Nobel House 17 Smith Square London SW1P 3JR Data via plota.co.uk

25/06172/LBC - Listed Building Consent Application Approved

Proposal

Internal and external alterations including erection of internal structures, part single story roof extension, new roof enclosure and associated structure above the western atrium, part demolition of the ground floor to create an opening into the basement. (Linked with 25/06171/FULL) Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
29 Aug 2025
✓
Approved
16 Mar 2026

Approved on 16 Mar 2026 · Sub-Committee · Last checked 31 Oct 2026

Documents 113

Statements & assessments 20

PDF NOBEL HOUSE DAS ADDENDUM - HERITAGE ROOMS Design and Access Statement · 19 Nov 2025 View ↗ PDF PLANNING STATEMENT Planning Statement · 7 Nov 2025 View ↗ PDF NOBEL HOUSE DESIGN AND ACCESS STATEMENT Design and Access Statement · 29 Aug 2025 View ↗ PDF NOBEL HOUSE DESIGN AND ACCESS STATEMENT Design and Access Statement · 29 Aug 2025 View ↗ PDF NOBEL HOUSE DESIGN AND ACCESS STATEMENT Design and Access Statement · 29 Aug 2025 View ↗ PDF NOBEL HOUSE DESIGN AND ACCESS STATEMENT Design and Access Statement · 29 Aug 2025 View ↗ PDF NOBEL HOUSE HOTEL NEEDS ASSESSMENT FINAL Background Papers · 29 Aug 2025 View ↗ PDF AWH D AND S REPORT - NOBEL HOUSE Daylight and Sunlight assessment · 29 Aug 2025 View ↗ PDF CRIME PREVENTION STATEMENT Background Papers · 29 Aug 2025 View ↗ PDF HERITAGE STATEMENT FULL APPLICATION NOBEL HOUSE Heritage Statement · 29 Aug 2025 View ↗ PDF HERITAGE STATEMENT FULL APPLICATION NOBEL HOUSE Heritage Statement · 29 Aug 2025 View ↗ PDF NOBEL HOUSE STATEMENT OF COMMUNITY INVOLVEMENT Background Papers · 29 Aug 2025 View ↗ PDF NOBEL HOUSE - FIRE STATEMENT LONDON PLAN Background Papers · 29 Aug 2025 View ↗ PDF NOISE IMPACT ASSESSMENT - NOVA ACOUSTICS LTD UPDATED Noise impact assessment · 29 Aug 2025 View ↗ PDF ODOUR ASSESSMENT - NOBEL HOUSE SMITH SQUARE LONDON Background Papers · 29 Aug 2025 View ↗ PDF NOBEL HOUSE PRELIMINARY ECOLOGICAL ASSESSMENT REPORT FINAL Background Papers · 29 Aug 2025 View ↗ PDF BNG EXEMPTION LETTER Background Papers · 29 Aug 2025 View ↗ PDF WHOLE LIFECYCLE CARBON ASSESSMENT Background Papers · 29 Aug 2025 View ↗ PDF SUSTAINABILITY REPORT Sustainability appraisal · 29 Aug 2025 View ↗ PDF ENERGY REPORT Energy Assessment · 29 Aug 2025 View ↗

