Land on Killingholme B Power Station and CLdn Ports Killingholme Terminal, DN40 3DZ Data via plota.co.uk

Proposal

Planning permission for the construction and operation of a Carbon Capture Plant (CCP) to capture carbon dioxide (CO2) from the adjacent consented Combined Cycle Gas Turbine (CCGT) generating station, comprising carbon capture equipment including absorber tower(s) with associated stack(s); flue gas cooling and treatment plant; CO2 purification and compression infrastructure; amine storage tanks; ducting and tie ins to the CCGT; utilities connections; and a new spur pipeline connecting the CCP to an above ground installation on either the Viking CCS Pipeline at Immingham or the Humber Carbon Capture Pipeline at North Killingholme; together with associated ancillary works comprising diversion of a public right of way, landscaping and biodiversity enhancement and security fencing Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Validated
4 Sept 2026
✓
Received
7 Sept 2026
Decision
Expected by 30 Oct 2026

Under consideration

No decision has been issued yet. Plota predicted a decision around 31 Oct 2026; it is now day 57.

The consultation period closed on 8 Oct 2026.

Site constraints 3

In flood zones plus climate change
Inside the extent flood zones 2 and 3 could reach with climate change: the Central allowance for the 2080s on rivers, the Upper End allowance for sea level rise to 2125. From the sea. Defences are not counted.
The Environment Agency flood map for planning. Councils use it to decide when a flood risk assessment and the sequential test are needed. It is indicative and does not show whether a particular property will flood.
Flood map ↗
Agricultural land, grade 3a
Best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s) agrees.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
National infrastructure project 190 m away: Hornsea Offshore Wind Farm (Zone 4) - Project Two
The site is 190 m from the project boundary. Generating station, decided. The project page says whether consent was granted. Also within 2 km: Hornsea Offshore Wind Farm (Zone 4) - Project One (decided, 190 m); North Killingholme Power Project (decided, 284 m); Able Marine Energy Park (decided, 554 m); Able Marine Energy Park Material Change 2 (decided, 554 m); H2East Pipeline: Humber to Nottinghamshire (at pre-application, the site is inside its boundary); Humber Carbon Capture Pipeline (at pre-application, 521 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in North Lincs - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Full planning permission
Postcode
DN40 3DZ
Received
7 Sept 2026
Validated
4 Sept 2026
Ward
Ferry
Parish
North Killingholme
Case officer
Show

Decision outlook

Day 57, past the statutory target. 88% of full applications in North Lincs are decided within thirteen weeks, which runs to 4 Dec 2026; extensions of time are common, and the council need not decide on the day. Last seen undecided on 6 Oct 2026.

Day 571 days past the 56-day target
65%decided within 8 weeks
86%approved
244decided in the last year

Plota live figures for full applications decided by North Lincs in the last twelve months, from validation. North Lincs decision record →

Consultation & key dates

Comments by
8 Oct 2026
North Lincs
Planning Authority Score
4.6/10
Below average
#169 of 296 councils
Relevant to this application:
Householder decisions

North Lincs ranks #123 out of 296 councils for householder decision speed. Householder applications are slightly more likely to be approved here (91%) than the national average (90%).

These figures are council-wide context, not a prediction for this application. View full council performance
North Lincs decision statistics
Based on MHCLG data, the year to March 2026
86%
Overall approval rate
Below avg (87%) #195 of 296
91%
Householder approved
Above avg (90%) #177 of 296
70%
Decided in 8 weeks
Above avg (63%) #123 of 296
44%
Extended time limit
Above avg (41%) #182 of 296
70%
Minor dwellings approved
114 decided (1-9 homes)
79%
Major dwellings approved
14 decided (10+ homes)
78%
Change of use approved
37 decided
705
Total decisions
96 refused in the year to March 2026