Marchwood Military Port, Cracknore Hard, Marchwood SO40 4ZG Data via plota.co.uk

26/10859 - Full Planning Permission Registered

Proposal

Demolition of existing buildings, alteration and erection of fencing, provision of vehicular ramps and access, resurfacing & erection of lighting and CCTV columns, with other associated works and drainage details. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
4 Sept 2026
✓
Validated
7 Sept 2026
✓
Consultation
9 Sept 2026
Decision
Expected by 7 Dec 2026

Under consideration

No decision has been issued yet. Plota predicted a decision around 23 Nov 2026; it is now day 77.

The consultation period closed on 27 Oct 2026.

Documents 85

Statements & assessments 21

PDF CONSULTEE - ECOLOGIST Consultee Comment · 18 Nov 2026 View ↗ PDF HABITATS REGULATIONS ASSESSMENT SCREENING REPORT Applications Processing · 18 Nov 2026 View ↗ PDF CONSULTEE RESPONSE LETTER_SURFACE_FOUL_WATER_DRAINAGE_STRATEGY_PART_4 Applications Processing · 11 Nov 2026 View ↗ PDF DRAINAGE STRATEGY REPORT Applications Processing · 3 Nov 2026 View ↗ PDF WATERCOURSE BNG METRIC Applications Processing · 5 Oct 2026 View ↗ PDF BNG REPORT Applications Processing · 5 Oct 2026 View ↗ PDF TRANSPORT NOTE Submitted Applications · 7 Sept 2026 View ↗ PDF BNG METRIC Submitted Applications · 7 Sept 2026 View ↗ PDF DRAINAGE SPECIFICATION Submitted Applications · 7 Sept 2026 View ↗ PDF FLOOD RISK ASSESSMENT Submitted Applications · 7 Sept 2026 View ↗ PDF LIGHTING PLANNING STATEMENT Submitted Applications · 7 Sept 2026 View ↗ PDF RIVER CONDITION ASSESSMENT & BNG OF CRACKNORE HARD STREAM Submitted Applications · 7 Sept 2026 View ↗ PDF BIODIVERSITY CHECKLIST Submitted Applications · 7 Sept 2026 View ↗ PDF PHASE 5 - PHASE II BAT SURVEY REPORT Submitted Applications · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HDG-05-DE-C-0505 DRAINAGE STANDARD DETAILS SHEET 5 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HDG-05-DR-C-0502 DRAINAGE LAYOUT SHEET 2 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HDG-05-DR-C-0501 DRAINAGE LAYOUT SHEET 1 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HDG-05-DE-C-0502 DRAINAGE STANDARD DETAILS SHEET 2 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HDG-05-DE-C-0504 DRAINAGE STANDARD DETAILS SHEET 4 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HDG-05-DE-C-0501 DRAINAGE STANDARD DETAILS SHEET 1 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HDG-05-DE-C-0503 DRAINAGE STANDARD DETAILS SHEET 3 Plans · 7 Sept 2026 View ↗

Plans & drawings 35

PDF DEMOLITION ENVIRONMENTAL MANAGEMENT PLAN - PHASE 5 Submitted Applications · 7 Sept 2026 View ↗ PDF FENCING & GATES Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HGN-05-DR-C-0602 ISOPACHYTE LAYOUT SHEET 2 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HDG-05-DR-C-0511 CATCHMENT PLAN SHEET 1 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-GEN-05-DR-C-1003 PHASING PLAN SHEET 2 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-GEN-05-DR-C-1002 PHASING PLAN SHEET 1 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HDG-05-DE-C-0552 PETROL INTERCEPTOR DETAIL SHEET 2 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HDG-05-DE-C-0551 PETROL INTERCEPTOR DETAIL SHEET 1 Plans · 7 Sept 2026 View ↗ PDF LOCATION PLAN Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HGN-05-DR-C-0102 GENERAL ARRANGEMENT SHEET 2 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HGN-05-DR-C-0101 GENERAL ARRANGEMENT SHEET 1 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HGL-05-DR-C-1401 LIGHTING SCHEMATIC Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HGL-05-DR-C-1311 LIGHTING ISOLUX LAYOUT Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HGL-05-DR-C-1301 LIGHTING LAYOUT SHEET 1 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HFE-05-DR-C-0301 FENCING LAYOUT SHEET 1 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HFE-05-DR-C-0302 FENCING LAYOUT SHEET 2 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HDG-05-DR-C-0512 CATCHMENT PLAN SHEET 2 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HDG-05-DR-C-0522 EXCEEDANCE PLAN SHEET 2 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HGL-05-DR-C-1302 LIGHTING LAYOUT SHEET 2 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HDG-05-DR-C-0521 EXCEEDANCE PLAN SHEET 1 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-VUT-05-DR-C-0102 EXISTING UTILITIES SHEET Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-VUT-05-DR-C-0101 EXISTING UTILITIES SHEET 1 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HSC-05-DR-C-0202 SITE CLEARANCE SHEET 2 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HPV-05-DR-C-0702 PAVEMENT, KERBS, FOOTWAYS AND PAVED AREAS SHEET 2 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HPV-05-DR-C-0701 PAVEMENT, KERBS, FOOTWAYS AND PAVED AREAS SHEET 1 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HSC-05-DR-C-0201 SITE CLEARANCE SHEET 1 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HPV-05-DE-C-0701 PAVEMENT STANDARD DETAILS Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HGN-05-DR-C-3001 CROSS SECTIONS Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HKF-05-DE-C-1101 KERB DETAILS Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HGN-05-DR-C-0601 ISOPACHYTE LAYOUT SHEET 1 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HGN-05-DR-C-0123 VEHICLE TRACKING SHEET 3 OF 3 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HGN-05-DR-C-0121 VEHICLE TRACKING SHEET 1 OF 3 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HGN-05-DR-C-0122 VEHICLE TRACKING SHEET 2 OF 3 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HGN-05-DR-C-0111 PROPOSED CONTOURS SHEET 1 Plans · 7 Sept 2026 View ↗ PDF 1620019054-RAM-HGN-05-DR-C-0112 PROPOSED CONTOURS SHEET 2 Plans · 7 Sept 2026 View ↗

