Middleton Substation Faraday Road Heysham Lancashire Data via plota.co.uk

25/01055/FUL - Full Application Approved

Proposal

Extension to Middleton 400kV electricity substation including the construction of substation and control building, siting of two new supergrid transformers, installation of other above ground transmission and below ground cabling, and associated works including internal access roads, culvert, surfacing, boundary fence and car parking Data via plota.co.uk

View original council record ↗Last checked

Application progress

✓
Received
26 Sept 2025
✓
Consultation
8 Apr 2026
✓
Approved
14 May 2026

Approved on 14 May 2026 · Delegated Decision · Last checked 12 Oct 2026

Planning committee

Decided by Lancaster Planning Regulatory Committee on 11 May 2026.

Approved by 14 votes to 0

As officers recommended.

  • Officers advised approval because the site is safeguarded for energy infrastructure and impacts were acceptable subject to conditions.
  • One public letter raised concerns about construction noise, the construction period and the structure’s visibility.
Read how the committee decided The proposal, site history, officers’ assessment, consultation responses, committee vote and conditions.

Source: Plota analysis of Lancaster's committee minutes of 11 May 2026.

Documents 55

Statements & assessments 18

PDF consultee response - bng officer Consultee Response p · 4 Dec 2025 View ↗ PDF Email with response from applicant's ecologist - open mosaic habitat Application Amendments p · 26 Nov 2025 View ↗ PDF 60712477 Preliminary ecological appraisal report v04 Application Amendments p · 26 Nov 2025 View ↗ PDF 606436226 Transport statement Supporting Information p · 15 Oct 2025 View ↗ PDF Consultation response - biodiversity officer Consultee Response p · 9 Oct 2025 View ↗ PDF consultee response - arboricultural officer Consultee Response p · 7 Oct 2025 View ↗ PDF Arboricultural impact assessment Supporting Information p · 26 Sept 2025 View ↗ PDF Drainage strategy report Supporting Information p · 26 Sept 2025 View ↗ PDF Ecological impact assessment Supporting Information p · 26 Sept 2025 View ↗ PDF Energy statement Supporting Information p · 26 Sept 2025 View ↗ PDF Flood risk assessment Supporting Information p · 26 Sept 2025 View ↗ PDF Cultural heritage desk based assessment Supporting Information p · 26 Sept 2025 View ↗ PDF Hydrogeological assessment Supporting Information p · 26 Sept 2025 View ↗ PDF Superseded: preliminary ecological appraisal report Supporting Information p · 26 Sept 2025 View ↗ PDF Noise impact assessment Supporting Information p · 26 Sept 2025 View ↗ PDF Biodiversity net gain assessment Supporting Information p · 26 Sept 2025 View ↗ PDF Bng metrix Supporting Information p · 26 Sept 2025 View ↗ PDF Planning, design, access, utilities, mineral safeguarding and sustainable draina Supporting Information p · 26 Sept 2025 View ↗

Consultation & comments 25

PDF consultee response - natural england Consultee Response p · 16 Apr 2026 View ↗ PDF consultee response - natural england Consultee Response p · 9 Feb 2026 View ↗ PDF Middleton aecom response Application Amendments p · 22 Jan 2026 View ↗ PDF consultee response - county public rights of way officer Consultee Response p · 14 Jan 2026 View ↗ PDF consultee response - county resilience team Consultee Response p · 23 Dec 2025 View ↗ PDF consultee response - natural england Consultee Response p · 3 Dec 2025 View ↗ PDF Applicant response to emergency planning Application Amendments p · 7 Nov 2025 View ↗ PDF Cadent gas - no objection Consultee Response p · 31 Oct 2025 View ↗ PDF consultee response - county archaeology Consultee Response p · 30 Oct 2025 View ↗ PDF consultee response - environmental health Consultee Response p · 30 Oct 2025 View ↗ PDF consultee response - natural england Consultee Response p · 29 Oct 2025 View ↗ PDF consultee response - emergency planning Consultee Response p · 27 Oct 2025 View ↗ PDF consultee response - climate change Consultee Response p · 21 Oct 2025 View ↗ PDF Consultee response - llfa response Consultee Response p · 16 Oct 2025 View ↗ PDF Consultee response - middleton parish council response Consultee Response p · 16 Oct 2025 View ↗ PDF Consultee response - environmental health Consultee Response p · 16 Oct 2025 View ↗ PDF county highways response Consultee Response p · 16 Oct 2025 View ↗ PDF Consultee response - environment agency Consultee Response p · 15 Oct 2025 View ↗ PDF consultee response - natural england Consultee Response p · 9 Oct 2025 View ↗ PDF consultee response - fire safety officer Consultee Response p · 2 Oct 2025 View ↗ PDF Cadent gas - holding objection Consultee Response p · 30 Sept 2025 View ↗ PDF Electricity nw - advice Consultee Response p · 30 Sept 2025 View ↗ PDF Esp utilities group - not affecting apparatus Consultee Response p · 30 Sept 2025 View ↗ PDF National grid electricity - high risk response Consultee Response p · 30 Sept 2025 View ↗ PDF Orsted Consultee Response p · 30 Sept 2025 View ↗

