Waterbutts Cottage And Westland Cottage Mill Lane Byfleet West Byfleet Surrey KT14 7RS Data via plota.co.uk

PLAN/2025/0708 - Full Planning Application Refused

Proposal

Proposed alterations to Waterbutts and Westland Cottages to form a single dwelling house. Erection of porch and alterations to fenestration north-east elevation. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
around 9 Oct 2025
✗
Refused
4 Dec 2025
Appeal
Appeal Pending

Refused on 4 Dec 2025 · Delegated · Last checked 11 Oct 2026

Documents 26

All documents on the council site ↗

Site constraints 7

Green belt: London
Inappropriate development needs very special circumstances.
Green belt policy allows a short list of exceptions, such as limited extensions and replacement buildings. Anything else needs very special circumstances that clearly outweigh the harm. Some green belt land can count as grey belt, where it does not strongly serve the green belt's purposes. The council decides this in its green belt assessment or on each application, so we do not mark it here.
Read the government guidance ↗
In flood zones plus climate change
Inside the extent flood zones 2 and 3 could reach with climate change: the Central allowance for the 2080s on rivers, the Upper End allowance for sea level rise to 2125. From rivers. Defences are not counted.
The Environment Agency flood map for planning. Councils use it to decide when a flood risk assessment and the sequential test are needed. It is indicative and does not show whether a particular property will flood.
Flood map ↗
Agricultural land, grade 3a
Best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s), which most planning maps still show, had this area as grade 2. The predicted grade is Defra's current estimate; only a site survey settles it.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
National infrastructure project 264 m away: M25 junction 10/A3 Wisley interchange improvement
The site is 264 m from the project boundary. Highway, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Habitat network: Network Expansion Zone
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
2 listed buildings within 150 m
Nearest: Manor House and Manorside West, Grade II*, 61 m away · 1 Grade II*, 1 Grade II
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show all 2 with distances
Historic England ↗
Also on the record
Priority habitat 28 m away: No main habitat but additional habitats present.
Not affected
Outside flood zones 2 and 3 · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area173 m² (1,862 sq ft)
Energy ratingF (29 out of 100), could reach E
PropertySemi-detached house, 9 habitable rooms
BuiltBefore 1900
HeatingBoiler and radiators, oil
WallsSolid brick, as built, no insulation (assumed)

From the energy performance certificate lodged in May 2010, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in Woking - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Woking
Application type
Full Planning Application
Postcode
KT14 7RS
Received
around 9 Oct 2025
Validated
9 Oct 2025
Ward
Byfleet And West Byfleet
Case officer
Show
Target decision
4 Dec 2025
Decision
Refused
Decision date
4 Dec 2025
Decision level
Delegated
Applicant
Show
Agent
Both Creative

How this decision compares

Decided in 56 days from validation, 13 days faster than Woking's median of 69 for full applications. Refused, as 29% of full applications here are.

31%decided within 8 weeks
71%approved
12%go to committee

Plota live figures for full applications decided by Woking in the last twelve months, from validation. Woking decision record →

Public comments

No public comments yet.

9 neighbours consulted · Last counted 11 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Comments by
5 Nov 2025
Statutory expiry
4 Dec 2025
Env. assessment
No
Woking
Planning Authority Score
3.1/10
Poor
#234 of 296 councils
Relevant to this application:
Householder decisions

Woking is slower than most councils at deciding householder applications, ranking #217 out of 296. Woking is also one of the strictest councils - it refuses more householder applications than almost any other, with only 84% approved vs 90% nationally.

One of the strictest councils
only 84% approved vs 90% nationally
These figures are council-wide context, not a prediction for this application. View full council performance
Woking decision statistics
Based on MHCLG data, the year to March 2026
82%
Overall approval rate
Below avg (87%) #254 of 296
84%
Householder approved
Below avg (90%) #258 of 296
54%
Decided in 8 weeks
Below avg (63%) #217 of 296
38%
Extended time limit
Below avg (41%) #136 of 296
55%
Minor dwellings approved
40 decided (1-9 homes)
100%
Major dwellings approved
1 decided (10+ homes)
72%
Change of use approved
18 decided
736
Total decisions
133 refused in the year to March 2026

Freehold boundary: © Crown copyright and database rights 2026, HM Land Registry. Polygons © Crown copyright and database rights 2026 Ordnance Survey 100026316. Conditions of use

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.