Dean Clough Mills Dean Clough Halifax Calderdale Data via plota.co.uk

26/00785/FUL - Full Application Pending Consideration

Proposal

Repair E Mill and Victoria Shed roofs and Installation of solar panels to the roofs of Victoria Mill, F Mill, E Mill and G Mill, Dean Clough Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
1 Sept 2026
✓
Validated
30 Sept 2026
✓
Consultation
14 Oct 2026
Decision
Expected by 25 Nov 2026

Under consideration

No decision has been issued yet. Plota predicts a decision between 25 Nov 2026 and 5 Dec 2026, from Calderdale's recent utility and infrastructure works.

Comments are open until 12 Nov 2026

Comment on this application ↗

Site constraints 10

Flood zone 2, rivers and sea
Medium chance: between a 1 in 100 and 1 in 1,000 annual chance from rivers, or 1 in 200 to 1 in 1,000 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
10 listed buildings within 150 m
Nearest: Bowling Dyke Mill at East End of Dean Clough Mills, Grade II, 10 m away · 10 Grade II
The site itself is not listed. Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show all 10 with distances
Historic England ↗
Also on the record
Nature recovery project: Bradford and South Pennines; Radon affected area, class 2; Flood defence 10 m away (wall); Conservation area 72 m away: Akroydon; Coalfield, development low risk area; National infrastructure project 605 m away: Calderdale Energy Park, at pre-application; Heritage at risk 72 m away: Akroydon; Inside the Halifax built-up area.
Not affected
Not green belt · No scheduled monument at the site

Checked on 15 October 2026. Historic England, the Environment Agency, Natural England, the Mining Remediation Authority, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Calderdale - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Calderdale
Application type
Full Application
Received
1 Sept 2026
Validated
30 Sept 2026
Ward
Halifax Town
Parish
Not In A Parish
Case officer
Show
Target decision
25 Nov 2026
Applicant
Show
Agent
Mike Hide Associates

Decision outlook

Day 20 of the 56-day target. Calderdale usually decides utility and infrastructure works by day 56.

Day 2036 days to the 56-day target
52%decided within 8 weeks
92%approved
27decided in the last year

Plota live figures for utility and infrastructure works decided by Calderdale in the last twelve months, from validation. Calderdale decision record →

Public comments

No public comments yet.

40 neighbours consulted · Last counted 14 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-15182634
Planning Portal ref
PP-15182634
Neighbours
14 Oct 2026
Consultation
14 Oct 2026
Comments by
12 Nov 2026
Site or press notice
22 Oct 2026
Statutory expiry
25 Nov 2026
Env. assessment
No
Calderdale
Planning Authority Score
2.7/10
Poor
#240 of 296 councils
Relevant to this application:
Householder decisions

Calderdale ranks #193 out of 296 councils for householder decision speed. 50% of applications have the time limit extended, above the 41% national average. Householder applications are slightly less likely to be approved here (87%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
Calderdale decision statistics
Based on MHCLG data, the year to March 2026
86%
Overall approval rate
Below avg (87%) #192 of 296
87%
Householder approved
Below avg (90%) #229 of 296
58%
Decided in 8 weeks
Below avg (63%) #193 of 296
50%
Extended time limit
Above avg (41%) #223 of 296
73%
Minor dwellings approved
103 decided (1-9 homes)
82%
Major dwellings approved
11 decided (10+ homes)
89%
Change of use approved
61 decided
856
Total decisions
121 refused in the year to March 2026

Freehold boundary: © Crown copyright and database rights 2026, HM Land Registry. Polygons © Crown copyright and database rights 2026 Ordnance Survey 100026316. Conditions of use