Lands at Slean's Farm (Strife Hill) approximately 1Km Northwest of No. 60 Loughbracken Road, Pomeroy and West… Data via plota.co.uk

LA09/2026/0916/PAN - Proposal of Application Notice Awaiting decision

Proposal

Proposed electricity compound comprising hydrotreated vegetable oil generators (up to 27MW), other associated fuel storage, electrical infrastructure, substation and ancillary site works with access via Loughbracken Road Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
4 Sept 2026
Decision
Target date was 30 Oct 2026

Under consideration

No decision has been issued yet. Plota predicts a decision by 16 Dec 2026, from Mid Ulster's recent commercial and major works.

Site constraints 1

Radon affected area, class 5
An estimated 10 to 30% of homes reach the radon action level. Indicative for the 1 km square, which takes the highest class found in it; a radon test gives the answer for a building.
From the British Geological Survey and UK Health Security Agency indicative atlas. Under building regulations, as the BRE guide BR 211 (2023) sets out, new buildings and extensions need basic radon protection from class 3 in England and Wales and from class 2 in Scotland, and full protection from class 5. The class at the site itself, from the detailed BGS map, decides which.
UKHSA radon ↗
Not affected
Outside flood zones 2 and 3 · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Mid Ulster - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Mid Ulster
Application type
Proposal of Application Notice
Postcode
BT70 2SF
Received
4 Sept 2026
Validated
4 Sept 2026
Ward
Pomeroy
Parish
Cookstown
Decision level
Delegated Decision

Decision outlook

Day 80 of the 56-day target. Mid Ulster usually decides commercial and major works by day 96.

Day 8016 days to the predicted decision (day 96)
14%decided within 8 weeks
100%approved
6%go to committee

Plota live figures for commercial and major works decided by Mid Ulster in the last twelve months, from validation. Mid Ulster decision record →

Public comments

No public comments yet.

Last counted 22 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
DSFX1788359394162
Env. assessment
No