120-132 Pennington Street, London, E1W 2BB Data via plota.co.uk

PA/26/01071/A1 - Full Planning Permission Registered

Proposal

Demolition of existing building. Erection of part 8, part 7 and part 6-storey building comprising residential units (Use Class C3) and commercial space (Flexible Use Class E/Sui Generis [Recording Studio]), with associated amenity and play space, accessible car parking, cycle parking, landscaping, changes to existing access points and other associated works. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
28 Jul 2026
✓
Consultation
6 Aug 2026
Decision
Expected by 27 Oct 2026

Under consideration

No decision has been issued yet. Plota predicts a decision by 27 Oct 2026, from Tower Hamlets's recent commercial and major works.

The consultation period closed on 6 Sept 2026.

Documents 96

Statements & assessments 53

PDF D12 AND D5 FIRE STATEMENT Report · 15 Jul 2026 View ↗ PDF UTILITY STATEMENT- PART 9 Report · 22 Jun 2026 View ↗ PDF UTILITY STATEMENT- PART 10 Report · 22 Jun 2026 View ↗ PDF UTILITY STATEMENT- PART 11 Report · 22 Jun 2026 View ↗ PDF UTILITY STATEMENT- PART 1 Report · 22 Jun 2026 View ↗ PDF UTILITY STATEMENT- PART 2 Report · 22 Jun 2026 View ↗ PDF UTILITY STATEMENT- PART 3 Report · 22 Jun 2026 View ↗ PDF UTILITY STATEMENT- PART 4 Report · 22 Jun 2026 View ↗ PDF UTILITY STATEMENT- PART 5 Report · 22 Jun 2026 View ↗ PDF UTILITY STATEMENT- PART 6 Report · 22 Jun 2026 View ↗ PDF UTILITY STATEMENT- PART 7 Report · 22 Jun 2026 View ↗ PDF UTILITY STATEMENT- PART 8 Report · 22 Jun 2026 View ↗ PDF PHASE 1 GEO-ENVIRONMENTAL PRELIMINARY RISK ASSESSMENT - PART 1 Report · 22 Jun 2026 View ↗ PDF PHASE 1 GEO-ENVIRONMENTAL PRELIMINARY RISK ASSESSMENT - PART 2 Report · 22 Jun 2026 View ↗ PDF PHASE 1 GEO-ENVIRONMENTAL PRELIMINARY RISK ASSESSMENT - PART 3 Report · 22 Jun 2026 View ↗ PDF PHASE 1 GEO-ENVIRONMENTAL PRELIMINARY RISK ASSESSMENT - PART 4 Report · 22 Jun 2026 View ↗ PDF PHASE 1 GEO-ENVIRONMENTAL PRELIMINARY RISK ASSESSMENT - PART 5 Report · 22 Jun 2026 View ↗ PDF HERITAGE TOWNSCAPE AND VISUAL IMPACT ASSESSMENT - PART 1 Report · 22 Jun 2026 View ↗ PDF HERITAGE TOWNSCAPE AND VISUAL IMPACT ASSESSMENT - PART 2 Report · 22 Jun 2026 View ↗ PDF HERITAGE TOWNSCAPE AND VISUAL IMPACT ASSESSMENT - PART 3 Report · 22 Jun 2026 View ↗ PDF DRAINAGE STRATEGY ( INC. SUDS) AND FOUL SEWAGE ASSESSMENT- PART 2 Report · 22 Jun 2026 View ↗ PDF DRAINAGE STRATEGY ( INC. SUDS) AND FOUL SEWAGE ASSESSMENT- PART 3 Report · 22 Jun 2026 View ↗ PDF DRAINAGE STRATEGY ( INC. SUDS) AND FOUL SEWAGE ASSESSMENT- PART 4 Report · 22 Jun 2026 View ↗ PDF DRAINAGE STRATEGY ( INC. SUDS) AND FOUL SEWAGE ASSESSMENT- PART 1 Report · 22 Jun 2026 View ↗ PDF TRANSPORT ASSESSMENT - PART 1 Report · 22 Jun 2026 View ↗ PDF PRELIMINARY ECOLOGICAL APPRAISAL AND PRELIMINARY BAT ROOST ASSESSMENT Report · 22 Jun 2026 View ↗ PDF TRANSPORT ASSESSMENT - PART 2 Report · 22 Jun 2026 View ↗ PDF ENERGY STATEMENT Report · 22 Jun 2026 View ↗ PDF STATEMENT OF COMMUNITY INVOLVEMENT Report · 22 Jun 2026 View ↗ PDF BAT SURVEY REPORT Report · 22 Jun 2026 View ↗ PDF NOISE IMPACT ASSESSMENT Report · 22 Jun 2026 View ↗ PDF AIR QUALITY ASSESSMENT Report · 22 Jun 2026 View ↗ PDF BIODIVERSITY NET GAIN ASSESSMENT Report · 22 Jun 2026 View ↗ PDF EXTERNAL LIGHTING ASSESSMENT Report · 22 Jun 2026 View ↗ PDF HEALTH IMPACT ASSESSMENT Report · 22 Jun 2026 View ↗ PDF SUSTAINABILITY STATEMENT Report · 22 Jun 2026 View ↗ PDF PART 2 Design & Access Statement · 22 Jun 2026 View ↗ PDF PART 3 Design & Access Statement · 22 Jun 2026 View ↗ PDF PART 4 Design & Access Statement · 22 Jun 2026 View ↗ PDF PART 5 Design & Access Statement · 22 Jun 2026 View ↗ PDF PART 6 Design & Access Statement · 22 Jun 2026 View ↗ PDF PART 7 Design & Access Statement · 22 Jun 2026 View ↗ PDF PART 8 Design & Access Statement · 22 Jun 2026 View ↗ PDF PART 9 Design & Access Statement · 22 Jun 2026 View ↗ PDF PART 10 Design & Access Statement · 22 Jun 2026 View ↗ PDF PART 11 Design & Access Statement · 22 Jun 2026 View ↗ PDF PART 12 Design & Access Statement · 22 Jun 2026 View ↗ PDF PART 1 Design & Access Statement · 22 Jun 2026 View ↗ PDF FINANCIAL VIABILITY ASSESSMENT Report · 22 Jun 2026 View ↗ PDF Planning Statement Planning Statement · 22 Jun 2026 View ↗ PDF GATEWAY 1 FIRE STATEMENT Correspondence · 22 Jun 2026 View ↗ PDF ARCHAEOLOGICAL DESK BASED ASSESSMENT Report · 22 Jun 2026 View ↗ PDF LANDSCAPE STATEMENT Report · 22 Jun 2026 View ↗

