Land at Former Fairways Garage Heeley Road Lytham St Annes Lancashire FY8 2JX Data via plota.co.uk

25/0358 - Full Planning Permission Approved at committee

Approved at planning committee on 25 March 2026, subject to a legal agreement. The council issues its decision notice once the agreement is signed.

Proposal

Residential development of 22 dwellings comprising construction of 19 three storey dwellings and extensions and alterations to existing building (the former co-op) to facilitate change of use to 3 dwellings together with associated infrastructure Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
12 Jun 2025
✓
Validated
22 Jul 2025
✓
Committee
25 Mar 2026
Decision notice
Not issued yet

Under consideration

No decision has been issued yet. Plota predicted a decision soon after comments close on 26 Dec 2025; it is now day 477.

The consultation period closed on 26 Dec 2025.

Planning committee

Decided by Fylde Planning Committee on 25 Mar 2026. The council has not yet issued its decision notice.

Approved

No officer report was published for this decision; this summary is from the committee minutes.

  • Authority was delegated to officers to grant permission for 22 new homes, including conversion of the former Co-op building, subject to conditions and a planning obligation.
  • The developer must contribute money towards affordable housing, public open space and GP capacity in the area.
  • Five of the homes must be built to an adaptable standard for elderly occupants.
Read how the committee decided The decision, the money secured for the area, and the conditions attached. Includes the meeting recording

Source: Plota analysis of Fylde's committee minutes of 25 Mar 2026.

Documents 89

Statements & assessments 21

PDF Ecology & BNG technical note Additional Information · 4 Mar 2026 View ↗ PDF Additional Information BNG Statement_revised · 16 Jan 2026 View ↗ PDF BNG Habitat Management & Monitoring Plan Additional Information · 16 Jan 2026 View ↗ PDF Biodiversity Net Gain Metric BNG Statutory Metric_revised · 16 Jan 2026 View ↗ PDF Arboricultural Statement_Revised Additional Information · 8 Dec 2025 View ↗ PDF Swept Path Assessment Large Refuse Vehicle J000450/ATR101 - B · 8 Oct 2025 View ↗ PDF Flood Risk Assessment & Drainage Strategy_Updated Additional Information · 7 Oct 2025 View ↗ PDF Flood Risk Sequential Test Additional Information · 7 Oct 2025 View ↗ PDF Lead Local Flood Authority 13.08.25 Consultee Comment · 13 Aug 2025 View ↗ PDF Bat Dusk Presence/ Absence Survey 2 - 30 July 2025 Additional Information · 30 Jul 2025 View ↗ PDF Bat Dusk Presence/ Absence Survey 1 - 7 July 2025 Background Documents · 22 Jul 2025 View ↗ PDF Flood Risk Assessment & Drainage Strategy Superseded · 22 Jul 2025 View ↗ PDF Statutory Biodiversity Metric Calculation Tool Superseded · 19 Jun 2025 View ↗ PDF Statutory Biodiversity Metric Condition Assessments Superseded · 19 Jun 2025 View ↗ PDF Statement Of Community Involvement Background Documents · 12 Jun 2025 View ↗ PDF Noise & Vibration Impact Assessment Background Documents · 12 Jun 2025 View ↗ PDF Background Documents Transport Assessment · 12 Jun 2025 View ↗ PDF Design & Access Statement Background Documents · 12 Jun 2025 View ↗ PDF Background Documents Drainage Strategy · 12 Jun 2025 View ↗ PDF Ecological Appraisal & BNG Assessment Background Documents · 12 Jun 2025 View ↗ PDF Arboricultural Statement Superseded · 12 Jun 2025 View ↗

