GREATFIELDS SECONDARY SCHOOL Net Street, Barking, Barking And Dagenham, IG11 7QG Data via plota.co.uk

25/00672/FULL - Full Planning Permission Approved

Proposal

Construction of a staff car park within Zone 2B of Greatfields School including associated cycle parking and hard and soft landscaping Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
30 Apr 2025
✓
Approved
17 Jul 2025

Approved on 17 Jul 2025 · Last checked 9 Nov 2026

Site constraints 7

Article 4 direction
HMO Article 4. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
In flood zones plus climate change
Inside the extent flood zones 2 and 3 could reach with climate change: the Central allowance for the 2080s on rivers, the Upper End allowance for sea level rise to 2125. From the sea. Defences are not counted.
The Environment Agency flood map for planning. Councils use it to decide when a flood risk assessment and the sequential test are needed. It is indicative and does not show whether a particular property will flood.
Flood map ↗
Air quality management area: Barking and Dagenham AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project 1 km away: Thames Tideway Tunnel
The site is 1 km from the project boundary. Waste water treatment, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
Also on the record
Inside the Barking and Dagenham built-up area; Public transport access: PTAL 2 (poor), TfL 2023, for the 100 m square.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 9 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Barking and Dagenham - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Planning Permission
Postcode
IG11 7QG
Received
30 Apr 2025
Validated
30 Apr 2025
Ward
Gascoigne
Case officer
Show
Target decision
31 Jul 2025
Decision
Approved
Decision date
17 Jul 2025
Applicant
Show
Agent
RENEW Planning Limited

How this decision compares

Decided in 78 days from validation, 22 days slower than Barking and Dagenham's median of 56 for full applications. Approved, as 64% of full applications here are.

54%decided within 8 weeks
64%approved
253decided in the last year

Plota live figures for full applications decided by Barking and Dagenham in the last twelve months, from validation. Barking and Dagenham decision record →

Consultation & key dates

Statutory expiry
31 Jul 2025
Barking and Dagenham
Planning Authority Score
6.4/10
Average
#81 of 296 overall
Relevant to this application:
Householder decisions

Barking and Dagenham is one of the fastest councils in England for householder decisions: #9 of 296 on speed. Only 16% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Barking and Dagenham is also one of the strictest councils - it refuses more householder applications than almost any other, with only 68% approved vs 90% nationally.

Among the fastest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Barking and Dagenham decision statistics
Based on MHCLG data, the year to March 2026
64%
Overall approval rate
Below avg (87%) #296 of 296
68%
Householder approved
Below avg (90%) #296 of 296
93%
Decided in 8 weeks
Above avg (63%) #9 of 296
16%
Extended time limit
Below avg (41%) #13 of 296
43%
Minor dwellings approved
86 decided (1-9 homes)
100%
Major dwellings approved
7 decided (10+ homes)
28%
Change of use approved
80 decided
725
Total decisions
260 refused in the year to March 2026