most councils
97% approved vs 90% nationally
These figures are council-wide context, not a prediction for this application. View full council performance
North East Lincs decision statistics
Based on MHCLG data, the year to March 2026
95%
Overall approval rate
Above avg (87%) #22 of 296
97%
Householder approved
Above avg (90%) #35 of 296
64%
Decided in 8 weeks
Above avg (63%) #151 of 296
52%
Extended time limit
Above avg (41%) #235 of 296
95%
Minor dwellings approved
43 decided (1-9 homes)
87%
Major dwellings approved
15 decided (10+ homes)
82%
Change of use approved
22 decided
467
Total decisions
24 refused in the year to March 2026