Plans & drawings 39

PDF FRAMEWORK TRAVEL PLAN Report · 22 Jun 2026 View ↗ PDF OUTLINE CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN Report · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P0)203 P1 EXISTING EAST ELEVATION Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P0)003 P1 EXISTING GROUND FLOOR PLAN Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P0)202 P1 EXISTING NORTH ELEVATION Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P0)300 P1 EXISTING SECTION AA (EAST- WEST) Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P0)301 P1 EXISTING SECTION BB (NORTH- SOUTH) Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P0)002 P1 EXISTING SITE PLAN Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P0)200 P1 EXISTING SOUTH ELEVATION Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P0)201 P1 EXISTING WEST ELEVATION Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P0)001 P1 SITE LOCATION PLAN Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P1)202 P4 PROPOSED NORTH ELEVATION Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P1)201 P4 PROPOSED WEST ELEVATION Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P1)203 P4 PROPOSED EAST ELEVATION Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P4)002 P2 BAY STUDY 2 - MASONRY BAY TO BALCONY- WINTER GARDENS Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P4)003 P2 BAY STUDY 3 - MASONRY BAY TO HABITABLE ROOM Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P4)001 P2 BAY STUDY 1 - METAL BAY Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P4)004 P2 BAY STUDY 4 - REAR EXTERNAL WALKWAY BAY Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P1)113 P4 PROPOSED SECOND-THIRD FLOOR PLAN Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P1)114 P4 PROPOSED FOURTH-FIFTH FLOOR PLAN Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P1)111 P4 PROPOSED FIRST FLOOR PLAN Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P1)116 P4 PROPOSED SIXTH FLOOR PLAN Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P1)300 P4 SECTION AA (EAST-WEST) Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P1)117 P3 PROPOSED SEVENTH FLOOR PLAN Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P1)110 P5 PROPOSED GROUND FLOOR PLAN Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P3)101 P1 TWO BED M4 (2) FLAT TYPES Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P3)100 P1 ONE BED M4(2) FLAT TYPES Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P1)304 P4 SECTION EE (NORTH-SOUTH) Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P3)103 P1 THREE BED M4(2) FLAT TYPES Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P1)302 P4 SECTION CC (EAST-WEST) Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P1)301 P4 SECTION BB (NORTH-SOUTH) Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P3)104 P1 FOUR BED M4(3) FLAT TYPES Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P1)305 P4 SECTION FF (NORTH-SOUTH) Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P3)102 P1 TWO BED M4(3) FLAT TYPES Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P1)303 P4 SECTION DD (NORTH-SOUTH) Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P1)120 P4 PROPOSED ROOF PLAN Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P1)005 P1 PROPOSED ROOF TOP SECTION (NORTH-SOUTH) Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P1)100 P3 PROPOSED SITE PLAN Current Plan · 22 Jun 2026 View ↗ PDF 0726-BPA-ZZ-XX-DR-A-(P1)200 P4 PROPOSED SOUTH ELEVATION Current Plan · 22 Jun 2026 View ↗

