Belvedere and Mandeville Place, Queen Elizabeth Olympic Park, London E20 2AA Data via plota.co.uk

PA/26/01509/S - Non-material amendment (TCPA S96a) Approved

Proposal

Application for a Non-Material Amendment (S96a) to planning permission ref. dated 25/11/2024. Amendment: To alter Condition 3 to revise the cycle track works, planting areas, rain gardens, tree planting locations, seating, crossing points, pedestrian access arrangements, and lighting column provision within Phase 1 of the approved development. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
around 27 Aug 2026
✓
Approved
7 Sept 2026

Approved on 7 Sept 2026 · Delegated · Last checked 23 Sept 2026

Documents 24

All documents on the council site ↗

Site constraints 11

Archaeological priority area: Tower Hamlets APA 3.2
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Tower Hamlets AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Conservation area about 14 m away: Fish Island
The edge of the area; work outside it can still affect its setting.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
Opportunity area
Where the London Plan expects significant growth.
Boundaries are indicative and the borough holds the detailed plan.
National infrastructure project about 1.1 km away: Thames Tideway Tunnel
The site is about 1.1 km from the project boundary. Waste water treatment, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Radon affected area, class 2; Flood defence about 19 m from the postcode pin (engineered high ground, designed for a 1 in 50 year flood); Inside the Tower Hamlets built-up area; Public transport access: PTAL 2 (poor), TfL 2023, for the 100 m square; Designated open space about 15 m away; Metropolitan Open Land about 65 m away.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 2 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI), Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Tower Hamlets - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Non-material amendment (TCPA S96a)
Postcode
E20 2AA
Received
around 27 Aug 2026
Validated
27 Aug 2026
Ward
Bow East
Case officer
Show
Target decision
24 Sept 2026
Decision
Permit
Decision date
7 Sept 2026
Decision level
Delegated
Applicant
Show

Consultation & key dates

Statutory expiry
24 Sept 2026
Env. assessment
No
Tower Hamlets
Planning Authority Score
3.9/10
Below average
#201 of 296 overall
Relevant to this application:
Householder decisions

Tower Hamlets is slower than most councils at deciding householder applications: #207 of 296 on speed. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

Slower than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Tower Hamlets decision statistics
Based on MHCLG data, the year to March 2026
84%
Overall approval rate
Below avg (87%) #229 of 296
92%
Householder approved
Above avg (90%) #167 of 296
56%
Decided in 8 weeks
Below avg (63%) #207 of 296
42%
Extended time limit
Above avg (41%) #167 of 296
63%
Minor dwellings approved
52 decided (1-9 homes)
80%
Major dwellings approved
15 decided (10+ homes)
55%
Change of use approved
67 decided
998
Total decisions
164 refused in the year to March 2026