Land At Protos Marsh Lane Ince Data via plota.co.uk

25/03329/FUL - Full Application Awaiting decision

Proposal

Installation of underground electricity cable between Ince Bio Power Facility and Protos Plastics Recycling Facility. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
23 Oct 2025
✓
Validated
23 Apr 2026
Decision
Target date was 18 Jun 2026

Under consideration

No decision has been issued yet. Plota predicted a decision soon after comments close on 4 Jun 2026; it is now day 214.

The consultation period closed on 4 Jun 2026.

Site constraints 4

Green belt: Merseyside and Greater Manchester
Inappropriate development needs very special circumstances.
Green belt policy allows a short list of exceptions, such as limited extensions and replacement buildings. Anything else needs very special circumstances that clearly outweigh the harm. Some green belt land can count as grey belt, where it does not strongly serve the green belt's purposes. The council decides this in its green belt assessment or on each application, so we do not mark it here.
Read the government guidance ↗
Agricultural land, grade 3b
Not best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s) agrees.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
National infrastructure project about 420 m away: Frodsham Solar
The site is about 420 m from the project boundary. Generating station, awaiting the Secretary of State's decision. Also within 2 km: HyNet Carbon Dioxide Pipeline (decided, about 992 m); Hynet North West Hydrogen Pipeline (at pre-application, about 420 m); Stanlow Hydrogen Ready Modular Combined Heat and Power Project (at pre-application, about 669 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Habitat network: Network Enhancement Zone 2
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Not affected
Outside flood zones 2 and 3 · No scheduled monument at the site

Checked on 2 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Chester - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Chester
Application type
Full Application
Received
23 Oct 2025
Validated
23 Apr 2026
Ward
Gowy Rural
Parish
Ince
Case officer
Show
Applicant
Show

Decision outlook

Day 214, past the statutory target. 92% of utility and infrastructure works in Chester are decided within thirteen weeks; extensions of time are common, and the council need not decide on the day. Last seen undecided on 16 Nov 2026.

Day 214158 days past the 56-day target
89%decided within 8 weeks
99%approved
111decided in the last year

Plota live figures for utility and infrastructure works decided by Chester in the last twelve months, from validation. Chester decision record →

Public comments

No public comments yet.

2 neighbours consulted · Last counted 16 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14374248
Planning Portal ref
PP-14374248
Comments by
4 Jun 2026
Env. assessment
No