All documents on the council site ↗

Site constraints 8

Nutrient neutrality catchment: Solent: Includes Chichester and Langstone Harbours SPA/Ramsar, Solent and Southampton Water SPA/Ramsar, Solent Maritime SAC, Portsmouth Harbour SPA/Ramsar
New homes and overnight accommodation must show nutrient neutrality before approval.
Natural England advice: extra wastewater in these catchments harms protected habitats, so schemes must offset their nutrient load, usually through credits.
Article 4 direction
Hovercraft in the Solent. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
In flood zones plus climate change
Inside the extent flood zones 2 and 3 could reach with climate change: the Central allowance for the 2080s on rivers, the Upper End allowance for sea level rise to 2125. From the sea. Defences are not counted.
The Environment Agency flood map for planning. Councils use it to decide when a flood risk assessment and the sequential test are needed. It is indicative and does not show whether a particular property will flood.
Flood map ↗
Habitat network: Network Enhancement Zone 2
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
SSSI 203 m away: Hythe to Calshot Marshes SSSI
Natural England may need consulting, depending on what is proposed.
Sites of special scientific interest are the best wildlife and geological sites in the country. Development likely to harm one is rarely permitted.
Special protection area 315 m away: Solent and Dorset Coast
Work nearby can need a habitats assessment.
Harm to a protected site is only accepted where there is no alternative and an overriding public interest.
Also on the record
National infrastructure project: Solent Gateway 2, at pre-application; Inside the Marchwood built-up area.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in New Forest (District) - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Planning Permission
Postcode
SO40 4ZG
Received
4 Sept 2026
Validated
7 Sept 2026
Ward
Marchwood & Eling
Parish
Marchwood
Case officer
Show
Target decision
7 Dec 2026
Agent
Savills UK Limited

Decision outlook

Day 77, past the statutory target. 84% of demolitions in New Forest (District) are decided within thirteen weeks, which runs to 7 Dec 2026; extensions of time are common, and the council need not decide on the day. Last seen undecided on 21 Nov 2026.

Day 7721 days past the 56-day target
59%decided within 8 weeks
94%approved
71decided in the last year

Plota live figures for demolitions decided by New Forest (District) in the last twelve months, from validation. New Forest (District) decision record →

Public comments

No public comments yet.

Last counted 21 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-15117325
Planning Portal ref
PP-15117325
Consultation
9 Sept 2026
Comments by
27 Oct 2026
Env. assessment
No
New Forest (District)
Planning Authority Score
7.8/10
Good
#29 of 296 overall
Relevant to this application:
Householder decisions

New Forest (District) is faster than most councils at deciding householder applications: #37 of 296 on speed. Householder applications are slightly more likely to be approved here (96%) than the national average (90%).

Faster than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
New Forest (District) decision statistics
Based on MHCLG data, the year to March 2026
90%
Overall approval rate
Above avg (87%) #112 of 296
96%
Householder approved
Above avg (90%) #54 of 296
80%
Decided in 8 weeks
Above avg (63%) #37 of 296
35%
Extended time limit
Below avg (41%) #103 of 296
69%
Minor dwellings approved
87 decided (1-9 homes)
91%
Major dwellings approved
11 decided (10+ homes)
78%
Change of use approved
40 decided
885
Total decisions
85 refused in the year to March 2026