New medical facility at Unit 26 Oakham Enterprise Park, Ashwell Road, Oakham
Summary of planning committee decision
Decided by Rutland Planning Committee on 20 Oct 2026.
What was proposed
A two-storey medical facility of about 915 square metres would include healthcare rooms, operating theatres, diagnostic and recovery facilities, parking and a mobile MRI area.
“06/06/2023 V1 parking, landscaping, drainage, external plant and infrastructure. The building would provide approximately 915 square metres of floorspace and accommodate a range of health-related functions, including consultation/interview rooms, two operating theatres, diagnostic and recovery facilities, together with flexible accommodation associated with healthcare research and innovation.”
“The proposal also incorporates 40 car parking spaces, including accessible and EV charging spaces, motorcycle and cycle parking, a patient/ambulance drop-off area, improvements to pedestrian routes through the Enterprise Park and a dedicated area for a mobile MRI unit. External plant would be located to the rear of the building within an acoustic enclosure.”
Officer report
The site and surroundings
The vacant site is within Oakham Enterprise Park, a former prison site with commercial and industrial buildings, internal roads and surrounding countryside.
“Site & Surroundings 1. The application site comprises an undeveloped area of land within Oakham Enterprise Park, approximately 3km north of Oakham town centre and accessed from Ashwell Road. The wider Enterprise Park occupies the site of the former HMP Ashwell and comprises a range of commercial and industrial buildings served by an established internal road network.”
“The overall site is relatively level, albeit with rubble heaps from historic demolition, and is presently vacant. Existing trees are located close to the western boundary, while an existing road spur provides access from the internal estate road. The site lies outside the Planned Limits of Development but forms part of the established Enterprise Park. Proposal 3.”
Officer report
Planning history
The wider site was previously a prison, and an earlier application approved its redevelopment for business, industry, storage, education, leisure and related uses.
“The proposed site plan is attached as Appendix 1. Relevant Planning History Previously a prison – full site history for this not relevant to this application. APP/2013/0192 - Proposed demolition of identified buildings, Change of Use of land and buildings from former Prison (Sui Generis Use) to B1 (Business), B2 (General Industry including manufacturing), B8 (Storage and Distribution), D1 (Non-residential Education and Training Centres), D2 (Assembly, Leisure and…”
Officer report
What officers recommended
Officers recommended approval because the enterprise park context, employment and economic activity, and significant public-health benefits outweighed the identified adverse effects.
“The proposed facility would provide clinical services alongside accommodation associated with healthcare enterprise, research and innovation. While the proposal would not constitute a conventional employment use, it would itself generate employment and economic activity and would be compatible with the established mixed commercial and employment character of the Enterprise Park.”
“Having regard to the established employment character of Oakham Enterprise Park, the previously developed context of the site, the employment and economic activity associated with the proposed use and the significant public health benefits arising from the development, officers consider the proposal to be acceptable in principle.”
Officer report
Habitat and technical matters
The proposal would substantially reduce priority open-mosaic habitat, but off-site biodiversity units, revised technical information and conditions addressed the identified impacts.
“Following consideration of this additional information and the revised layout, the Local Highway Authority raise no objection, subject to conditions. The proposal would not result in an unacceptable impact upon highway safety or the operation of the highway network. The proposal is therefore considered to accord with Policy CS18 of the Core Strategy, Policy SP15 of the Site Allocations and Policies DPD and Policies TR3, TR4 and TR6 of the NPPF (2026).”
“Mandatory Biodiversity Net Gain cannot be delivered wholly within the application site. The submitted Biodiversity Gain Plan records a pre- development value of 5.66 habitat units and a post-development on-site value of 0.56 units, representing a 90.05% on-site reduction. The strategy consequently proposes the acquisition of off-site units from the proposed Wild Rutland habitat bank operated through Hanbury Farms Partnership in order to…”
Officer report
Consultation responses
Highways, ecology, archaeology, public protection, Anglian Water and flood authorities raised no objection, subject where specified to conditions.
“LCC Ecology No objection following the submission of additional ecological and BNG information, subject to conditions relating to construction-phase ecological protection, biodiversity enhancements, lighting and maintenance of an up-to- date ecological baseline.”
“Public Protection No objection, subject to conditions…”
Officer report
What members considered
Members were told that the principle, highway and flood matters were acceptable, while habitat loss would be addressed through mitigation remaining within Rutland.
“Officers considered the principle acceptable because the facility supported healthcare- related enterprise, created employment, and provided significant public-health infrastructure within the established enterprise park. The Highway Authority raised no objection subject to conditions, the Lead Local Flood Authority identified no flooding impact, and design and highway details had been refined during the application.”
“The existing open-mosaic habitat would largely be lost through construction. Ecology officers accepted off-site biodiversity mitigation using units from the proposed Wild Rutland Habitat Bank operated by Hanbury Farms Partnership; officers confirmed that the mitigation would remain within Rutland.”
Minutes
The vote
Councillor R Payne proposed approval, and the motion was carried with seven votes in favour and no vote against or abstention.
“It was proposed by Councillor R Payne and seconded that the application be approved subject to the conditions in the report.”
“Upon being put to the vote, with seven votes in favour, the motion was unanimously carried.”
Minutes
Councillors at the meeting
- Nick BegyChairIndependent
- Kevin CorbyVice-ChairIndependent
- Giles CliftonConservative
- Steve McRobbLabour
- Karen PayneConservative
- Raymond PayneLib Dem
Apologies Andrew Brown Independent, Diane Ellison Lib Dem, Abigail West Lib Dem, Tim Smith Lib Dem
Source: Plota analysis of the council's minutes; parties from the council's list of councillors.
Sources
- Rutland Planning Committee minutes, 20 October 2026
- Agenda and papers (council website)
Source: Plota analysis of Rutland's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Committee
- Rutland Planning Committee
- Council
- Rutland
- Date
- Tuesday 20 October 2026
- Recommendation
- Officers recommended approval
- Committee decided
- Approved
- Vote
- Unanimous
- Councillors
- 6Conservative 2Independent 2Labour 1Lib Dem 1Show councillors
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- View application →
- All decisions
- Rutland committee decisions →
This committee's year
26 decisions in the 12 months to this meeting, 1 against officer advice.
Source: Plota analysis of the committee's minutes.