Plans & drawings 72

PDF DEMOLITION GROUND FLOOR PLAN Drawing · 9 Feb 2026 View ↗ PDF DEMOLITION FIRST FLOOR PLAN Drawing · 9 Feb 2026 View ↗ PDF DEMOLITION SECOND FLOOR PLAN Drawing · 9 Feb 2026 View ↗ PDF DEMOLITION THIRD FLOOR PLAN Drawing · 9 Feb 2026 View ↗ PDF DEMOLITION FOURTH FLOOR PLAN Drawing · 9 Feb 2026 View ↗ PDF DEMOLITION FIFTH FLOOR PLAN Drawing · 9 Feb 2026 View ↗ PDF DEMOLITION SIXTH FLOOR PLAN Drawing · 9 Feb 2026 View ↗ PDF DEMOLITION EIGHTH FLOOR PLAN Drawing · 9 Feb 2026 View ↗ PDF PROPOSED GROUND FLOOR PLAN Drawing · 9 Feb 2026 View ↗ PDF PROPOSED FIRST FLOOR PLAN Drawing · 9 Feb 2026 View ↗ PDF PROPOSED SECOND FLOOR PLAN Drawing · 9 Feb 2026 View ↗ PDF PROPOSED THIRD FLOOR PLAN Drawing · 9 Feb 2026 View ↗ PDF PROPOSED FOURTH FLOOR PLAN Drawing · 9 Feb 2026 View ↗ PDF PROPOSED FIFTH FLOOR PLAN Drawing · 9 Feb 2026 View ↗ PDF PROPOSED SIXTH FLOOR PLAN Drawing · 9 Feb 2026 View ↗ PDF PROPOSED EIGHTH FLOOR PLAN Drawing · 9 Feb 2026 View ↗ PDF PLANNING ISSUE SHEET REV B Drawing · 9 Feb 2026 View ↗ PDF PROPOSED SIXTH FLOOR PLAN Drawing · 19 Nov 2025 View ↗ PDF PROPOSED EIGHTH FLOOR PLAN Drawing · 19 Nov 2025 View ↗ PDF PROPOSED SECTION 1 Drawing · 19 Nov 2025 View ↗ PDF LOCATION PLAN Location Plan · 29 Aug 2025 View ↗ PDF DEMOLITION BASEMENT PLAN Drawing · 29 Aug 2025 View ↗ PDF DEMOLITION GROUND FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF DEMOLITION FIRST FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF DEMOLITION SECOND FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF DEMOLITION THIRD FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF DEMOLITION FOURTH FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF DEMOLITION FIFTH FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF DEMOLITION SIXTH FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF DEMOLITION SEVENTH FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF DEMOLITION EIGHTH FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF DEMOLITION ROOF PLAN Drawing · 29 Aug 2025 View ↗ PDF EAST ELEVATION DEMOLITION Drawing · 29 Aug 2025 View ↗ PDF NORTH AND WEST ELEVATION DEMOLITION Drawing · 29 Aug 2025 View ↗ PDF EAST ELEVATION - EXISTING Drawing · 29 Aug 2025 View ↗ PDF NORTH AND WEST ELEVATION - EXISTING Drawing · 29 Aug 2025 View ↗ PDF SOUTH ELEVATION- EXISTING Drawing · 29 Aug 2025 View ↗ PDF GA SECTION 1 - EXISTING Drawing · 29 Aug 2025 View ↗ PDF GA SECTION 2 AND 3 - EXISTING Drawing · 29 Aug 2025 View ↗ PDF EXISTING SITE PLAN- BASEMENT LEVEL Drawing · 29 Aug 2025 View ↗ PDF EXISTING SITE PLAN- GROUND FLOOR LEVEL Drawing · 29 Aug 2025 View ↗ PDF EXISTING BASEMENT PLAN Drawing · 29 Aug 2025 View ↗ PDF EXISTING GROUND FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF EXISTING FIRST FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF EXISTING SECOND FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF EXISTING THIRD FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF EXISTING FOURTH FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF EXISTING FIFTH FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF EXISTING SIXTH FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF EXISTING SEVENTH FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF EXISTING EIGHT FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF EXISTING ROOF PLAN Drawing · 29 Aug 2025 View ↗ PDF PROPOSED EAST ELEVATION Drawing · 29 Aug 2025 View ↗ PDF PROPOSED NORTH AND WEST ELEVATION Drawing · 29 Aug 2025 View ↗ PDF PROPOSED SOUTH ELEVATION Drawing · 29 Aug 2025 View ↗ PDF PROPOSED BASEMENT FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF PROPOSED GROUND FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF PROPOSED FIRST FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF PROPOSED SECOND FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF PROPOSED THIRD FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF PROPOSED FOURTH FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF PROPOSED FIFTH FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF PROPOSED SIXTH FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF PROPOSED SEVENTH FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF PROPOSED EIGHTH FLOOR PLAN Drawing · 29 Aug 2025 View ↗ PDF PROPOSED ROOF PLAN Drawing · 29 Aug 2025 View ↗ PDF PROPOSED SITE PLAN BASEMENT LEVEL Drawing · 29 Aug 2025 View ↗ PDF PROPOSED SITE PLAN GROUND FLOOR LEVEL Drawing · 29 Aug 2025 View ↗ PDF PROPOSED SECTION 1 Drawing · 29 Aug 2025 View ↗ PDF PROPOSED SECTION 2 AND 3 Drawing · 29 Aug 2025 View ↗ PDF CDL - CONSTRUCTION LOGISTICS PLAN - NOBEL HOUSE (WESTMINTER) Background Papers · 29 Aug 2025 View ↗ PDF SERVICING MANAGEMENT PLAN Other · 29 Aug 2025 View ↗

