Land At 459390 423479 Myrtle Farm Drive Hensall North Yorkshire Data via plota.co.uk

SELZG2026/0469/PIP - Permission in Principle Approved

Proposal

Permission in Principle for up to 9no. Dwellings Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
20 May 2026
✓
Validated
29 Jun 2026
✓
Consultation
6 Aug 2026
✓
Approved
2 Sept 2026

Approved on 2 Sept 2026 · Chief Planner · Last checked 25 Sept 2026

Site constraints 4

National infrastructure project 950 m away: Eggborough CCGT
The site is 950 m from the project boundary. Generating station, decided. The project page says whether consent was granted. Also within 2 km: East Coast Hydrogen Humber Pipeline (at pre-application, 193 m).
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
1 listed building within 150 m; Coalfield, development low risk area; Natural England's Provisional ALC map (1:250,000, 1970s) had this area as grade 3, but it predates the buildings here and the current map does not class it as farmland.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Mining Remediation Authority, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Selby - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Selby
Application type
Permission in Principle
Received
20 May 2026
Validated
29 Jun 2026
Ward
Camblesforth And Carlton
Parish
Hensall Parish Council
Case officer
Show
Target decision
4 Sept 2026
Decision
Application Permitted
Decision date
2 Sept 2026
Decision level
Chief Planner
Applicant
Show
Agent
DDR & Partners Ltd

How this decision compares

Decided in 65 days from validation, 5 days slower than Selby's median of 60 for new homes. Approved, as 49% of new homes here are.

46%decided within 8 weeks
49%approved
44decided in the last year

Plota live figures for new homes decided by Selby in the last twelve months, from validation. Selby decision record →

Public comments

8comments received
8 objecting

100% object · above the UK average of 74%

Last counted 25 Sept 2026

Read the comments on the council site ↗

Consultation & key dates

Consultation
6 Aug 2026
Comments by
20 Aug 2026
Site or press notice
29 Jul 2026
Statutory expiry
3 Aug 2026
Env. assessment
No