Langstone Technology Park, 2B Langstone Road, Havant, PO9 1SA Data via plota.co.uk

APP/25/00596 - Approval of reserved matters Approved

Proposal

Application for approval of reserved matters for phase 2a and 2b pursuant to outline planning permission (ref: ) Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
15 Jul 2025
✓
Approved
20 Mar 2026

Approved on 20 Mar 2026 · Delegated Decision · Last checked 14 Oct 2026

Documents 26

All documents on the council site ↗

Associated applications 11

Site constraints 5

Nutrient neutrality catchment: Solent: Includes Chichester and Langstone Harbours SPA/Ramsar, Solent and Southampton Water SPA/Ramsar, Solent Maritime SAC, Portsmouth Harbour SPA/Ramsar
New homes and overnight accommodation must show nutrient neutrality before approval.
Natural England advice: extra wastewater in these catchments harms protected habitats, so schemes must offset their nutrient load, usually through credits.
Article 4 direction
0164B3. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
National infrastructure project about 328 m away: Hampshire Water Transfer and Water Recycling Project
The site is about 328 m from the project boundary. Dam or reservoir, accepted for examination.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Radon affected area, class 2; Inside the Havant built-up area.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 1 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Havant - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Havant
Application type
Approval of reserved matters
Postcode
PO9 1SA
Received
15 Jul 2025
Validated
15 Jul 2025
Ward
St Faiths
Case officer
Show
Target decision
14 Oct 2025
Decision
Approve with Conditions
Decision date
20 Mar 2026
Decision level
Delegated Decision
Applicant
Show
Agent
Stantec
Freehold owner
Show

How this decision compares

Decided in 248 days from validation, 142 days slower than Havant's median of 106 for reserved matters. Approved, as 97% of reserved matters here are.

22%decided within 8 weeks
97%approved
11%go to committee

Plota live figures for reserved matters decided across the UK in the last twelve months, from validation; too few recent reserved matters in Havant to go on. Havant decision record →

Public comments

9comments received
1 objecting8 neutral

11% object · below the UK average of 74%

Last counted 14 Oct 2026

Read the comments on the council site ↗

Havant
Planning Authority Score
3/10
Poor
#235 of 296 overall
Relevant to this application:
Major dwellings

Havant is one of the slowest councils in England for householder decisions: #283 of 296 on speed. The council extends the time limit on 59% of applications - one of the highest rates in England. Expect your application to take longer than the standard deadline. Householder applications are slightly more likely to be approved here (95%) than the national average (90%).

Among the slowest councils in England
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Havant decision statistics
Based on MHCLG data, the year to March 2026
94%
Overall approval rate
Above avg (87%) #39 of 296
95%
Householder approved
Above avg (90%) #78 of 296
31%
Decided in 8 weeks
Below avg (63%) #283 of 296
59%
Extended time limit
Above avg (41%) #264 of 296
82%
Minor dwellings approved
17 decided (1-9 homes)
57%
Major dwellings approved
7 decided (10+ homes)
86%
Change of use approved
21 decided
408
Total decisions
26 refused in the year to March 2026

Freehold owner and leaseholders: Information produced by HM Land Registry. © Crown copyright 2026. Source: HM Land Registry, UK and overseas companies that own property in England and Wales, September 2026 release.