All documents on the council site ↗

Associated applications 2

Site constraints 11

Grade II listed: Norwest House
List entry 1222795 · The pin is inside its outline · 37 more listed buildings within 150 m (1 Grade I, 7 Grade II*, 29 Grade II)
Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show the other 37 with distances
Historic England ↗
Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Smith Square conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
Article 4 direction
Article 4 Basement Development Permitted Rights Removed. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
Archaeological priority area: City of Westminster APA 1.1
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Westminster AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
National infrastructure project 56 m away: Thames Tideway Tunnel
The site is 56 m from the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: London Strategic Heat Main Project (at pre-application, 43 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Central activities zone
The core of central London in the London Plan.
Offices, culture and the other strategic functions of the centre take priority over new housing here.
World heritage site 66 m away: Victoria Tower Gardens
Its setting is a consideration for work nearby.
Registered parks and gardens, battlefields, world heritage sites and protected wrecks are designated heritage assets: harm needs clear and convincing justification.
Historic England ↗
Also on the record
Inside the City of Westminster built-up area; Public transport access: PTAL 5 (very good), TfL 2023, for the 100 m square.
Not affected
Not green belt · No scheduled monument at the site

Checked on 1 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Sales history 2

Last sold for £50,475,000 in March 2026. Other property, freehold.

31 March 2026£50,475,000Recorded as a transfer outside a standard sale
1 January 2016£61,386,128Recorded as a transfer outside a standard sale

Sale prices from HM Land Registry's price paid record, matched to this application by its address.

Building

Floor area19,362 m² (208,411 sq ft)
Energy ratingC (asset rating 75)
UseOffices and Workshop Businesses
HeatingHeating and Mechanical Ventilation

From the energy performance certificate lodged in September 2022, the latest held for this property. The building may have changed since. View the certificate

Work with planning data?

Every application in Westminster - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Listed Building Consent Application
Postcode
SW1P 3JR
Received
29 Aug 2025
Validated
29 Aug 2025
Ward
St James's
Case officer
Show
Target decision
24 Oct 2025
Decision
Application Permitted
Decision date
16 Mar 2026
Decision level
Sub-Committee
Agent
DP9
Freehold owner
Show

How this decision compares

Decided in 199 days from validation, 142 days slower than Westminster's median of 57 for listed building works. Approved, as 90% of listed building works here are.

49%decided within 8 weeks
90%approved
2,227decided in the last year

Plota live figures for listed building works decided by Westminster in the last twelve months, from validation. Westminster decision record →

Public comments

5comments received
5 objecting

100% object · above the UK average of 74%

5 neighbours consulted · Last counted 31 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14286765
Planning Portal ref
PP-14286765
Comments by
8 Oct 2025
Site or press notice
17 Sept 2025
Committee
24 Feb 2026
Env. assessment
No
Westminster
Planning Authority Score
3.5/10
Below average
#221 of 296 overall
Relevant to this application:
Other decisions

Westminster is slower than most councils at deciding householder applications: #258 of 296 on speed. Only 28% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Westminster is also one of the strictest councils - it refuses more householder applications than almost any other, with only 81% approved vs 90% nationally.

One of the strictest councils
only 81% approved vs 90% nationally
These figures are council-wide context, not a prediction for this application. View full council performance
Westminster decision statistics
Based on MHCLG data, the year to March 2026
86%
Overall approval rate
Below avg (87%) #201 of 296
81%
Householder approved
Below avg (90%) #277 of 296
44%
Decided in 8 weeks
Below avg (63%) #258 of 296
28%
Extended time limit
Below avg (41%) #46 of 296
83%
Minor dwellings approved
12 decided (1-9 homes)
67%
Major dwellings approved
3 decided (10+ homes)
81%
Change of use approved
133 decided
4,602
Total decisions
648 refused in the year to March 2026

Sale prices: Contains HM Land Registry data © Crown copyright and database right 2026. This data is licensed under the Open Government Licence v3.0.

Energy performance: Energy performance certificates from the Energy Performance of Buildings Register, Ministry of Housing, Communities and Local Government. Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright 2026.

Freehold owner: Information produced by HM Land Registry. © Crown copyright 2026. Source: HM Land Registry, UK and overseas companies that own property in England and Wales, September 2026 release.