Plans & drawings 31

PDF Proposed Corner House Type B (Plot 19) Plans & Elevations Amended Plan · 4 Mar 2026 View ↗ PDF Proposed Adaptable House Type Floor Plans Amended Plan · 4 Dec 2025 View ↗ PDF Illustrative Landscaping Sections 417-LYR-XX-ZZ-DWG-L-5001 - 3 · 2 Dec 2025 View ↗ PDF 417-LYR-XX-ZZ-DWG-L-8001 - 1 Boundary Treatments Layout · 2 Dec 2025 View ↗ PDF Proposed Site Layout Amended Plan · 9 Oct 2025 View ↗ PDF Proposed House Type A Plans & Elevations Amended Plan · 7 Oct 2025 View ↗ PDF Proposed House Type B Plans & Elevations Amended Plan · 7 Oct 2025 View ↗ PDF Proposed Detached House Type A (Plot 11) Plans & Elevations Amended Plan · 7 Oct 2025 View ↗ PDF Proposed Ground Floor Plan (Former Co-op) Amended Plan · 7 Oct 2025 View ↗ PDF Proposed First Floor Plan (Former Co-op) Amended Plan · 7 Oct 2025 View ↗ PDF Proposed Second Floor Plan (Former Co-op) Amended Plan · 7 Oct 2025 View ↗ PDF Accomodation Schedule Rev A Amended Plan · 7 Oct 2025 View ↗ PDF Proposed Corner House Type B (Plot 19) Plans & Elevations Superseded · 7 Oct 2025 View ↗ PDF Illustrative Landscaping Sections 417-LYR-XX-ZZ-DWG-L-5001 - 2 · 29 Aug 2025 View ↗ PDF Proposed East Elevation (Former Co-op) Initial Drawing · 19 Jun 2025 View ↗ PDF Proposed South Elevation (Former Co-op) Initial Drawing · 19 Jun 2025 View ↗ PDF Proposed West Elevation (Former Co-oP) Initial Drawing · 19 Jun 2025 View ↗ PDF Existing Ground & 1st Floor Plans (Former Co-op) Initial Drawing · 12 Jun 2025 View ↗ PDF Existing 2nd Floor & Roof Plans (Former Co-op) Initial Drawing · 12 Jun 2025 View ↗ PDF Existing Elevations (Former Co-op) Initial Drawing · 12 Jun 2025 View ↗ PDF Proposed Roof Plan (Former Co-op) Initial Drawing · 12 Jun 2025 View ↗ PDF Proposed Site Sections Initial Drawing · 12 Jun 2025 View ↗ PDF Location Plan P-001 - B · 12 Jun 2025 View ↗ PDF Proposed Site Layout Superseded · 12 Jun 2025 View ↗ PDF Proposed House Type A Plans & Elevations Superseded · 12 Jun 2025 View ↗ PDF Proposed House Type B Plans & Elevations Superseded · 12 Jun 2025 View ↗ PDF Proposed Street Scene Elevations Superseded · 12 Jun 2025 View ↗ PDF Proposed Adaptable House Type Floor Plans Superseded · 12 Jun 2025 View ↗ PDF Proposed Ground Floor Plan (Former Co-op) Superseded · 12 Jun 2025 View ↗ PDF Proposed First Floor Plan (Former Co-op) Superseded · 12 Jun 2025 View ↗ PDF Proposed Second Floor Plan (Former Co-op) Superseded · 12 Jun 2025 View ↗

All documents on the council site ↗

Site constraints 2

National infrastructure project about 115 m away: Morgan and Morecambe Offshore Wind Farms Transmission Assets
The site is about 115 m from the project boundary. Electricity line, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Also on the record
Inside the Lytham St Anne's built-up area.
Not affected
Outside flood zones 2 and 3 · Not green belt · No scheduled monument at the site

Checked on 1 November 2026. The pin for this application is the centre of its postcode rather than the building, so distances to nearby designations are measured from the postcode and can be out by the width of the postcode area. Historic England, the Environment Agency, Natural England, the Planning Inspectorate and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Fylde - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Fylde
Application type
Full Planning Permission
Postcode
FY8 2JX
Received
12 Jun 2025
Validated
22 Jul 2025
Ward
Ashton New
Parish
St Anne's on the Sea
Case officer
Show
Decision level
Committee
Applicant
Show
Agent
Paul Butler Associates Ltd

Decision outlook

Day 477, past the statutory target. 55% of full applications in Fylde are decided within thirteen weeks; extensions of time are common, and the council need not decide on the day. Last seen undecided on 5 Nov 2026.

Day 477386 days past the 91-day target
35%decided within 8 weeks
96%approved
9%go to committee

Plota live figures for full applications decided by Fylde in the last twelve months, from validation. Fylde decision record →

Consultation & key dates

Consultation
23 Jul 2025
Comments by
26 Dec 2025
Site or press notice
1 Aug 2025
Committee
25 Mar 2026
Fylde
Planning Authority Score
5.3/10
Average
#130 of 296 councils
Relevant to this application:
Change of use

Fylde ranks #184 out of 296 councils for householder decision speed. 49% of applications have the time limit extended, above the 41% national average. Householder applications are more likely to be approved here than most councils, with a 98% approval rate vs 90% nationally.

More permissive than most councils
98% approved vs 90% nationally
These figures are council-wide context, not a prediction for this application. View full council performance
Fylde decision statistics
Based on MHCLG data, the year to March 2026
96%
Overall approval rate
Above avg (87%) #11 of 296
98%
Householder approved
Above avg (90%) #17 of 296
60%
Decided in 8 weeks
Below avg (63%) #184 of 296
49%
Extended time limit
Above avg (41%) #220 of 296
79%
Minor dwellings approved
43 decided (1-9 homes)
100%
Major dwellings approved
9 decided (10+ homes)
100%
Change of use approved
28 decided
422
Total decisions