Land At Wigsley Wood, Moor Lane, Thorney Data via plota.co.uk

F/4813 Pending

Proposal

Removal of Existing above-ground sand mound Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
27 Jan 2026
✓
Validated
17 Mar 2026
Decision
Target date was 12 May 2026

Under consideration

No decision has been issued yet. Plota predicted a decision around 23 Nov 2026; it is now day 251.

Site constraints 4

Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
Public bridleway about 11 m away
Matters where it crosses or adjoins the site: obstructing a path without a diversion order is an offence, and work cannot start until the order is confirmed.
Compiled from highway authority data, not the legal definitive map. A few authorities have not published, so no path shown is not proof there is none.
Agricultural land, grade 2
Best and most versatile land (grades 1, 2 and 3a). Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s), which most planning maps still show, had this area as grade 4. The predicted grade is Defra's current estimate; only a site survey settles it.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
National infrastructure project about 267 m away: One Earth Solar Farm
The site is about 267 m from the project boundary. Generating station, decided. The project page says whether consent was granted. Also within 2 km: H2East Pipeline: Humber to Nottinghamshire (at pre-application, the site is inside its boundary).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Not affected
Not green belt · No scheduled monument at the site

Checked on 1 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Nottinghamshire County Council - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Received
27 Jan 2026
Validated
17 Mar 2026
Case officer
Show
Applicant
Show
Agent
Mike Sibthorp

Decision outlook

Day 251, past the statutory target. 73% of full applications in Nottinghamshire County Council are decided within thirteen weeks; extensions of time are common, and the council need not decide on the day. Last seen undecided on 22 Nov 2026.

Day 251195 days past the 56-day target
49%decided within 8 weeks
87%approved
158,523decided in the last year

Plota live figures for full applications decided across the UK in the last twelve months, from validation; too few recent full applications in Nottinghamshire County Council to go on. Nottinghamshire County Council decision record →