82 solar panels at Beech Green Barn, Main Road, Ipswich

Summary of planning committee decision

Decided by Babergh Mid Suffolk Mid Suffolk Planning Committee on 8 Apr 2026.

DC/26/00158Approved

What was proposed

The application proposed 82 ground-mounted solar panels, associated infrastructure and seven native trees connected to a private dwellinghouse.

“This application is for the erection of a ground‑mounted solar photovoltaic (PV) array comprising 82 panels, together with associated infrastructure including mounting frames, underground cabling and the planting of seven new native trees along the western boundary of the site in connection with a private dwellinghouse.”

Officer report

The site and surroundings

The site lies north of former fruit farms, near business and storage uses, within the setting of a grade II listed farmhouse and outside settlement boundaries.

“The site is to the north of the former Hemingstone Fruit Farms, which is now host to multiple business units, including a soap company, and construction company. This is within the Blue Line boundary of the applicants ownership, which also includes the ambulance and construction storage areas which are pending enforcement cases.”

“The site is within the setting of grade II listed Charity Farmhouse which is approx. 100m to the southeast.”

Officer report

Earlier applications and enforcement

Earlier applications included approvals for barn and workshop uses, while several later business and storage proposals were refused and remain subject to pending enforcement cases.

“DC/23/03872, DC/24/01438, & DC/24/01437 were refused and dismissed at appeal for ambulance storage, construction materials and equipment storage, and additional business units to the south and west of the site. At the time of the officer site visit, these were still present on site. These fall outside of the red line of this site.”

“Current enforcement cases EN/24/00655 & EN/24/00656 have been opened in response to the refusal and dismissed appeals to enforce against the continued use of the site for operations without planning permission. These cases are currently pending consideration.”

Officer report

What officers recommended

Officers recommended approval, finding the renewable energy scheme acceptable in principle and compliant with relevant requirements for landscape, heritage, ecology, amenity and infrastructure.

“LP25(1)(c) requires that the impact of on‑ and off‑site generation infrastructure is acceptable with regard to relevant policies in the Plan. The associated infrastructure is minimal, comprising only underground cabling linking the array to the dwelling. No substations, control buildings, overhead cables or external fencing related to power infrastructure are required.”

“The proposal complies with all criteria of LP25(1) and accords with SP03 in establishing the principle of development for renewable energy outside the settlement boundary. The development is small in scale, well‑integrated with the host dwelling, and delivers domestic‑level renewable energy generation without giving rise to harmful environmental, heritage, landscape, amenity or infrastructural impacts.”

Officer report

Consultation responses

The parish council made no comment; Environmental Health and the Heritage Team raised no objections, while the Ecologist requested biodiversity conditions.

“Environmental Health - Noise/Odour/Light/Smoke Comments Received - 03/02/2026 & 19/02/2026”

“No objection, subject to conditions for biodiversity enhancements and compliance with the recommendations of the ecology report and precautionary method statement.”

Officer report

Public representations

No letters, emails or online comments had been received when the report was prepared.

“At the time of writing this report no letters/emails/online comments have been received. An update shall be provided as necessary either via Tabled Papers or verbally at the meeting.”

“All individual representations are counted and considered. Repeated and/or additional communication from a single individual will be counted as one representation.”

Officer report

Who took part

The case officer introduced the application, officers answered Members’ questions, and Members considered a representation from a ward Member.

What Members discussed

Members debated the energy output, proposed panel numbers, land use, panel location, screening, biodiversity and whether energy should be restricted to domestic use.

“Members debated the application on issues including: the relevance to the application of the amount of energy produced and the use of that energy, and the proposed number of panels to be installed.”

“Members debated the application further on issues including; the existing use of the land, the proposed number of panels, the potential BNG, the level of energy being generated, and the location of the site.”

Minutes

The decision

Planning permission was granted with conditions covering construction, biodiversity, ecology, drainage, restoration, inverters, panel finishes, landscaping and lighting.

“That planning permission be GRANTED subject to the following conditions and informatives and any others as may be deemed necessary by the Chief Planning Officer:”

“Conditions: • Standard time limit • Approved Plans • Construction Management Plan • Biodiversity Enhancements • Compliance with Ecology Report • Compliance with Flood Risk Assessment • Decommissioning and restoration plan • Inverter Location • PV Panel Anti-Reflective Finishes • Landscape implementation and retention for 5 years • No lighting to be installed…”

Minutes

Sources

  • Babergh Mid Suffolk Mid Suffolk Planning Committee minutes, 8 April 2026
  • Agenda and papers (council website)

Source: Plota analysis of Babergh Mid Suffolk's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.

Committee decisions and nationwide planning applications, in one API

The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.

See the API →

At the meeting

Date
Wednesday 8 April 2026
Recommendation
Officers recommended approval
Committee decided
Approved
Vote
5 for, 1 against, 1 abstained
Minutes
The council's minutes
Meeting
Agenda and papers (council website)

Source: Plota analysis of the minutes.

This committee's year

21 decisions in the 12 months to this meeting.

Source: Plota analysis of the committee's minutes.

Every decision by this council's committees →