All documents on the council site ↗

Site constraints 9

National infrastructure project: Thames Tideway Tunnel
The site is inside the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, 537 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Archaeological priority area: Tower Hamlets APA 2.6
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Tower Hamlets AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
9 listed buildings within 150 m
Nearest: A Warehouse (Skin Floor) Including Vaults Extending Under Wapping Lane, Grade I, 27 m away · 2 Grade I, 7 Grade II
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show all 9 with distances
Historic England ↗
Scheduled monument 151 m away: Roman Bath House, Shadwell
Its setting is a consideration for work nearby.
Nationally important archaeology protected by the Secretary of State. Work that affects the monument or its setting is rarely permitted.
Historic England ↗
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
Conservation area 49 m away: St George in the East; Inside the Tower Hamlets built-up area; Public transport access: PTAL 4 (good), TfL 2023, for the 100 m square.
Not affected
Outside flood zones 2 and 3 · Not green belt

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Building

Floor area141 m² (1,518 sq ft)
Energy ratingD (asset rating 76)
UseB1 Offices and Workshop businesses
HeatingAir Conditioning

From the energy performance certificate lodged in January 2018, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in Tower Hamlets - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Planning Permission
Postcode
E1W 2BB
Received
28 Jul 2026
Validated
28 Jul 2026
Ward
St Katharines and Wapping
Case officer
Show
Target decision
27 Oct 2026
Decision level
Delegated
Applicant
Show
Agent
Rapleys

Decision outlook

Day 73, past the statutory target. 67% of commercial and major works in Tower Hamlets are decided within thirteen weeks, which runs to 27 Oct 2026; extensions of time are common, and the council need not decide on the day. Last seen undecided on 2 Oct 2026.

Day 7317 days past the 56-day target
37%decided within 8 weeks
85%approved
33decided in the last year

Plota live figures for commercial and major works decided by Tower Hamlets in the last twelve months, from validation. Tower Hamlets decision record →

Consultation & key dates

Neighbours
6 Aug 2026
Consultation
6 Aug 2026
Comments by
6 Sept 2026
Site or press notice
5 Aug 2026
Statutory expiry
27 Oct 2026
Env. assessment
No
Tower Hamlets
Planning Authority Score
3.9/10
Below average
#201 of 296 councils
Relevant to this application:
Householder decisions

Tower Hamlets is slower than most councils at deciding householder applications, ranking #207 out of 296. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

Slower than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Tower Hamlets decision statistics
Based on MHCLG data, the year to March 2026
84%
Overall approval rate
Below avg (87%) #229 of 296
92%
Householder approved
Above avg (90%) #167 of 296
56%
Decided in 8 weeks
Below avg (63%) #207 of 296
42%
Extended time limit
Above avg (41%) #167 of 296
63%
Minor dwellings approved
52 decided (1-9 homes)
80%
Major dwellings approved
15 decided (10+ homes)
55%
Change of use approved
67 decided
998
Total decisions
164 refused in the year to March 2026

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.