12 Danehurst New Road, Tiptoe, Lymington SO41 6FW Data via plota.co.uk

26/00862FULL - Full Application Pending Decision

Proposal

Conversion of existing outbuilding to form habitable accommodation linked to the main use of the house Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
10 Aug 2026
✓
Consultation
10 Aug 2026
✓
Validated
13 Aug 2026
Decision
Expected by 5 Oct 2026

Under consideration

No decision has been issued yet. Plota predicted a decision around 9 Oct 2026; it is now day 57.

The consultation period closed on 14 Sept 2026.

Site constraints 8

Aerodrome safeguarding zone
Nutrient neutrality catchment: Solent: Includes Chichester and Langstone Harbours SPA/Ramsar, Solent and Southampton Water SPA/Ramsar, Solent Maritime SAC, Portsmouth Harbour SPA/Ramsar
New homes and overnight accommodation must show nutrient neutrality before approval.
Natural England advice: extra wastewater in these catchments harms protected habitats, so schemes must offset their nutrient load, usually through credits.
New Forest National Park
The park authority decides applications here. Great weight to conserving the landscape; major development restricted.
Landscape, scenic beauty and wildlife carry great weight, and major development is only allowed in exceptional circumstances.
2 Article 4 directions
Article 4 Direction Np New Forest Campsite · Article 4 Direction Np New Forest Recreational Campsite. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
National infrastructure project: Navitus Bay Wind Park
The site is inside the project boundary. Generating station, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Aerodrome safeguarding zoneCouncil record
Recorded by the council for this site.
Council site ↗
Also on the record
SSSI 475 m away: The New Forest SSSI; Inside the Tiptoe built-up area; Natural England's Provisional ALC map (1:250,000, 1970s) had this area as grade 4, but it predates the buildings here and the current map does not class it as farmland.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Sales history 4

Last sold for £710,000 in January 2023. Detached house, freehold.

18 January 2023£710,000
24 March 2021£610,000
8 November 2010£440,000
22 May 1997£150,000

Sale prices from HM Land Registry's price paid record, matched to this application by its address.

Building

Floor area127 m² (1,367 sq ft)
Energy ratingD (61 out of 100), could reach C
PropertyDetached house, 6 habitable rooms
Built1930 to 1949
HeatingBoiler and radiators, mains gas
WallsCavity wall, as built, no insulation (assumed)

From the energy performance certificate lodged in June 2020, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in New Forest (Park) - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full Application
Postcode
SO41 6FW
Received
10 Aug 2026
Validated
13 Aug 2026
Parish
Hordle Parish Council
Case officer
Show
Target decision
5 Oct 2026
Applicant
Show
Agent
Kode Architecture

Decision outlook

Day 57, past the statutory target. 93% of extensions in New Forest (Park) are decided within thirteen weeks, which runs to 12 Nov 2026; extensions of time are common, and the council need not decide on the day. Last seen undecided on 7 Oct 2026.

Day 571 days past the 56-day target
80%decided within 8 weeks
91%approved
83%go to committee

Plota live figures for extensions decided by New Forest (Park) in the last twelve months, from validation. New Forest (Park) decision record →

Consultation & key dates

Alt. reference
PP-15139583
Comments by
14 Sept 2026
Site or press notice
10 Aug 2026
New Forest (Park)
Planning Authority Score
3.3/10
Poor
#226 of 296 councils
Relevant to this application:
Householder decisions

New Forest (Park) is slower than most councils at deciding householder applications, ranking #254 out of 296. Householder applications are slightly more likely to be approved here (92%) than the national average (90%).

Slower than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
New Forest (Park) decision statistics
Based on MHCLG data, the year to March 2026
89%
Overall approval rate
Above avg (87%) #136 of 296
92%
Householder approved
Above avg (90%) #160 of 296
45%
Decided in 8 weeks
Below avg (63%) #254 of 296
44%
Extended time limit
Above avg (41%) #180 of 296
75%
Minor dwellings approved
28 decided (1-9 homes)
50%
Major dwellings approved
4 decided (10+ homes)
83%
Change of use approved
18 decided
487
Total decisions
55 refused in the year to March 2026

Sale prices: Contains HM Land Registry data © Crown copyright and database right 2026. This data is licensed under the Open Government Licence v3.0.

Freehold boundary: © Crown copyright and database rights 2026, HM Land Registry. Polygons © Crown copyright and database rights 2026 Ordnance Survey 100026316. Conditions of use

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.