Gym with mezzanine at Douglas Valley Breakers, Bradley Lane, Standish, Wigan
Summary of planning committee decision
Decided by Wigan Planning Committee on 27 Oct 2026.
What was proposed
Retrospective permission was sought to change a vehicle breakers yard into a 24-hour gym, extend the upper floor and install a mezzanine.
“Retrospective planning permission is sought for the change of use of the former vehicle breakers yard to a gym (Use Class E(d)). The gym operates on a 24-hour basis, seven days per week. No external alterations to the building are proposed, however, internal works have been undertaken comprising the extension of the existing upper floor and the installation of a mezzanine level.”
“The gym operates as a managed fitness facility with supervised access, controlled occupancy levels and structured class scheduling. The submitted Operational Statement advises that occupancy is typically expected to range between 10 and 25 users during peak periods, with a maximum capacity of 40 users. Access is controlled through a digital membership and booking system which manages entry, monitors attendance and regulates class bookings.”
Officer report
The site and surroundings
The existing industrial building lies in the Bradley Lane Primary Employment Area, surrounded mainly by commercial premises, with open fields to the north and homes beyond intervening infrastructure.
“The application relates to an established industrial unit and associated parking area located within the Bradley Lane Primary Employment Area, Standish. The submitted application advises that the site was previously occupied as a vehicle breakers yard, involving the dismantling of vehicles, storage of parts and other associated commercial operations.”
“The surrounding area is predominantly commercial and industrial in character. A range of warehouses, factories, storage and distribution premises and office accommodation are located to the east, west and south of the site. To the north, the site adjoins open agricultural fields.”
Officer report
Earlier planning decisions
Earlier applications for an industrial building and an oil storage tank at the site were approved with conditions.
“Planning application reference: A/00/52203 (Land Adj to Sub Station) Proposal: Erection of Industrial Building totalling 1664sqm Decision: Approved with conditions 8 September 2000.”
“Planning application reference: A/74/01014 Proposal: Installation of Oil Storage Tank Decision: Approved with conditions 12 August 1974.”
Officer report
What officers recommended
Officers recommended approval because the proposal reused an existing building, supported employment and wellbeing, passed the sequential test and caused no unacceptable planning harm subject to conditions.
“The proposed use is not considered likely to result in unacceptable harm to the living conditions of nearby residents or the operation of surrounding commercial and industrial premises. Gym activities would take place within the enclosed building, appropriate internal noise-management measures are identified, and the site is separated from the nearest residential properties by intervening land uses and infrastructure.”
“In applying NPPF Policy S4, Officers consider that the identified economic, employment, health, wellbeing and land-use benefits of the development would not be substantially outweighed by any adverse effects. Subject to the recommended conditions, the proposal is considered to accord with the Development Plan when read as a whole and with the relevant provisions of national planning policy.”
Officer report
Consultation responses
Transport and planning officers raised no objections, noise officers sought opening-hour controls, and the ecology unit had no comments.
“The comments summarised below reflect the final positions of each consultee, some of whom have provided multiple responses and/or correspondence throughout the application assessment process. These summaries focus on the final comments relevant to the proposals being presented to Members. Full, unabridged consultee responses are available to view on the Council’s website.”
“Overall, no highway safety or transport objections are raised to the development.”
Officer report
What people said
Ninety-one representations supported the gym for its health, community, economic and accessibility benefits, while 26 objected over competition, congestion, traffic and parking.
“Community Benefits: - Many supported describe the community and inclusive atmosphere of the fitness facility…”
“Highways, Traffic and Parking Impacts: - Standish already experiences significant congestion - Bradley Lane is close to a constrained railway bridge junction - The site is opposite an active industrial estate generating commercial traffic - Parking provision may be inadequate leading to overspill parking - Additional traffic could have severe cumulative impact on the local highway network…”
Officer report
Who spoke
One speaker was scheduled to speak against the application and one speaker was scheduled to speak in favour, for four minutes each.
The committee vote
The committee approved the application with 12 votes in favour, no votes against and no abstentions.
“The Committee approve the planning application and grant planning permission, subject to the conditions specified below.”
Minutes
The conditions
Permission restricted the use to a gym and fitness centre and required management, cycle storage, waste facilities, parking, access closure and electric vehicle charging measures.
“A booking and membership management system including arrangements for class scheduling, customer bookings, capacity management and the control of peak demand; • Staffing arrangements including staff numbers, staff roles, management responsibility, hours of staff attendance and shift patterns; • Procedures for the management of customers, visitors, contractors and deliveries; and • A mechanism for the periodic review and updating of the Management Plan to ensure its…”
“Within two months of the date of this permission, smart Electric Vehicle (EV) charging provision shall be made available on the site in accordance with details that have previously been submitted to and approved in writing by the Local Planning Authority. The smart EV charging provision shall be retained thereafter.”
Minutes
Councillors at the meeting
- John HardingChairLabour
- David HurstVice-ChairLabour
- Paul John BlayLabour
- Liam ClarkeReform UK
- Matt DawberLabour
- Paul ForbesReform UK
- Stuart Andrew GerrardIndependent
- Yvonne KlieveLabour
- Charles RigbyLab Co-op
- Eileen StrathearnReform UK
- Michael WhalleyReform UK
- Adrian WhiteReform UK
Apologies Susan June Greensmith Labour, Maureen O'Bern Independent, Frederick Bown Walker Labour
Source: Plota analysis of the council's minutes; parties from the council's list of councillors.
Sources
- Wigan Planning Committee minutes, 27 October 2026
- Agenda and papers (council website)
Source: Plota analysis of Wigan's committee minutes and officer report. Quotations are the council's own words; headings and summaries are Plota's.
Committee decisions and nationwide planning applications, in one API
The Plota API returns planning applications from every council we cover, each with its decision, whether a committee or officers decided it, and the committee date. Build it into your own tools.
See the API →At the meeting
- Committee
- Wigan Planning Committee
- Council
- Wigan
- Date
- Tuesday 27 October 2026
- Recommendation
- Officers recommended approval
- Committee decided
- Approved
- Councillors
- 12Labour 5Reform UK 5Independent 1Lab Co-op 1Show councillors
- Minutes
- The council's minutes
- Meeting
- Agenda and papers (council website)
- Application
- View application →
- All decisions
- Wigan committee decisions →
This committee's year
19 decisions in the 12 months to this meeting, 1 against officer advice.
Source: Plota analysis of the committee's minutes.