All documents on the council site ↗

Associated applications 2

Site constraints 8

In flood zones plus climate change
Inside the extent flood zones 2 and 3 could reach with climate change: the Central allowance for the 2080s on rivers, the Upper End allowance for sea level rise to 2125. From the sea. Defences are not counted.
The Environment Agency flood map for planning. Councils use it to decide when a flood risk assessment and the sequential test are needed. It is indicative and does not show whether a particular property will flood.
Flood map ↗
Agricultural land, grade 5
Very poor quality farmland, not best and most versatile. Source: the Predictive Agricultural Land Classification Map (Defra and Natural England, 2025; the Welsh Government's Predictive ALC Map 2 in Wales), a model rather than a site survey. Natural England's Provisional ALC map (1:250,000, 1970s), which most planning maps still show, had this area as grade 3. The predicted grade is Defra's current estimate; only a site survey settles it.
Where development of farmland is needed, policy prefers poorer land over the best and most versatile (grades 1, 2 and 3a). Three sources: Natural England's post-1988 field surveys, which are definitive where they exist; the Defra predictive map for England (2025) and the Welsh Government predictive map, modelled from the soil map with 3a and 3b split; and the 1970s provisional map, which planners and other services still show, coarser and with grade 3 undivided. Where the provisional and predicted grades disagree, treat the predicted grade as the current estimate and expect an application to carry its own survey.
National infrastructure project 30 m away: Walney Extension Offshore Wind Farm
The site is 30 m from the project boundary. Generating station, decided. The project page says whether consent was granted.
Nationally significant infrastructure projects (power stations, electricity lines, pipelines, major roads and railways, harbours, airports and reservoirs) are consented by a Secretary of State under the Planning Act 2008, after an examination by the Planning Inspectorate, rather than by the council. The boundary is the one the Inspectorate consults on and can change as the scheme does. Projects are shown within 2 km of the site.
Planning Inspectorate project page ↗
Habitat network: Other Priority Habitats - NEZ
Where habitat is joined up enough to work as a network. Context, not a constraint on its own.
Also on the record
SSSI 244 m away: Heysham Moss SSSI; Radon affected area, class 2; Nature improvement area: Morecambe Bay Limestones and Wetlands; Priority habitat 20 m away: Coastal and floodplain grazing marsh.
Not affected
Outside flood zones 2 and 3 · Not green belt · No listed building at the site

Checked on 2 November 2026. Historic England, the Environment Agency, Natural England, the Planning Inspectorate, the British Geological Survey and UK Health Security Agency (radon, contains BGS materials © UKRI) and council datasets, Open Government Licence. A boundary can run through a site and the council holds the definitive record: confirm with the council before relying on this.

Work with planning data?

Every application in Lancaster - and every UK council - as a live feed, an API, or a bulk CSV export.

About Plota's data service

Important details

Council
Lancaster
Application type
Full Application
Received
26 Sept 2025
Validated
26 Sept 2025
Ward
Heysham South Ward
Parish
Heysham Neighbourhood Council
Case officer
Show
Target decision
15 May 2026
Decision
Application Permitted
Decision date
14 May 2026
Decision level
Delegated Decision
Applicant
Show

How this decision compares

Decided in 230 days from validation, 174 days slower than Lancaster's median of 56 for full applications. Approved, as 87% of full applications here are.

64%decided within 8 weeks
87%approved
451decided in the last year

Plota live figures for full applications decided by Lancaster in the last twelve months, from validation. Lancaster decision record →

Public comments

1comment received
1 neutral

Last counted 12 Oct 2026

Read the comments on the council site ↗

Consultation & key dates

Alt. reference
PP-13968343
Planning Portal ref
PP-13968343
Consultation
8 Apr 2026
Comments by
22 Apr 2026
Site or press notice
29 Sept 2025
Committee
11 May 2026
Statutory expiry
26 Dec 2025
Env. assessment
No
Lancaster
Planning Authority Score
5/10
Average
#147 of 296 councils
Relevant to this application:
Householder decisions

Lancaster is faster than most councils at deciding householder applications, ranking #84 out of 296. Householder applications are slightly less likely to be approved here (87%) than the national average (90%).

Faster than most councils
for householder decisions
These figures are council-wide context, not a prediction for this application. View full council performance
Lancaster decision statistics
Based on MHCLG data, the year to March 2026
83%
Overall approval rate
Below avg (87%) #237 of 296
87%
Householder approved
Below avg (90%) #231 of 296
74%
Decided in 8 weeks
Above avg (63%) #84 of 296
38%
Extended time limit
Below avg (41%) #130 of 296
71%
Minor dwellings approved
45 decided (1-9 homes)
63%
Major dwellings approved
16 decided (10+ homes)
63%
Change of use approved
48 decided
717
Total decisions
122 refused in the year to March 2026