The Lord Bute Hotel 181-185 Lymington Rd Highcliffe Christchurch BH23 4JS Data via plota.co.uk

8/24/0812/FUL - Full Planning Permission Refused

Proposal

Demolition of existing buildings (and detachment from East Lodge) and erection of 6 x residential dwellings associated parking and car port, bin and bike storage, access, landscaping and other associated works. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
28 Nov 2024
✓
Validated
22 Jan 2025
✗
Refused
3 Oct 2025
Appeal
Not lodged

Refused on 3 Oct 2025 · Delegated · Last checked 21 Oct 2026

Documents 26

All documents on the council site ↗

Site constraints 7

Article 4 direction
Hovercraft in the Solent. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
National infrastructure project about 606 m away: Navitus Bay Wind Park
The site is about 606 m from the project boundary. Generating station, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Habitat network: Network Enhancement Zone 2
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Also on the record
Local nature reserve about 321 m away: Steamer Point; SSSI about 249 m away: Highcliffe to Milford Cliffs SSSI; 4 listed buildings within 150 m of the postcode pin; Inside the Christchurch (Bournemouth, Christchurch and Poole) built-up area.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 1 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in BCP - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
BCP
Application type
Full Planning Permission
Postcode
BH23 4JS
Received
28 Nov 2024
Validated
22 Jan 2025
Ward
Highcliffe & Walkford
Parish
Highcliffe & Walkford Parish Council
Case officer
Show
Decision
Refused
Decision date
3 Oct 2025
Decision level
Delegated
Applicant
Show
Agent
Pure Town Planning

How this decision compares

Decided in 254 days from validation, 174 days slower than BCP's median of 80 for full applications. Refused, as 22% of full applications here are.

31%decided within 8 weeks
78%approved
760decided in the last year

Plota live figures for full applications decided by BCP in the last twelve months, from validation. BCP decision record →

Consultation & key dates

Consultation
6 Feb 2025
Comments by
27 Mar 2025
BCP
Planning Authority Score
1.7/10
Poor
#279 of 296 overall
Relevant to this application:
Householder decisions

BCP is slower than most councils at deciding householder applications: #256 of 296 on speed. The council extends the time limit on 60% of applications - one of the highest rates in England. Expect your application to take longer than the standard deadline. Householder applications are slightly less likely to be approved here (88%) than the national average (90%).

Frequently extends decision deadlines
expect longer than the statutory limit
These figures are council-wide context, not a prediction for this application. View full council performance
BCP decision statistics
Based on MHCLG data, the year to March 2026
83%
Overall approval rate
Below avg (87%) #233 of 296
88%
Householder approved
Below avg (90%) #214 of 296
44%
Decided in 8 weeks
Below avg (63%) #256 of 296
60%
Extended time limit
Above avg (41%) #267 of 296
67%
Minor dwellings approved
346 decided (1-9 homes)
68%
Major dwellings approved
56 decided (10+ homes)
81%
Change of use approved
78 decided
2,244
Total decisions
392 refused in the year to March 2026