Margam Substation Margam SA13 3NF Data via plota.co.uk

P2025/0817 - Full Plans Approved

Proposal

Full planning application for the extension of the Margam 275kV substation including the erection of a gas insulated switchgear hall (GIS hall) and the demolition of the existing control and amenities buildings to enable the erection of a new amenities building. Works to also include earthworks, surface water management and drainage infrastructure, lighting, CCTV, boundary treatment, car parking, ecological improvements including a wildlife tower and gabion baskets, improved internal access roads, diesel generator and hardstanding, storage building and water storage tank, flood defence wall including flood gates and appropriate landscaping and other associated engineering operations. Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
19 Nov 2025
✓
Validated
20 Nov 2025
✓
Consultation
27 Jan 2026
✓
Approved
17 Apr 2026

Approved on 17 Apr 2026 · Committee Decision · Last checked 13 Oct 2026

Planning committee

Decided by Neath Planning Committee on 3 Mar 2026.

Approved

As officers recommended.

  • Officers advised approval because the benefits outweighed ecological, drainage and flood-related harms, subject to mitigation and a legal agreement.
  • The committee approved the application in line with the officers’ recommendation, subject to the reported conditions and amendment sheet.
Read how the committee decided The proposed works, site context, officers’ assessment, consultation, representations, ward member’s contribution and committee decision.

Source: Plota analysis of Neath's committee minutes of 3 Mar 2026.

Associated applications 3

Work with planning data?

Every application in Neath - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Neath
Application type
Full Plans
Postcode
SA13 3NF
Received
19 Nov 2025
Validated
20 Nov 2025
Ward
Margam & Taibach
Parish
Port Talbot
Case officer
Show
Target decision
21 May 2026
Decision
Approved
Decision date
17 Apr 2026
Decision level
Committee Decision
Applicant
Show

How this decision compares

Decided in 148 days from validation, 94 days slower than Neath's median of 54 for full applications. Approved, as 97% of full applications here are.

56%decided within 8 weeks
97%approved
332decided in the last year

Plota live figures for full applications decided by Neath in the last twelve months, from validation. Neath decision record →

Public comments

No public comments yet.

9 neighbours consulted · Last counted 13 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Neighbours
4 Dec 2025
Consultation
27 Jan 2026
Comments by
10 Feb 2026
Site or press notice
9 Dec 2025
Statutory expiry
14 Jan 2026
Env. assessment
No