2026/1279/OHLI - Overhead Electricity Line Determined

Proposal

Notification under The Electricity Act 1989 Overhead Lines (Exemption) (England and Wales) Regulations 2009 for replacement electricity pole. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
18 Jun 2026
Decision
Expected by 13 Aug 2026

Under consideration

No decision has been issued yet. Plota predicted a decision around 9 Oct 2026; it is now day 113.

Site constraints 9

Nutrient neutrality catchment: River Eden SAC
New homes and overnight accommodation must show nutrient neutrality before approval.
Natural England advice: extra wastewater in these catchments harms protected habitats, so schemes must offset their nutrient load, usually through credits.
Settle-Carlisle Railway conservation area
Demolition needs planning permission and permitted development is restricted.
The council must give weight to preserving or enhancing the area's character and appearance. Not every council has published its boundaries as open data.
Council document ↗
Special area of conservation about 126 m away: River Eden
Work nearby can need a habitats assessment.
Harm to a protected site is only accepted where there is no alternative and an overriding public interest.
Habitat network: Network Enhancement Zone 2
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
SSSI about 126 m away: Town End Meadows, Little Asby SSSI
Natural England may need consulting, depending on what is proposed.
Sites of special scientific interest are the best wildlife and geological sites in the country. Development likely to harm one is rarely permitted.
National infrastructure project about 818 m away: A66 Northern Trans-Pennine Project
The site is about 818 m from the project boundary. Highway, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Nature recovery project: East of Eden; Inside the Long Marton built-up area; Natural England's Provisional ALC map (1:250,000, 1970s) had this area as grade 4, but it predates the buildings here and the current map does not class it as farmland.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 6 October 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Westmorland and Furness - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Application type
Overhead Electricity Line
Postcode
CA16 6BY
Received
18 Jun 2026
Validated
18 Jun 2026
Ward
Eden and Lyvennet Vale
Parish
Long Marton
Case officer
Show
Decision level
Delegated
Applicant
Show
Agent
SP Electricity North West

Decision outlook

Day 113, past the statutory target. 91% of utility and infrastructure works in Westmorland and Furness are decided within thirteen weeks; extensions of time are common, and the council need not decide on the day. Last seen undecided on 10 Sept 2026.

Day 11357 days past the 56-day target
61%decided within 8 weeks
98%approved
48decided in the last year

Plota live figures for utility and infrastructure works decided by Westmorland and Furness in the last twelve months, from validation. Westmorland and Furness decision record →

Consultation & key dates

Statutory expiry
16 Jul 2026
Westmorland and Furness
Planning Authority Score
3.1/10
Poor
#233 of 296 councils
Relevant to this application:
Householder decisions

Westmorland and Furness is slower than most councils at deciding householder applications, ranking #235 out of 296. 52% of applications have the time limit extended, above the 41% national average. Householder applications are slightly more likely to be approved here (93%) than the national average (90%).

Slower than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Westmorland and Furness decision statistics
Based on MHCLG data, the year to March 2026
92%
Overall approval rate
Above avg (87%) #96 of 296
93%
Householder approved
Above avg (90%) #145 of 296
51%
Decided in 8 weeks
Below avg (63%) #235 of 296
52%
Extended time limit
Above avg (41%) #238 of 296
84%
Minor dwellings approved
69 decided (1-9 homes)
100%
Major dwellings approved
18 decided (10+ homes)
89%
Change of use approved
135 decided
1,204
Total decisions
91 refused in the year to March 2026