Aggregates Express Asphalt, Great Central Way, London, NW10 0JD Data via plota.co.uk

26/1919 - Conditions pursuant to a full permission Registered

Proposal

Details pursuant to conditions 6 (construction environment management plan (CEMP)), 7 (construction method statement), 8 (landscaping), 9 (wildlife and nesting features) and 10 (delivery and servicing plan (DSP)) of Full Planning Permission reference dated 15 July, 2026, for Demolition of select buildings and structures; construction of new roof linking the existing open sided dry storage buildings; new containment fence along Great Central Way; new open sided aggregates processing buildings; new site control and welfare building;�and yard storage areas for an aggregates depot including associated infrastructure, new access to north of site to/from Great Central Way, removal of access gate to north west side of site and landscaping, new boundary treatment, new parking arrangements (vehicular and cycle provision); and continued use of the railhead to transport aggregates, subject to Deed of Agreement dated 13 July 2026 under Section 106 of Town and Country Planning Act, 1990, as amended . Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
28 Jul 2026
Decision
Expected by 22 Sept 2026

Under consideration

No decision has been issued yet. A decision is expected by 22 Sept 2026.

The consultation period closed on 21 Aug 2026.

Associated applications 3

  • Part of

    Fullcouncil archive

    Conditions 6, 7, 8, 9, 10 awaiting decision · 11 varied

Site constraints 6

Article 4 direction
Article 4 for HMOs. Named permitted development rights are withdrawn here.
An Article 4 direction withdraws particular permitted development rights, so work that would normally need no application needs one here. Not every council has published its directions.
Strategic industrial land
Reserved for industry and logistics.
The London Plan protects strategic industrial locations from other uses; release needs a plan-led process.
Air quality management area: Brent AQMA
The council has declared the area as failing an air quality objective.
Schemes that add traffic, parking or combustion plant are assessed against the area's action plan and may need an air quality assessment.
Council record ↗
Also on the record
Inside the Brent built-up area; Public transport access: PTAL 3 (moderate), TfL 2023, for the 100 m square; Designated open space 43 m away.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 6 October 2026. Historic England, the Environment Agency, Natural England, Transport for London (public transport access levels, Powered by TfL Open Data, OGL v3.0, contains OS data © Crown copyright and database right 2025) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Brent - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Brent
Application type
Conditions pursuant to a full permission
Postcode
NW10 0JD
Received
28 Jul 2026
Validated
28 Jul 2026
Ward
Stonebridge
Case officer
Show
Target decision
22 Sept 2026
Decision level
Delegated Team Manager
Agent
HGH Consulting

Public comments

No public comments yet.

Last counted 8 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-15116114
Planning Portal ref
PP-15116114
Comments by
21 Aug 2026
Env. assessment
No
Brent
Planning Authority Score
5.7/10
Average
#113 of 296 councils
Relevant to this application:
Householder decisions

Brent is faster than most councils at deciding householder applications, ranking #91 out of 296. Only 28% of applications have the time limit extended, well below the 41% national average - the council usually decides on time. Householder applications are slightly less likely to be approved here (85%) than the national average (90%).

Faster than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Brent decision statistics
Based on MHCLG data, the year to March 2026
78%
Overall approval rate
Below avg (87%) #269 of 296
85%
Householder approved
Below avg (90%) #247 of 296
73%
Decided in 8 weeks
Above avg (63%) #91 of 296
28%
Extended time limit
Below avg (41%) #42 of 296
53%
Minor dwellings approved
73 decided (1-9 homes)
85%
Major dwellings approved
13 decided (10+ homes)
54%
Change of use approved
193 decided
1,963
Total decisions
431 refused in the year to March 2026