Phases 3, 4 and 5 Greenwich Millennium Village, Peartree Way, Greenwich, London, SE10 Data via plota.co.uk

25/3074/MA - Minor material Amendment Approved at committee

Approved at planning committee on 24 February 2026, subject to a legal agreement. The council issues its decision notice once the agreement is signed.

Proposal

An application submitted under Section 73 of the Town & Country Planning Act 1990 for a minor material amendment in connection with the planning permission (dated 14/11/2019) "for mixed use development comprising: up to a total of 1,746 Class C3 residential units; up to a total of 1,190 sq.m (GEA) Flexible Class A1 (shops) and/or A2 (financial and professional services) and/or A3 (restaurants and cafes) and/or A4 (drinking establishments); up to a total of 4,462 sq.m (GEA) business space for B1(a) (offices) and/or B1(b) (research and development) and/or B1(c) (light industry); up to 500 sq.m (GEA) Class D1 for a children's nursery; up to a total of 750 sq.m (GEA) Class D2 for community space and a management facility; up to a total of 992 sq.m (GEA) for two energy centres; associated open space, hard and soft landscaping, car parking and servicing, highways and transport works and ancillary works; with all matters reserved for future approval except for access (Outline Application). In addition to the matters set out above, full details (access, appearance, landscaping, layout, scale) in relation to the first sub-phase, being Parcel 1, located to the north and east of the site for: 459 residential units; a 365 sq.m energy centre; associated open space, hard and soft landscaping, car parking and servicing, highways and transport works and ancillary works". To allow: For the addition of a planning condition to confirm that no development or works will take place on Plots 501 and 502 under this permission. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
18 Sept 2025
✓
Validated
25 Sept 2025
✓
Consultation
10 Nov 2025
✓
Committee
24 Feb 2026
Decision notice
Not issued yet

Under consideration

No decision has been issued yet. Plota predicted a decision soon after comments close on 1 Dec 2025; it is now day 419.

The consultation period closed on 1 Dec 2025.

Planning committee

Decided by Greenwich Planning Board on 24 Feb 2026. Earlier deferred on 20 Jan 2026. The council has not yet issued its decision notice.

Approved

As officers recommended.

  • Officers advised approval because the additional information addressed concerns about open space and the proposals remained acceptable.
  • Members discussed the loss of green land and doubts about the need for a 20-storey building.
  • The committee approved the amendment by 3 votes to 1, with 1 abstention, subject to conditions and legal obligations.
Read how the committee decided The proposed development, officers’ assessment, members’ debate, vote and decision conditions.

Source: Plota analysis of Greenwich's committee minutes of 24 Feb 2026.

Associated applications 14

Site constraints 8

Grade II listed: Former East Greenwich Fire Station
List entry 1213055 · 27 m away · 2 more listed buildings within 150 m (2 Grade II)
Listed building consent is needed for work that affects the special interest of a listed building, inside or out, on top of planning permission. Setting can be a consideration for buildings nearby; there is no fixed radius.
Show the other 2 with distances
Historic England ↗
Flood zone 3, rivers and sea
High chance: a 1 in 100 or greater annual chance from rivers, or 1 in 200 from the sea. Any development here needs a flood risk assessment. Defences are not counted.
The Environment Agency flood map for planning. Homes in zone 3 must also pass the sequential test. Surface water flooding is a separate map.
Flood map ↗
National infrastructure project: Thames Tideway Tunnel
The site is inside the project boundary. Waste water treatment, decided. The project page says whether consent was granted. Also within 2 km: Silvertown Tunnel (decided, 982 m); London Strategic Heat Main Project (at pre-application, the site is inside its boundary).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Archaeological priority area
An assessment or field evaluation may be asked for before ground works.
The council or Historic England considers archaeology likely here. A desk-based assessment, and sometimes trial trenching, can be asked for with the application.
Air quality management area: Greenwich AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Also on the record
Radon affected area, class 2; Inside the Greenwich built-up area; Public transport access: PTAL 5 (very good), TfL 2023, for the 100 m square.
Not affected
Not green belt · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI), Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Greenwich - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Greenwich
Application type
Minor material Amendment
Received
18 Sept 2025
Validated
25 Sept 2025
Ward
GREENWICH PENINSULA
Parish
Greenwich
Case officer
Show
Target decision
25 Dec 2025
Agent
Newmark

Decision outlook

Day 419, past the statutory target. 88% of amendments in Greenwich are decided within thirteen weeks; extensions of time are common, and the council need not decide on the day. Last seen undecided on 17 Nov 2026.

Day 419363 days past the 56-day target
74%decided within 8 weeks
81%approved
111decided in the last year

Plota live figures for amendments decided by Greenwich in the last twelve months, from validation. Greenwich decision record →

Public comments

542comments received
535 objecting5 neutral2 supporting

99% object · above the UK average of 74%

1,538 neighbours consulted · Last counted 17 Nov 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-14272482
Planning Portal ref
PP-14272482
Consultation
10 Nov 2025
Comments by
1 Dec 2025
Committee
24 Feb 2026
Statutory expiry
25 Dec 2025
Env. assessment
No
Greenwich
Planning Authority Score
5.4/10
Average
#123 of 296 councils
Relevant to this application:
Householder decisions

Greenwich is faster than most councils at deciding householder applications, ranking #76 out of 296. Only 29% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Greenwich is also one of the strictest councils - it refuses more householder applications than almost any other, with only 78% approved vs 90% nationally.

One of the strictest councils
only 78% approved vs 90% nationally
These figures are council-wide context, not a prediction for this application. View full council performance
Greenwich decision statistics
Based on MHCLG data, the year to March 2026
77%
Overall approval rate
Below avg (87%) #278 of 296
78%
Householder approved
Below avg (90%) #287 of 296
75%
Decided in 8 weeks
Above avg (63%) #76 of 296
29%
Extended time limit
Below avg (41%) #49 of 296
60%
Minor dwellings approved
114 decided (1-9 homes)
100%
Major dwellings approved
13 decided (10+ homes)
66%
Change of use approved
195 decided
1,468
Total decisions
331 refused in the year to March 2026